Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
12th Edition
ISBN: 9780134855424
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 11P
Consider a project to produce custom door moldings for GMC Acadia crossover vehicles, described in Table 7.4.
- If you start the project immediately, when will it be finished?
- You are interested iii completing your project as soon as possible. You have only one option. Suppose you could assign Employee A, currently assigned to activity G, to help Employee B, currently assigned to activity F. Each week that Employee A helps Employee B will result in activity G increasing its time by 1 week and activity F reducing its time by 1 week. How many weeks should Employee A work on activity F?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
b) Assuming that each task is started as soon as possible, construct the corresponding resource loading diagram for the project. c) How would you rearrange the timing of project activities to reduce the fluctuation in resource demand? Assume that the overall project duration cannot be extended. Remember that the specified precedence relationships must be maintained. d) If there are only 20 workers available for the project, how would you assign workers to tasks to ensure that the project can be completed without violating the resource limit? In this case, the project duration may be extended if necessary (but without violating precedence relationships). e) Given the results from (c) and (d) above, what recommendations would you make to senior management regarding the staffing of this project, and why?
Consider a project to produce custom door moldingsfor GMC Acadia cross-over vehicles, described inTable 7.4.
a. If you start the project immediately, when will it be finished?b. You are interested in completing your project as soon aspossible. You have only one option. Suppose you couldassign Employee A, currently assigned to activity G, tohelp Employee B, currently assigned to activity F. Eachweek that Employee A helps Employee B will result inactivity G increasing its time by one week and activity Freducing its time by one week. How many weeks shouldEmployee A work on activity F?
The company decided that the project in the previous problem had to be expedite in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.
Activity
Duration (Days)
Expedited Time (Days)
Normal Direct Cost ($)
Expedited Direct Cost ($)
A
32
26
200
500
B
21
20
300
375
C
30
30
200
200
D
45
40
200
800
E
26
20
700
1,360
F
28
24
1,000
1,160
G
20
18
400
550
What is the optimal time to complete the project?
What is the optimal project cost?
Chapter 7 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Project 1-3: Creating a Project Schedule for Hiring a New EmployeeIn this project, you will create a project schedule for the process of hiring a new employee for your department. GET READY. OPEN a new blank project schedule. Set the project start date to be October 21, 2019.Enter the following tasks and durations:Task DurationWrite job description 2dNotify departmental recruiter 1dPost job internally 5dPost job externally 5dCollect résumés 10dReview résumés 5dSet up interviews 3dConduct interviews 8dSelect candidate 1dMake offer milestoneAssign a finish-to-start relationship to all the tasks.Change the relationship between tasks 3 and 4 to a start-to-start relationship.Auto-fit all the columns and rows.Change all tasks to the Automatically Scheduled mode.Use the statistics button on the Project Information dialog box to determine the current project duration.SAVE the project schedule in the solutions folder for this lesson as Hiring Employee xxd where…arrow_forwardThe information below shows the order in which the activities of a project occur alongwith the time taken for each activity:Q must follow PR must follow PS must follow PT must follow SU must follow S and TV must follow S and TW must follow P, Q, R, S, T , U, VP takes 8 minutesQ takes 6 minutesR takes 6 minutesS takes 3 minutesT takes 3 minutesU takes 7 minutesV takes 7 minutesW takes 18 minutesConstruct an activity network to represent the project information given. Include the earlystart, early finish, late start and late finish times for EACH activity. Hence, determine thecritical path for the project.arrow_forwardConsider the AON graph of a project shown in Figure 19.17. Which of the following statements is correct? a. A1 is a predecessor activity to A2. b. A2 is a successor activity of A1. c. A3 and A5 can be carried out in parallel. d. All of these statements are correct. (PICTURE ADDED)arrow_forward
- Assume that the activities in Problem 3.11 have the following costs to shorten: A, $300/week; B, $100/week; C, $200/ week; E, $100/week; and F, $400/week. Assume also that you can crash an activity down to 0 weeks in duration and that every week you can shorten the project is worth $250 to you. What activities would you crash? What is the total crashing cost? Note: The attached photos is the activities in problem 3.11.arrow_forwardA potential conflict on projects is work scope; conflict can arise from differences of opinion on all the following except A. how much work should be done. B. how the work should be done. C. at what level of quality the work should be done. D. the cost of the work to be done.arrow_forwardYou may need to use the appropriate technology to answer this question. Use the following network with activities and times estimated in days to answer the questions. A project network with 13 activities and 17 directed arcs is shown. Activity Start is connected to activity A, to activity B, and to activity C. Activity A is connected to activity D, to activity E, and to activity F. Activity B is connected to activity F. Activity C is connected to activity G and to activity H. Activity D is connected to activity K. Activity E is connected to activity I. Activity F is connected to activity I. Activity G is connected to activity I. Activity H is connected to activity J. Activity I is connected to activity K. Activity J is connected to activity K. Activity K is connected to activity Finish. Activity Finish has no arcs directed to other activities. Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 5 6 9 D 5 12 14 E 3 4 5 F 9 10 13 G 4 6 8 H 3 6 8 I 5 7 12 J 11 12 13 K 1 3 4…arrow_forward
- You own a software development company that has been hired to build an online classified ads website (refer to Craigslist.com as an example). Managing Systems Projects Review “What Is a Project Triangle?” . Consider the scenario outlined above, and in your own words: provide a hypothetical example of changes in cost impacting scope & time. provide a hypothetical example of changes in scope impacting time & cost. Provide a hypothetical example of changes in time impacting cost & scope. Identify and list ten different information systems tasks that will need to be completed for this project. Estimate the duration for each of these tasks (in days). Identify any task dependencies. Create a Gantt chart that represents these project tasks, durations, and dependencies. Illustrate the critical path in your Gantt chart. Explain why the critical path is important to project managers and how they use it.arrow_forwardI need a detailed explanation and assistance on how to solve this problem: The company decided that the project in the previous problem has to be expedited in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting the project reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below. Activity Normal Time (days) Expedited Time (days) Normal Cost ($) Expedited Cost ($) A 32 26 200 500 B 21 20 300 375 C 30 30 200 200 D 45 40 200 800 E 26 20 700 1,360 F 28 24 1,000 1,160 G 20 18 400 550 From this table you can compute the direct cost incurred by expediting an…arrow_forwardA project consists of three tasks: A, B, and C. Task A is known to take five days forsure. Tasks B and C are each dependent on A. B takes five days. C takes seven dayswith a probability of 0.5 and three days with a probability of 0.5. What is the expectedcompletion time of the project?a. 8 daysb. 10 daysc. 11 daysd. 12 daysarrow_forward
- Briefly describe 'Parkinson's Law' and 'Murphy's Law'. One sentence each. Then briefly in 3-6 sentences, please explain why these 'Laws' are relevant in project planning in regard to schedule, risk, cost, and resources (especially the 'people resource')..arrow_forwardI need assistance with the following questions in: Project Scheduling. This is a follow up to a question answered earlier. Question 1) was answered. 1) A company decides to plan a project, with activities, precedences and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F 2) The company decided that the project in the previous problem has to be expedited in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting the project reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.…arrow_forward27. Consider a project with six activities: G, B, C, D, E, and F. Assume G and F can be started as soon as the project is kicked off. B can start as soon as G is completed, C can start as soon as both G and F are completed. D will start as soon as both B and C are completed. E will start as soon as D finishes. Which of the following choices is the correct collection of immediate precedence relationships in the project network? G--> B, F--> C, B --> D, C--> E, D--> E, F--> D G--> B, G--> C, B --> D, C--> D, D--> E, F--> C G--> B, G--> C, B --> D, C--> D, D--> E, D--> F None of choices G--> B, F--> C, B --> D, C--> D, D--> E, F--> D G--> B, G--> C, B --> D, C--> D, D--> E, D--> Farrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY