Summary Introduction
Interpretation:The effect of increasing activity A by 1 week after becoming critical is to be determined.
Concept Introduction: Critical path is a method used to evaluate the project. It is used when the activity times are deterministic. It is the longest path in the network. It defines the minimum time required for completion of the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Calculate, ES, EF, LS and LF for each activity, and highlight the critical path indicating the length of this project.
A project has the following activities, with specified precedents and expected durations (in hours). How much slack does Activity E have?
The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8,respectively. What is the critical path?a. A1, A2, A3, A4, A8b. A1, A2, A3, A6, A7, A8c. A1, A2, A5, A7, A8d. None of these options is the critical path.
Chapter 7 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Consider the following information for a project...Ch. 7 - Consider the following data for a project to...
Ch. 7 - Paul Silver, owner of Sculptures International,...Ch. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Table 7.8 contains data for the installation of...Ch. 7 - The diagram in Figure 7.12 was developed for the...Ch. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - You are the project manager of the software...Ch. 7 - Jordanne King, the project manager for Webjets...Ch. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?arrow_forwardOp2. Consider a project with the following activity list. with one day delay in the start of activity C, the duration of the project will be _____________. Choose one of the following options for the question above.arrow_forwardWhat is the Ealiest and Latest start for Activity I and Latest finish for Activity G?arrow_forward
- 11-17 The following are the activity times for the project in Problem 11-16. Find the earliest, latest, and slack times for each activity. Then find the critical path. ACTIVITY TIME (DAYS) A 3 B 7 C 4 D 2 E 5 F 6 G 3 11-16.arrow_forwardExplain the meaning of the term "project scheduling." While making preliminary estimates of schedules, what considerations need to be given priority?arrow_forwardYou are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…arrow_forward
- How has slack changed for each activity? Has the risk of being late changed? How?arrow_forwardSchedule the following activities using CPM: Activity Immediate Predecessor Time (weeks) A - 1 B A 4 C A 3 D B 2 E C,D 5 F D 2 G F 2 H E,G 3 Part (a) Draw the network : Part (b) What is the critical path? Part (c) How many weeks will it take to complete the project? Part (d) What activities have slack, and how much?arrow_forwardINSTRUCTIONS: Draw the AON network for Exercise 14 (pg ASSIGNMENT 200 & 201). Complete the forward and backward passes, calculate total slack for each activity, identify the critical path, identify the total project length (or how long it will take to complete the project) based on days, calculate free slack for appropriate activities, and create the Gantt chart. When creating the Gantt chart, you must include slack into the schedule.arrow_forward
- The following are the activity times. Find the earliest, latest. and slack times for each activity. Then find the critical path.arrow_forward(PERT-CPM) A small project consisting of eight activities has the following characteristics: -Draw the PERT network for the project. -Prepare the activity schedule for the project showing (Project duration, ES, EF, LS, LF, FLOAT/SLACK). -Determine the critical path.arrow_forwardThere is a running project in the company that you work for, which has the following activities: Activity Predecessors Duration A - 4 B A 4 C A 7 D B 6 E C 4 F D, E 2 Draw a network diagram for the above activities. Identify the critical path. Show the formula for calculating the EF and ES. “You must mention how did you know that this is your critical path”arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY