CNCT ACC CORPORATE FINANCE
12th Edition
ISBN: 9781264604081
Author: Ross
Publisher: MCGRAW-HILL HIGHER EDUCATION
expand_more
expand_more
format_list_bulleted
Question
Chapter 7, Problem 12QAP
Summary Introduction
To determine: The sensitivity analysis if quantity sold is changed on operating cash flows.
Introduction: Sensitivity analysis is the method where the sensitivity of the project’s cash flow is checked with the changes in one variable. For instance, if the quantity sold is increasing or decreasing then the impact on the cash flows is analyzed.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You are considering the following project. What is the NPV of the project? WACC of the project: 0.10 Revenue growth rate: 0.05 Tax rate: 0.40 Revenue for year 1: 13,000 Fixed costs for year 1: 3,000 variable costs (% of revenue): 0.30 project life: 3 years Economic life of equipment: 3 years Cost of equipment: 20,000 Salvage value of equipment: 4,000 Initial investment in net working capital: 2,000
Plot a sensitivity graph for annual worth versus initial cost, annual revenue, and salvage value for the data below. Vary only one
parameter at a time, each within the range of -20% to +20%. MARR is 3%/year. Project life is 4 years. Based on your graph, which
parameter shows the MOST sensitivity? Initial Cost: $120,000- Annual Revenue: $25,000 - Salvage Value: $35,000
O Cannot be determined
O Annual Revenue
O Initial Cost
O Salvage Value
To illustrate how a sensitivity analysis might be performed, we consider once more the SMP investment: a $500,000 initial investment, annual savings of $92,500 for a 10-year period, and a salvage value of $50,000. As before, a 10% MARR applies. Let’s consider how sensitive the annual worth for the investment is to errors in estimating the initial investment, the annual savings, the salvage value, the investment’s duration, and the MARR. Specifically, for an error range of ±50% for each parameter, what is the impact on AW?
Chapter 7 Solutions
CNCT ACC CORPORATE FINANCE
Ch. 7 - Forecasting Risk What is forecasting risk? In...Ch. 7 - Sensitivity Analysis and Scenario Analysis What is...Ch. 7 - Prob. 3CQCh. 7 - Break-Even Point As a shareholder of a firm that...Ch. 7 - Prob. 5CQCh. 7 - Real Options Why does traditional NPV analysis...Ch. 7 - Real Options The Mango Republic has just...Ch. 7 - Prob. 8CQCh. 7 - Prob. 9CQCh. 7 - Project Analysis You are discussing a project...
Ch. 7 - Sensitivity Analysis and Break-Even Point We are...Ch. 7 - Prob. 2QAPCh. 7 - Prob. 3QAPCh. 7 - Prob. 4QAPCh. 7 - Prob. 5QAPCh. 7 - Prob. 6QAPCh. 7 - Prob. 7QAPCh. 7 - Prob. 8QAPCh. 7 - Prob. 9QAPCh. 7 - Prob. 10QAPCh. 7 - Prob. 11QAPCh. 7 - Prob. 12QAPCh. 7 - Prob. 13QAPCh. 7 - Prob. 14QAPCh. 7 - Prob. 15QAPCh. 7 - Prob. 16QAPCh. 7 - Prob. 17QAPCh. 7 - Prob. 18QAPCh. 7 - Prob. 19QAPCh. 7 - Prob. 20QAPCh. 7 - Prob. 21QAPCh. 7 - Prob. 22QAPCh. 7 - Prob. 23QAPCh. 7 - Prob. 24QAPCh. 7 - Prob. 25QAPCh. 7 - Prob. 26QAPCh. 7 - Prob. 28QAPCh. 7 - Prob. 29QAPCh. 7 - Prob. 30QAP
Knowledge Booster
Similar questions
- Please plot a sensitivity graph for annual worth versus initial cost, annual revenue, and salvage value, varying only one parameter at a time, each within the range of +/− 50%arrow_forwardDetermine the associated risk measure in this equipment investment in terms of standard deviation. Because of the uncertainty of technology being used in this equipment, it has not been possible to get the initial cost accurately. The annual benefit, however, is estimated to be $20,000 with a possible equipment life of 5 years. The salvage value is expected to be 10% of the initial cost. MARR =8% First Cost, $ $50,000 $80,000 $100,000 $125,000 Probability 0.25 0.35 0.30 0.10arrow_forwardBased on the image , Calculate the ARR for XYZ Corporation. Assume depreciation is calculated on the straight-linemethod and that the project has a scrap value of R5000.arrow_forward
- Average rate of return Determine the average rate of return for a project that is estimated to yield total income of 936,000 over eight years, has a cost of 1,200,000, and has a 100,000 residual value.arrow_forwardRoberts Company is considering an investment in equipment that is capable of producing more efficiently than the current technology. The outlay required is 2,293,200. The equipment is expected to last five years and will have no salvage value. The expected cash flows associated with the project are as follows: Required: 1. Compute the projects payback period. 2. Compute the projects accounting rate of return. 3. Compute the projects net present value, assuming a required rate of return of 10 percent. 4. Compute the projects internal rate of return.arrow_forwardWhy straight-line depreciation method is used instead of the sinking fund depreciation method?arrow_forward
- Indicate how the internal rate of return is calculated using the factor. (answer is in % format) Please don't give solution in an image format thank uarrow_forwardThe most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: $ 50 $ 30 $ 490,000 48,000 units per year However, you recognize that some of these estimates are subject to error. Suppose each variable turns out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $2.3 million, which will be depreciated straight-line over the project life to a final value of zero. The firm's tax rate is 21%, and the required rate of return is 10%. a. NPV b. NPV a. What is project's NPV in the best-case scenario, that is, assuming all variables take on the best possible value? b. What is project's NPV in the worst-case scenario? Note: For all the requirements, a negative amount should be indicated by a minus sign. Enter your answers in dollars, not in millions. Do not round intermediate calculations. Round your answers to the nearest dollar amount. 4arrow_forwardThe below information relates to a prospective project that is under evaluation of Draw plc. Initial investment outlay MVR 1 000 000 Net profit Year 1 MVR 450 000 Year 2 MVR 400 000 Year 3 MVR 350 000 Year 4 MVR 300 000 It was estimated that the project will have a residual value of MVR 200 000 after useful life of 4 years. a) Calculate Accounting Rate of Return (ARR), clearly showing the workings. b) State one main disadvantage of using ARR as an investment appraisal techiiīque.arrow_forward
- Assuming monetary benefits of a construction project at $50,000 per year, one-time costs (initial investment) of $15,000, recurring costs of $35,000 per year, a discount rate of 10 per cent, and a 4-year time horizon, calculate the net present value (NPV) of an information system's costs and benefits. Calculate the overall return on investment (ROI) of the project. During which year does break-even occur? Use the NPV template provided (modify to suit your answer) and clearly display the NPV, ROI, and year in which payback occurs. Write a paragraph explaining whether you would recommend investing in this project based on your financial analysis. Explain your answer referring to the NPV, ROI and payback for this project. Discount Rate (10%) Year 0 - 1.0000 Year 1 - .9091 Year 2 - .8264 Year 3 - .7513 Year 4 - .6830arrow_forwardDetermine which equipment should be favored, comparing the net present values of the two proposals and assuming a minimum rate of return of 15%. Use the present value table appearing above. Processing Mill Electric Shovel EE Present value of net cash flow total Less amount to be invested Net present value Which project should be favored?arrow_forwardThe most likely outcomes for a particular project are estimated as follows: Unit price: Variable cost: Fixed cost: Expected sales: 50 24 30 $370,000 36,000 units per year However, you recognize that some of these estimates are subject to error. Suppose that each variable may turn out to be either 10% higher or 10% lower than the initial estimate. The project will last for 10 years and requires an initial investment of $1.4 million, which will be depreclated straight-line over the project life to a final value of zero. The firm's tax rate is 21% and the required rate of return is 14%. (For all the requirements, a negative amount should be indicated by a minus sign. Enter your answer in dollars not in millions. Do not round intermediate calculations. Round your answer to the nearest dollar amount.) a. What is project NPV in the best-case scenario, that is, assuming all variables take on the best possible value? b. What is project NPV in the worst-case scenario?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub