The director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administrative assistant identified the various activities that must be done and their relationships to each other, as shown in Table 7.13.
Because of the uncertainty in planning the new course, the assistant also has supplied the following time estimates for each activity.
The director wants to conduct the seminar 47 working days from now. What is the probability that everything will be ready in time?
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
OPERATIONS MANAGEMENT LL PACKAGE
Additional Business Textbook Solutions
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Business in Action (8th Edition)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Operations Management
Principles Of Operations Management
- You may need to use the appropriate technology to answer this question. Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 (a) Draw a project network. A project network with 11 activities and 13 directed arcs is shown. Activity Start is connected to activity A. Activity A…arrow_forwardPlanning the next semester's course schedule. The optimal schedule for the whole class may be calculated with the help of an algorithm after students enter their desired course load. The school has determined that a perfect schedule cannot be created in a reasonable length of time. To save time, the team has elected to use a less complex approach that nonetheless produces a workable, if not perfect, strategy. Which overarching principle may be seen most clearly in this decision?arrow_forwardSarah was recently hired to work as a secretary, and it is after work hours. Herson, John, needs some copies for a school project and arrives at the office. Theson has brought his own paper and needs 100 copies for his class project. If Johndoesn’t bring the copies to class tomorrow then he will fail the project. The copyshops are all closed. There is no one else in the office. There is basically nooversight about copies she makes since she often does special projects for theboss. What should Sarah do?arrow_forward
- please answer 5 questions below, my deadline is coming in tomorrow Information are all in 2 picturesarrow_forwardPlan that establishes a required method of handling future activities is called?arrow_forwardThe mowry machine shop still has five jobs to be processed as of 8A.M today (day 29) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in order of arrival: Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 12 4 10 B 7 3 24 C 5 10 16 D 3 8 7 E 1 4 13 Develope serpate schedules by using the FCF and EDS rules. Using FCF, the order is Using EDS, the order is The average flow time and average days past due are. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…arrow_forward3- For the following test marketing project at week 6:a. Ignore the far right “% Complete” column and using the 50–50 percent completion rule for PV and EV, calculate the cost, schedule, and time variances. Also calculate the CPI, SPI, CSI, and the ETC and EAC. b. Repeat the calculations in a, but now using the “% Complete” column. Assume that the PV values are based on time proportionality but the “% Complete” values for EV are from the workers actually doing the tasks.arrow_forwardHumber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…arrow_forward
- Job Costing Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead ratebased on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct laborhours are 95,000 and estimated factory overhead is $617,500. The following information is for Septemberof the current year. Job A was completed during September, and Job B was started but not finished.[LO 4-3, 4-4, 4-5]September 1, InventoriesMaterials Inventory $ 7,500Work-in-Process Inventory (All Job A) 31,200Finished Goods Inventory 67,000Material purchases 104,000Direct materials requisitionedJob A 65,000Job B 33,500Direct labor hoursJob A 4,200Job B 3,500Labor costs incurredDirect labor ($8.50/hour) 65,450Indirect labor 13,500Supervisory salaries 6,000Rental costsFactory 7,000Administrative offices 1,800Total equipment depreciation costsFactory 7,500Administrative offices 1,600Indirect materials used 12,000Required1. What is the total cost of Job A?2. What is the total…arrow_forwardIf the time remaining to complete a job is 10 days and the lead time remaining is 12 days, whatis the critical ratio? Is the order ahead of schedule, on schedule, or behind schedule?arrow_forwardActivities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 1 The latest finish time for activity H A. is 11. B. is 14. C.is 18 D.annot be determined. ( don't hand writing solution)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.