OPERATIONS MANAGEMENT LL PACKAGE
11th Edition
ISBN: 9781323592632
Author: KRAJEWSKI
Publisher: Pearson Custom Publishing
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 2P
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel.
- Draw the network diagram for this project.
- Determine the critical path and project duration.
- Calculate the slack for each activity.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Construct this problem. Draw a network diagram, determine the early start, early finish, late start, late finish, and slack times for each activity (table), determine how long the project will take, and which activities are on the critical path.
The following is the data available for a project:
Activity
Predecessor
Expected Duration (Days)
A
-
12
B
A
9
C
B,E
3
D
-
10
E
D
6
F
E
3
G
-
2
H
G
9
I
E,H
2
Expected duration for the completion of the project. Calculate earliest and latest start and finish times for each activity.
Draw the network diagram for the project and determine the critical path
Ken Johnston, the data processing manager for Stanley Morgan Bank, is planning a project to install a new management information system. He is ready to start the project, and wishes to finish in 20 weeks. After identifying the 14 separate activities needed to carry out this project, as well as their precedence relationships and estimated durations (in weeks), Ken has constructed the following project network:
1. Create the network diagram for the project highlighting the critical path.
2. Identify the tasks in the critical path.
3. Find the earliest start and earliest finish, latest start, latest finish, and slack for each activity. Will Ken be able to
meet his deadline if no delays occur?
4. Use the information generated to determine the following:
a. What would be the duration of the project if Activity-I takes 2 extra weeks?
b. What would be the duration of the project if Activity-H takes 2 extra weeks?
c. What would be the duration of the project if Activity-J takes 2 extra weeks?
Chapter 7 Solutions
OPERATIONS MANAGEMENT LL PACKAGE
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7P
Ch. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
What is precedent, and how does it affect common law?
Business in Action
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- . Given the following network with activity times in weeks, determine the earliest start and finish times, latest start and finish times, and slack for each activity. Indicate the critical path and the project duration. photo attached- Calculate and insert ALL missing Earliest Start or Earliest Finish at each Activity. Calculate and insert ALL missing Latest Start and Latest Finish at each Activity. Calculate missing Slack at Every Activity on the network Diagram. List of all possible paths & Total Slacks from Start to finish for each path. *Which activities are on the critical path? What is the total slack along the critical path.arrow_forwardConstruct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:arrow_forwardThe activities of a project, their normal and shortest completion times in days, their respective completion costs in euros, and the constraints on their execution sequence are presented in the table below. Questions: A) To build the network that graphically illustrates the project. B) To find the shortest and slowest start and end times. C) Find the critical path and calculate the total cost. D) To consider the case of reducing the total duration of the project by 1 day at the lowest possible cost.arrow_forward
- Construct a network for the project whose activities and predecessor relationship is given below. Determine also the critical Path.arrow_forwardOffice Automation, has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be ac- accomplished to complete the new office-system project. Information about the activities is shown below where times are in weeks and costs are in thousands of dollars. NOTE: The crashing cost given in the last (seventh) column of the table below is the total cost to finish an activity by its minimum time given in the fifth column.arrow_forwardDraw the network and identify the critical path of following data and total slack time in the network. Also calculate the earliest-latest starting and finishing times for each activity and re-plan the above mentioned network to complete the project in less time.arrow_forward
- You have to manage a project with activities and their respective durations as listed in the table below. Draw a network diagram, Calculate the forward, backward pass, total slack, free slack and identify the critical path.arrow_forwardCanesta Company is working on a project with the following network: a) Determine the earliest and latest activity times and slack for each activity. b) Determine the duration of the project and the critical path.arrow_forwardA group of developers is building a new shopping center. A consultant for the developers has constructed the following project network and assigned activity times, in weeks. Determine the earliest and latest activity times, activity slack, critical path, and duration for the project.arrow_forward
- Using the activity table below, construct a CPM/PERT network noting the activity numbers and durations. Identify the critical path through the network, determine the project completion time, and determine the earliest and latest end dates for each node. Activity Predecessor Time (months) 1 - 10 2 - 1 3 - 6 4 2 3 5 1,3,4 5 6 3 8 7 5,6 2arrow_forwardPaul Silver, owner of Sculptures International, just initiated a new art project. The following data are available for the project: a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardPaul Silver, owner of Sculptures International, just initiated a new art project. The following data are available for the project:a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY