Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern is the hiring of a manager and several associates who are animal lovers. She also has to coordinate the renovation of a building that was previously owned by a chic clothing store. Kramer has gathered the data shown in Table 7.14.
- How long is the project expected to take?
- Suppose that Kramer has a personal goal of completing the project in 14 weeks. What is the probability that it will happen this quickly?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern is the hiring of a manager and several associates who are animal lovers. She also has to coordinate the renovation of a building that was previously owned by a chic clothing store. Kramer has gathered the data shown in Table.a. How long is the project expected to take?b. Suppose that Kramer has a personal goal of completing the project in 14 weeks. What is the probability that it will happen this quickly?
Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern is the hiring of a manager and several associates who are animal lovers. She also has to coordinate the renovation of a building that was previously owned by a chic clothing store. Kramer has gathered the data shown in Table 7.14.a. How long is the project expected to take?b. Suppose that Kramer has a personal goal of completing the project in 14 weeks. What is the probability that it will happen this quickly?
Gabrielle Kramer, owner of Pet Paradise, is opening a newstore in Columbus, Ohio. Her major concern is the hiringof a manager and several associates who are animal lovers.She also has to coordinate the renovation of a building thatwas previously owned by a chic clothing store. Kramer hasgathered the data shown in Table 7.14.
a. How long is the project expected to take?b. Suppose that Kramer has a personal goal of completingthe project in 14 weeks. What is the probability that it willhappen this quickly?
Chapter 7 Solutions
OPERATIONS MANAGEMENT LL PACKAGE
Ch. 7 - One of your colleagues comments that software is...Ch. 7 - Explain how to determine the slack for each...Ch. 7 - Define risk as it applies to projects. What are...Ch. 7 - Consider the following data for a project to...Ch. 7 - The following information is known about a project...Ch. 7 - A project for improving a billing process has the...Ch. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7P
Ch. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - The following information concerns a project to...Ch. 7 - Consider a project to produce custom door moldings...Ch. 7 - Table 7.5 contains information about au...Ch. 7 - The Advanced Tech Company has a project to design...Ch. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Recently, you were assigned to manage a project to...Ch. 7 - In Solved Problem 2, estimate the probability that...Ch. 7 - The director of continuing education at Bluebird...Ch. 7 - Gabrielle Kramer, owner of Pet Paradise, is...Ch. 7 - The project manager of Good Public Relations...Ch. 7 - Consider the office renovation project data in...Ch. 7 - Activity B and activity K are critical activities....Ch. 7 - Prob. 2AMECh. 7 - Prob. 3AMECh. 7 - Prob. 4AMECh. 7 - Prob. 5AMECh. 7 - Assess the four categories of a risk-management...Ch. 7 - Prob. 2VCCh. 7 - Assume you are Denise Tower and have...Ch. 7 - Prob. 1CCh. 7 - Prob. 2CCh. 7 - Prob. 3CCh. 7 - Prob. 4C
Additional Business Textbook Solutions
Find more solutions based on key concepts
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeksarrow_forwardDoug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project: A. Draw a project network. B. What are the critical activities and what is the expected project completion time? C. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?arrow_forwardA small software development project at Krishna Dhir's firm has five major activities. The times are estimated and provided in the table below. ACTIVITY IMMEDIATE PREDECESSOR a m b A − 1 4 13 B − 4 7 10 C A 2 8 14 D B 3 6 15 E C 3 3 3 Part 2 a) Find the expected completion time for this project. The expected completion time for this project is enter your response here (enter your response as a whole number). Part 3 b) What variance value would be used to find probabilities of…arrow_forward
- A project has the activity duration and cost information indicated in the table where all times are in weeks. What is the total cost for completing this project in 50 days? Activity Predecessor Normal Time Normal Cost Crash Time Crash Cost A -- 8 $12,000 5 $21,000 B A 12 $20,000 9 $30,000 C A 15 $24,000 10 $60,000 D B 3 $10,000 2 $15,000 E C 9 $17,000 6 $34,000 F E 7 $5,000 6 $6,000 G D 8 $14,000 6 $20,000 H A 12 $22,000 10 $30,000 I H 6 $50,000 5 $55,000 J F, G, I 11 $33,000 9 $50,000arrow_forwardExpected length of a project is 37.16 days and the variance of its length is 6.14 days. What is the probability that the project is completed within 40 days?arrow_forwardA project consists of five activities listed below. The project network is shown for the activities. The critical path is B-C-E and the expected completion time is 8. Optimistic Most Probable Pessimistic Activity Time (hr) Time (hr) Time (hr) A Floor sanding 3 4 5 B Paint mixing 0.5 1 1.5 C Ceiling painting 1 5.5 7 D Wall painting 1 2 9 E Floor buffing 1 2 3 What is the probability that the project can be completed within 9 hr.?arrow_forward
- You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 3 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 5 H E, F…arrow_forwardConsider the office renovation project data in Table 7.16. A“zero” time estimate means that the activity could take a verysmall amount of time and should be treated as a numericzero in the analysis.a. Based on the critical path, find the probability ofcompleting the office renovation project by 39 days.b. Find the date by which you would be 90 percent sure ofcompleting the project.arrow_forwardRecently, you were assigned to manage a project to remodelthe seminar room for your company. You have constructed anetwork diagram depicting the various activities in the project(Figure 7.13). In addition, you have asked your team to estimatethe amount of time that they would expect each of the activitiesto take. Their responses are shown in the following table: a. What is the expected completion time of the project?b. What is the probability of completing the project in 21 days?c. What is the probability of completing the project in 17 days?arrow_forward
- The following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is the probability that the project will be completed 18 weeks before its expected completion date? 2- Draw Normal Curve & Analysis your solution with conclusionarrow_forwardThe following precedence diagram reflects three time estimates in weeks for each activity.Determine:a. The expected completion time for each path and its variance.b. The probability that the project will require more than 49 weeks.c. The probability that the project can be completed in 46 weeks or less.arrow_forwardA project has 7 activities P, Q, R, S, T, U, and V. Three time estimates (optimistic, most-likely, pessimistic) are used for each activity. Write down your answers to all parts of the question in the box given below. Give your answer to 3 decimal places. (Note (a) has of 2 parts and (b) has of 3 parts) For activity Q, these time estimates are as follows: optimistic time = 9, most-likely time = 14, pessimistic time = 20. Write down the average activity time for Q the variance of activity time for Q. The critical path of this project has a mean project time of 44 days and a standard deviation of 5 days. Assume project completion time is normally distributed. Find the probability that the project will be completed in 47 days. Find the probability that the project will take more than 40 days. We want to set a deadline for this project completion. If the probability of meeting this set deadline is 0.88, what will be the deadline for this project.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY