Textbook Question
Book Icon
Chapter 7, Problem 5P

Suppose a work center has a setup plus run time of 30 minutes to make 50 parts. Also assume it takes 10 minutes to move a standard container of 50 parts to the next work center and the demand rate is one part per minute throughout the day.

  1. a. Schedule this situation by drawing a picture of when work center A should be producing and idle and when movements of containers take place from A to B, the using work center.
  2. b. How many standard containers are needed for this part to circulate from the picture in part a?
Blurred answer
Students have asked these similar questions
Suppose a work center has a setup plus run time of 30 minutes to make 50 parts. Also assume it takes 10 minutes to move a standard container of 50 parts to the next work center and the demand rate is one part per minute throughout the day.a. Schedule this situation by drawing a picture of when work center A should be producing and idle and when movements of containers take place from A to B, the using work center.b. How many standard containers are needed for this part to circulate from the picture in part a?c. Use the formula n = DT ÷ C to calculate the number of containers.
Jason Carter works for a producer of soaps that come inpackages of 6 each. His job is to fi ll the packages with soap, andhe is expected to process 30 packages an hour. Th e facility whereJason works uses a kanban production system in which eachcontainer holds 5 packages of soap. It takes 20 minutes to receivethe packages he needs from the previous workstation. How manykanbans are needed for the fi lling process?
3. At Golf Co. product is automated to load golf balls into packaging. On an average day, the equipmentcan load 25 cases per hour, where each case contains 20 boxes and each box contains 12 balls.After maintenance, the machine is loading a little faster so that it takes 0.2 seconds less time to load onegolf ball into a box compared with the normal speed.How many cases per hour can the machine load at this new rate?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY