Textbook Question
Chapter 7, Problem 7.32E
Price and efficiency variances, benchmarking. Nantucket Enterprises manufactures insulated cold beverage cups printed with college and corporate logos, which it distributes nationally in lots of 12 dozen cups. In June 2017, Nantucket produced 5,000 lots of its most popular line of cups, the 24-ounce lidded tumbler, at each of its two plants, which are located in Providence and Amherst. The production manager, Shannon Bryant, asks her assistant, Joel Hudson, to find out the precise per-unit budgeted variable costs at the two plants and the variable costs of a competitor, Beverage Mate, who offers similar-quality tumblers at cheaper prices. Hudson pulls together the following information for each lot:
- 1. What is the budgeted variable cost per lot at the Providence Plant, the Amherst Plant, and at Beverage Mate?
Required
- 2. Using the Beverage Mate data as the standard, calculate the direct materials and direct manufacturing labor price and efficiency variances for the Providence and Amherst plants.
- 3. What advantage does Nantucket get by using Beverage Mate’s benchmark data as standards in calculating its variances? Identify two issues that Bryant should keep in mind in using the Beverage Mate data as the standards.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Price and efficiency variances, benchmarking. Nantucket Enterprises manufactures insulated cold beverage cups printed with college and corporate logos, which it distributes nationally in lots of 12 dozen cups. In June 2017, Nantucket produced 5,000 lots of its most popular line of cups, the 24-ounce lidded tumbler, at each of its two plants, which are located in Providence and Amherst. The production manager, Shannon Bryant, asks her assistant, Joel Hudson, to nd out the precise per-unit budgeted variable costs at the two plants and the variable costs of a competitor, Beverage Mate, who offers similar-quality tumblers at cheaper prices. Hudson pulls together the following information for each lot:
Surrey Bikes, Inc. manufactures double bench bikes for resorts and other vacation properties.
Management now wants the accountants to complete an analysis to compare the budgeted costs to standard costs for 2021.
During the year 2021, the company completed 680 bikes.
Let's discuss changes from budget and standard that occurred during 2021.
Overall, the company was able to increase several efficiencies.
However, the company also experienced some increased costs.
Use this information to complete the CH24 Budet Variances tab; the green section.
Electrical Parts Direct Materials
The purchase price, net of discounts increase by $2.50 per set.
There was also an increase in freight of by $0.25 per set.
Wheel Sets Direct Materials:
The company was able to secure…
Possible causes for price and efficiency variances. You have been invited to interview for an internship with an international food manufacturing company. When you arrive for the interview, you are given the following information related to a ctitious Belgian chocolatier for the month of June. The chocolatier manufactures truffles in 12-piece boxes. The production is labor intensive, and the delicate nature of the chocolate requires a high degree of skill.
Chapter 7 Solutions
COST ACCT
Ch. 7 - What is the relationship between management by...Ch. 7 - What are two possible sources of information a...Ch. 7 - Distinguish between a favorable variance and an...Ch. 7 - What is the key difference between a static budget...Ch. 7 - Why might managers find a flexible-budget analysis...Ch. 7 - Describe the steps in developing a flexible...Ch. 7 - List four reasons for using standard costs.Ch. 7 - How might a manager gain insight into the causes...Ch. 7 - List three causes of a favorable direct materials...Ch. 7 - Describe three reasons for an unfavorable direct...
Ch. 7 - How does variance analysis help in continuous...Ch. 7 - Why might an analyst examining variances in the...Ch. 7 - Prob. 7.13QCh. 7 - When inputs are substitutable, how can the direct...Ch. 7 - Benchmarking against other companies enables a...Ch. 7 - Metal Shelf Companys standard cost for raw...Ch. 7 - All of the following statements regarding...Ch. 7 - Amalgamated Manipulation Manufacturings (AMM)...Ch. 7 - Atlantic Company has a manufacturing facility in...Ch. 7 - Basix Inc. calculates direct manufacturing labor...Ch. 7 - Flexible budget. Sweeney Enterprises manufactures...Ch. 7 - Flexible budget. Bryant Companys budgeted prices...Ch. 7 - Flexible-budget preparation and analysis. Bank...Ch. 7 - Flexible budget, working backward. The Clarkson...Ch. 7 - Flexible-budget and sales volume variances....Ch. 7 - Price and efficiency variances. Sunshine Foods...Ch. 7 - Materials and manufacturing labor variances....Ch. 7 - Direct materials and direct manufacturing labor...Ch. 7 - Price and efficiency variances, journal entries....Ch. 7 - Materials and manufacturing labor variances,...Ch. 7 - Journal entries and T-accounts (continuation of...Ch. 7 - Price and efficiency variances, benchmarking....Ch. 7 - Static and flexible budgets, service sector....Ch. 7 - Flexible budget, direct materials, and direct...Ch. 7 - Variance analysis, nonmanufacturing setting. Joyce...Ch. 7 - Comprehensive variance analysis review. Ellis...Ch. 7 - Possible causes for price and efficiency...Ch. 7 - Material-cost variances, use of variances for...Ch. 7 - Direct manufacturing labor and direct materials...Ch. 7 - Direct materials efficiency, mix, and yield...Ch. 7 - Direct materials and manufacturing labor...Ch. 7 - Direct materials and manufacturing labor...Ch. 7 - Use of materials and manufacturing labor variances...Ch. 7 - Direct manufacturing labor variances: price,...Ch. 7 - Direct-cost and selling price variances. MicroDisk...Ch. 7 - Variances in the service sector. Derek Wilson...Ch. 7 - Prob. 7.47P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Ed Co. manufactures two types of O rings, large and small. Both rings use the same material but require different amounts. Standard materials for both are shown. At the beginning of the month, Edve Co. bought 25,000 feet of rubber for $6.875. The company made 3,000 large O rings and 4,000 small O rings. The company used 14,500 feet of rubber. A. What are the direct materials price variance, the direct materials quantity variance, and the total direct materials cost variance? B. If they bought 10,000 connectors costing $310, what would the direct materials price variance be for the connectors? C. If there was an unfavorable direct materials price variance of $125, how much did they pay per toot for the rubber?arrow_forwardBuenolorl Company produces a well-known cologne. The standard manufacturing cost of the cologne is described by the following standard cost sheet: Management has decided to investigate only those variances that exceed the lesser of 10% of the standard cost for each category or 20,000. During the past quarter, 250,000 four-ounce bottles of cologne were produced. Descriptions of actual activity for the quarter follow: a. A total of 1.35 million ounces of liquids was purchased, mixed, and processed. Evaporation was higher than expected. (No inventories of liquids are maintained.) The price paid per ounce averaged 0.42. b. Exactly 250,000 bottles were used. The price paid for each bottle was 0.048. c. Direct labor hours totaled 48,250, with a total cost of 733,000. Normal production volume for Buenolorl is 250,000 bottles per quarter. The standard overhead rates are computed by using normal volume. All overhead costs are incurred uniformly throughout the year. (Note: Round unit costs to the nearest cent and total amounts to the nearest dollar.) Required: 1. Calculate the upper and lower control limits for materials and labor. 2. Compute the total materials variance, and break it into price and usage variances. Would these variances be investigated? 3. Compute the total labor variance, and break it into rate and efficiency variances. Would these variances be investigated?arrow_forwardThe Chocolate Cow Ice Cream Company has grown substantially recently, and management now feels the need to develop standards and compute variances. A consulting firm was hired to develop the standards and the format for the variance computation. One standard in particular that the consulting firm developed seemed too excessive to plant management. The consulting firm’s standard was production of 100 gallons of ice cream every 45 minutes. The plant’s middle level of management thought the standard should be 100 gallons every 55 minutes, while the top management of the company thought that the consulting firm’s standard would provide more motivation to the employees. Why is the company establishing a standard for production? What are some factors the company may need to consider before selecting one of the proposed standards?arrow_forward
- Comprehensive Variance Analysis Marvel Parts Inc. manufactures auto accessories. One of the company’s products is a set of seat covers that can be adjusted to fit nearly any small car. The company uses a standard cost system for all of its products. According to the standards that have been set for the seat covers, the factory should work 2,850 hours each month to produce 1,900 sets of covers. The standard costs associated with this level of production are: During August, the factory worked only 2,800 direct labor-hours and produced 2,000 sets of covers. The following actual costs were recorded during the month. At standard, each set of covers should require 5.6 yards of material. All of the materials purchased during the month were used in production. Required: Compute the following variances August: 1. The materials price and quantity variances. 2. The labor rate and efficiency variances. 3. The variable overhead rate and efficiency variances.arrow_forwardRouse manufactures coffee mugs that it sells to other companies for customizing with their own logos. Rouse prepares flexible budgets and uses a standard cost system to control manufacturing costs. The standard unit cost of a coffee mug is based on static budge volume of 59,700 coffee mugs per month: Requirement 1. Compute the cost and efficiency variances for direct materials and direct labor. Begin with the cost variances Select the required formulas, compute the cost variances for direct materials and direct labor and identify whether each variance is favorable (F) or unfavorable (U). (Abbreviations used AC = actualco cost AQ = actual quantity, FOH = fixed overheard; SC = standard cost; SQ= standard quantity.)arrow_forwardThe production cost for a waterproof phone case is $9 per unit and fixed costs are $27,000 per month. How much is the favorable or unfavorable variance if 5,000 units were produced for a total of $71,600? Enter the amount as positive number. (favorable or unfavorable) variance _____?arrow_forward
- Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: Standard Hours Standard Rate per Hour Standard Cost 30 minutes $ 6.20 $ 3.10 During August, 10,370 hours of direct labor time were needed to make 19,600 units of the Jogging Mate. The direct labor cost totaled $63,257 for the month. What is the labor rate variance and the labor efficiency variance? The budgeted variable manufacturing overhead rate is $4.50 per direct labor-hour. During August, the company incurred $55,998 in variable manufacturing overhead cost. Compute the variable overhead rate and efficiency variances for the month.arrow_forwardOaklands Manufacturing LtdOaklands Manufacturing Ltd. produces a health drink which it sells in health shops and gyms across the country. The business has been doing well and an examination of its results for the month of July showed that it had produced and sold 500 more bottles of the drink than the expected 4,000 units of Product A during July. Despite the increased number of bottles produced the business is pleased to find that its manufacturing costs have actually decreased overall, and management are keen to identify the individual variances to see where savings were made, or where costs increased.The following are the actual results for July as produced by the management accountant. Materials (4,200 litres drink mix) Direct employee labour (15,000 hours) Variable overhead based on labour hrs Fixed overheadsTotal actual manufacturing cost£37,800 63,000 79,500 69,000249,300 The company never carries stocks of materials, finished goods, or work-in-progress.The following was the…arrow_forwardDog Bone Bakery, which bakes dog treats, makes a special biscuit for dogs. Each biscuit uses 0.75 cup of pure semolina flour. They buy 4,000 cups of flour at $0.55 per cup. They use 3,587.5 cups of flour to make 4,800 biscuits. The standard cost per cup of flour is $0.53. A. What are the direct materials price variance, the direct materials quantity variances, and the total direct materials cost variance? Round your answers to two decimals. Enter all amounts as positive numbers. Direct materials price variance $ fill in the blank 1 Unfavorable Direct materials quantity variance $ fill in the blank 3 Favorable Total direct materials cost variance $ fill in the blank 5 Unfavorable B. What is the standard cost per biscuit for the semolina flour? Round your answer to four decimals. $ fill in the blank 7arrow_forward
- The Lockit Company manufactures door knobs for residential homes and apartments. Lockit is considering the use of simple (single-driver) and multiple regression analyses to forecast annual sales because previous forecasts have been inaccurate. The new sales forecast will be used to initiate the budgeting process and to identify more completely the underlying process that generates sales. Larry Husky, the controller of Lockit, has considered many possible independent variables and equations to predict sales and has narrowed his choices to four equations. Husky used annual observations from 20 prior years to estimate each of the four equations. Following are definitions of the variables used in the four equations and a statistical summary of these equations: St=ForecastedsalesindollarsforLockitinperiodtSt1=ActualsalesindollarsforLockitinperiodt1Gt=ForecastedU.S.grossdomesticproductinperiodtGt1=ActualU.S.grossdomesticproductinperiodt1Nt1=Lockitsnetincomeinperiodt1 Required: 1. Write Equations 2 and 4 in the form Y = a + bx. 2. If actual sales are 1,500,000 in the current year, what would be the forecasted sales for Lockit in the coming year? 3. Explain why Larry Husky might prefer Equation 3 to Equation 2. 4. Explain the advantages and disadvantages of using Equation 4 to forecast sales.arrow_forwardChypre, Inc., produces a cologne mist using a solvent mix (water and pure alcohol) and aromatic compounds (the scent base) that it sells to other companies for bottling and sale to consumers. Chypre developed the following standard cost sheet: On May 2, Chypre produced a batch of 1,000 gallons with the following actual results: Required: 1. Calculate the yield ratio. 2. Calculate the standard cost per unit of the yield. (Round to the nearest cent.) 3. Calculate the direct materials yield variance. (Round to the nearest cent.) 4. Calculate the direct materials mix variance. (Round to the nearest cent.)arrow_forwardMaterials and labor variances Branca Inspections Inc. specializes in determining whether a building or houses drainpipes are properly tied into the citys sewer system. The company pours colored chemical through the pipes and collects an inspection sample from each outlet, which is then analyzed. Each job should take 15 hours for each of four inspectors, at a standard rate of 18 per hour. Each job requires a standard quantity of 5 gallons of Glow (a colored chemical), which should cost 25 per gallon. Data from the companys most recent job (a building) follow: Required: Compute the following variances, using the formulas on pages 421422 and 424: 1. Materials price and quantity variances. 2. Labor rate and efficiency variances.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license