Textbook Question
Book Icon
Chapter 7, Problem 7.7QP

You are working on a concrete mix design that requires each cubic yard of concrete to have 0.45 water-cement ratio, 1963 lb/yd3 of dry gravel, 4% air content, and 565 lb/yd3 of cement. The available gravel has a specific gravity of Ggravel = 2.7, a moisture content of 1.6%, and absorption of 2.4%. The available sand has a specific gravity of Gsand = 2.5, a moisture content of 4.8%, and absorption of 1.5%. For each cubic yard of concrete needed on the job, calculate the weights of cement, moist gravel, moist sand, and water that should be added to the batch. Summarize and total the mix design when finished (don’t include air entrainer in summary).

Blurred answer
Students have asked these similar questions
You are working on a concrete mix design that requires each cubic yard of concrete to have a 0.43 water–cement ratio, 1232 kg/m3 of dry gravel, 145 kg/m3 of water, and 4% air content. The available gravel has a specific gravity of Ggravel = 2.60, a moisture content of 2.3%, and absorption of 4.5%. The available sand has a specific gravity of Gsand = 2.40, a moisture content of 2.2%, and absorption of 1.7%. Air entrainer is to be included using the manufacturers specification of 6.3 mL/1% air/100 kg cement. For each cubic meter of concrete needed on the job, calculate the weight of cement, moist gravel, moist sand, and water that should be added to the batch. Summarize and total the mix design when finished.
You are working on a concrete mix design that requires each cubic yard ofconcrete to have 0.45 water–cement ratio, 1165 kg/m3 of dry gravel, 4% aircontent, and 335 kg/m3 of cement. The available gravel has a specific gravity of Ggravel = 2.7, a moisture content of 1.6%, and absorption of 2.4%. The available sand has a specific gravity of Gsand = 2.5, a moisture content of 4.8%, and absorption of 1.5%. For each cubic meter of concrete needed on the job, calculate the mass of cement, moist gravel, moist sand, and water that should be added to the batch. Summarize and total the mix design when finished (don’t include air entrainer in summary).
You are working on a concrete mix design that requires each cubic yard ofconcrete to have 0.45 water–cement ratio, 1165 kg/m3 of dry gravel, 4% air content, and 335 kg/m3 of cement. The available gravel has a specific gravity of Ggravel = 2.7, a moisture content of 1.6%, and absorption of 2.4%. The available sand has a specific gravity of Gsand = 2.5, a moisture content of 4.8%, and absorption of 1.5%. For each cubic meter of concrete needed on the job, calculate the mass of cement, moist gravel, moist sand, and water that should be added to the batch. Summarize and total the mix design when finished (don’t include air entrainer in summary).

Chapter 7 Solutions

Materials for Civil and Construction Engineers (2nd Edition)

Ch. 7 - Prob. 7.11QPCh. 7 - Prob. 7.12QPCh. 7 - Students in the materials lab mixed concrete with...Ch. 7 - Students in the materials lab mixed concrete with...Ch. 7 - Why is it necessary to measure the air content of...Ch. 7 - What do we mean by curing concrete? What will...Ch. 7 - Discuss five different methods of concrete curing.Ch. 7 - Draw a graph showing the typical relation between...Ch. 7 - Why is extra water harmful to fresh concrete, but...Ch. 7 - Discuss the change in volume of concrete at early...Ch. 7 - Discuss the creep response of concrete structures....Ch. 7 - Prob. 7.22QPCh. 7 - On one graph, draw a sketch showing the typical...Ch. 7 - Using Figure 7.34, a. Determine the ultimate...Ch. 7 - Three concrete mixes with the same ingredients,...Ch. 7 - Three concrete mixes with the same ingredients,...Ch. 7 - Three 100 mm 200 mm concrete cylinders with water...Ch. 7 - Students in the materials class prepared three 4 ...Ch. 7 - Three 150 mm 300 mm concrete cylinders with water...Ch. 7 - Three 6 in. 12 in. concrete cylinders with water...Ch. 7 - A normal-weight concrete has an average...Ch. 7 - Discuss the significance of the compressive...Ch. 7 - What is the standard size of PCC specimens to be...Ch. 7 - Prob. 7.34QPCh. 7 - What is the purpose of performing the flexure test...Ch. 7 - What are the advantages of using a third-point...Ch. 7 - Consider a standard flexural strength specimen of...Ch. 7 - To evaluate the effect of a certain admixture on...Ch. 7 - To evaluate the effect of a certain admixture on...Ch. 7 - Prob. 7.40QPCh. 7 - Prob. 7.41QPCh. 7 - A normal-weight concrete has an average...Ch. 7 - Three batches of concrete were prepared using the...Ch. 7 - Three batches of concrete were prepared using the...Ch. 7 - Prob. 7.45QPCh. 7 - Prob. 7.46QPCh. 7 - Discuss two nondestructive tests to be performed...Ch. 7 - Discuss the concept of concrete maturity meters.Ch. 7 - Discuss four alternatives that increase the use...Ch. 7 - What is self-consolidating concrete? How are its...Ch. 7 - Prob. 7.51QPCh. 7 - Two 6 in. 12 in. concrete cylinders with randomly...Ch. 7 - Discuss the concept of high-performance concrete....Ch. 7 - Comparing PCC with mild steel, answer the...Ch. 7 - Prob. 7.55QP
Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Types of Cement; Author: Tyler Ley;https://www.youtube.com/watch?v=cApoqFALh8s;License: Standard Youtube License