The Pullman Mfg., Inc., three-station work cell illustrated in Figure S7.8 has two machines at station 1 in parallel (The product needs to go through only one of the two machines before proceeding to station 2.) The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2.
a) What is the throughput time of the new work cell?
b) What is the bottleneck time of the new work cell?
c) If the firm operates 8 hours per day. 6 days per week, what is the weekly capacity of this work cell?
d) How did the addition of the second machine at workstation 2 affect the performance of the work cell from Problem S7.12?
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management Plus MyLab Operations Management with Pearson eText - Access Card Package (10th Edition)
- Capacity Constraints (the chart is in the picture below) A visa application process from a Tumaritis country can be described in the chart below. The head of visa administration notices that the visa application process has gone wrong and decides to check the whole process. Questions:a. Explain the difference between bottlenecks and constraints (answered)b. Identify the bottleneck of this process and explain your answer (answered)c. Calculate the throughput time of the above process and explain how many files can be processed in 1 hour? (answered)d. Explain how to solve the problem in the above process. (not yet answered)arrow_forwardA production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).a) Which operation is the bottleneck?b) What is the bottleneck time?c) What is the throughput time of the overall system?d) If the firm operates 8 hours per day, 20 days per month, whatis the monthly capacity of the manufacturing process?arrow_forwardDefine the concept of Bottleneck? Explain what system capacity is? Explain why doubling the capacity of a bottleneck may not double the system capacity?arrow_forward
- There is a canteen set up serving food (Breakfast, Lunch, Snacks-tea, and Dinner) to 500 students in a B school. It has a huge well-furnished dining hall and has a serving zone where students queue to pick up their eatables. The Institute director, during his regular Gemba walks in the canteen, has seen a lot of inefficiency in the related operational processes and needs a major improvement. (a)Provide one relatable and relevant example of five of the eight wastes under Lean systems which are likely to be witnessed in the canteen. (b)Recommend lean tools & techniques/system solutions to be employed for curbing each of those five wastes with a line on justification. (c) Suggest three key enablers and measures track the progress on lean in the canteen.arrow_forwardgiven information: which step is in bottleneck=30 min for tan leather 60/30=2 briefcases per hr are processed at the bottleneck workstation per hour throughput time of the overall process Throughput = 75 minutes PLEASE answer the following 3 questions:  If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process.  Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process.  Answer parts a through d again based on the new process created in part e?arrow_forwardOperations Management Question: A production line at V. J.​ Sugumaran's machine shop has three stations. The first station can process a unit in 6 minutes. The second station has two identical​ machines, each of which can process a unit in 16 minutes​ (each unit only needs to be processed on one of the two machines). The third station can process a unit in 10 minutes. What is the bottleneck station with its bottleneck time in minutes per unit? Please be thorough with the answer you'll argue. Thank you in advance. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- The three-station work cell at Pullman Mfg., Inc.is illustrated in Figure S7.8. It has two machines a t station I inparallel (i.e., the product needs to go through only one of the twomachines before proceeding to station 2).                                                                                                      a) What is the throughput time of this work cell?b) What is the bottleneck time of this work cell?c) What is the bottleneck station?d) If the firm operates 8 hours per day, 6 days per week, what isthe weekly capacity of this work cell?arrow_forwardMr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean floors. The process to produce this piece of equipment consists of 10 steps. Determine what other information is needed in order to balance this assembly line. Also, set up a numerical example of the line balancing problem at hand. Using this example, demonstrate how to balance the line and how to calculate its efficiency.arrow_forwardA small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two alternatives, A and B, have been identified, and the associated costs and revenues have beenestimated. Annual fixed costs would be $40,000 for A and $30,000 for B; variable costs per unitwould be $10 for A and $11 for B; and revenue per unit would be $15.b. At what volume of output would the two alternatives yield the same profit?arrow_forward
- Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (i.e., not including queue time), are given for each line in the following table: Process Old Line New Line Rate per Machine (parts/hour) # Machines per Station Time (minute) Rate per Machine (parts/hour) # Machines per Station Time (minute) Punching 15 4 4.0 120 1 0.50 Braking 12 4 5.0 120 1 0.50 Assembly 20 2 3.0 125…arrow_forwardWhen bottlenecks are identified, resources become accessible, and some people may go looking for them.arrow_forwardWhat type of process—project, job shop, flow shop, and continuous flow—would most likely be used to produce the following? Explain your reasoning.  Apple iPads Weddings Paper Tax preparationarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.