Textbook Question
Chapter 7.S, Problem 17P
Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding new equipment. Two vendors have presented proposals. The fixed costs for proposal A are $50 000, and for proposal B, $70 000. The variable cost for A is $12 00, and for B, $10 00. The revenue generated by each unit is $20.00
- a. What is the break-even point in units for proposal A?
- b. What is the break-even point in units for proposal B?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Stapleton Manufacturing intends to increase capacity through the addition of new equipment. Two vendors have presented proposals. The fixed cost for proposal A is
$55,000, and for proposal B, $33,000. The variable cost for A is $9, and for B, $14. The revenue generated by each unit is $18.
a) What is the crossover point for the two options?
The crossover point for the two options is
units. (Round your response to the nearest whole number.)
b) At an expected volume of 6,200 units, which alternative should be chosen?
The profit (loss) if proposal A is accepted and 6,200 units are produced is $
(Round your response to the nearest dollar and include a minus sign if necessary.)
The profit (loss) if proposal B is accepted and 6,200 units are produced is $ (Round your response to the nearest dollar and include a minus sign if necessary.)
should be chosen at an expected volume of 6,200 units.
Markland Manufacturing intends to increase capacity by overcoming a bottleneck operation byadding new equipment. Two vendors have presented proposals. The fixed costs for proposal A are$50,000, and for proposal B, $70,000. The variable cost for A is $12.00, and for B, $10.00. The revenuegenerated by each unit is $20.00.a) What is the break-even point in units for proposal A?b) What is the break-even point in units for proposal B?
The owner of Old-Fashioned Berry Pies, S. Simon, is contemplating adding a
new line of pies, which will require leasing new equipment for a monthly
payment of $6,000. Variable costs would be $2 per pie, and pies would retail
for $7 each.
a.
How many pies must be sold in order to break even?
b.
What would the profit (loss) be if 1,000 pies are made and sold in a month?
How many pies must be sold to realize a profit of $4,000?
С.
d.
If 2,000 can be sold, and a profit target is $5,000, what price should be charged per pie?
5-30
Chapter 7 Solutions
Operations Management
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - How is actual, or expected, output computed?Ch. 7.S - Explain why doubling the capacity of a bottleneck...Ch. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prepare a flowchart tor one of the following: a....Ch. 7 - Prob. 14PCh. 7 - Prepare a time-function map for one of the...Ch. 7 - Prepare a service blueprint for one of the...Ch. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Using Figure 7.6 in the discussion of value-stream...Ch. 7 - Metters Cabinets, Inc., needs to choose a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Sroufe Manufacturing intends to increase capacity by overcoming a bottleneck operation by adding new equipment. Two vendors have presented proposals. The fixed costs are $50,000 for proposal A and $70,000 for proposal B. The variable cost is $14.00 for A and $11.00 for B. The revenue generated by each unit is $20.00. a) The break-even point in units for the proposal by Vendor A =units (round your response to the nearest whole number). b) The break-even point in units for the proposal by Vendor B =units (round your response to the nearest whole number).arrow_forwardConcord, Inc. is unsure of whether to sell its product assembled or unassembled. The unit cost of the unassembled product is $12, while the cost of assembling each unit is estimated at $14. Unassembled units can be sold for $59, while assembled units could be sold for $65 per unit. What decision should Concord make? Process further; the company will save $8 per unit. Sell before assembly; the company will save $8 per unit. Sell before assembly; the company will save $4 per unit. Process further; the company will save $6 per unit.arrow_forwardMarkland Manufacturing intends to increase capac-ity by overcoming a bottleneck operation by adding new equip-ment. Two vendors have presented proposals. The fixed costs for proposal A are $50,000, and for proposal B, $70,000. The variablecost for A is $12.00, and for B, $10.00. The revenue generated byeach unit is $20.00.a) What is the break-even point in units for proposal A?b) What is the break-even point in units for proposal B?arrow_forward
- Jupiter Game Company manufactures pocket electronic games. Last year Jupiter sold 25,000 games at $25 each. Total costs amounted to $525,000, of which $150,000 were considered fixed costs. In an attempt to improve its product, the company is considering replacing a component part that has a cost of $2.50 with a new and better part costing $4.50 per unit in the coming year. A new machine also would be needed to increase plant capacity. The machine would cost $18,000 with a useful life of six years and no salvage value. The company uses straight-line depreciation on all plant assets. (Ignore income taxes). 1) If management holds the sales price constant and makes the suggested changes, how many units of product must be sold in the coming year to break even?arrow_forwardWalton, Inc. is unsure whether to sell its product assembled or unassembled. The unit cost of the unassembled product is $32, while the cost of assembling each unit is estimated at $34. Unassembled units can be sold for $110, while assembled units could be sold for $142 per unit. What decision should Walton make?arrow_forwardINSTRUCTIONS: We're looking to work with a new publisher that is interested in selling us two different placements. The publisher has told us that placement 1 has an approximate CTR of 0.3% and will get 2M impressions per month. Placement 2 has an approximate CTR of 0.4% and will get 3M impressions. The CPM for Placement 1 is $5, CPM for Placement 2 is 6$ The conversion rate of our landing page is 8% and the leads generated all are worth $50. Please use the worksheet outlined below to fill in the highlighted cells with the answers you find. 1. What is the total cost? 2. What is the total revenue and retutn on ad spend? 3. What is the total clickthrough rate (CTR)? 4. Which placement is more effective in terms of ROAS? Placement 1 Placement 2 Total Impressions 2,000,000 3,000,000 CTR 0.30% 0.40% CR 8.00% 8.00% Clicks Leads = Impressions * CTR = Clicks * CR Revenue = Leads RPL DEFINITIONS: Revenue: Money generated from leads submitted by visitors filling out forms. Impressions: The…arrow_forward
- Sroufe Manufacturing intends to increase capacityby overcoming a bottleneck operation by adding new equipment.Two vendors have presented proposals. The fixed costs for proposalA are $50,000, and for proposal B, $70,000. The va riablecost for A is $12.00, and fo r B, $10.00. The revenue generated byeach unit is $20.00.a) What is the break-even point in units for proposal A?b) What is the break-even point in units for proposal B?arrow_forwardPrepare a memo to the Board of Directors that proposes cost containment projects that reduce facility costs as well as improve quality.arrow_forwardBrown’s, a local bakery, is worried about increased costs—particularly energy. Last year’s records can provide a fairly good estimate of the parameters for this year. Wende Brown, the owner, does not believe things have changed much, but she did invest an additional $3,000 for modifications to the bakery’s ovens to make them more energy efficient. The modifications were supposed to make the ovens at least 15% more efficient. Brown has asked you to check the energy savings of the new ovens and also to look over other measures of the bakery’s productivity to see if the modifications were beneficial. You have the following data to work with:arrow_forward
- Sawyer's, a local bakery, is worried about increased costs-particularly energy. Last year's records provide a fairly good estimate of the parameters for this year. Judy Sawyer, the owner, does not believe things have changed much, but she did invest an additional $3,000 for modifications to the bakery's ovens to make them more energy efficient. The modifications were supposed to make the ovens at least 15% more efficient. Sawyer has asked you to check the energy savings of the new ovens and also to look over other measures of the bakery's productivity to see if the modifications were beneficial. You have the following data to work with. Last Year Now Production (dozen) Labour (hours) Capital Investment ($) Energy (BTU) 1,500 1,500 350 325 15,000 18,000 3.000 2,750 Energy productivity increase = % (Enter your response as a percentage rounded to two decimal places and include a minus sign if necessary.) Capital productivity increase = % (Enter your response as a percentage rounded to two…arrow_forwardProduct A has a fixed cost of $5,000 and a variable cost of $5 per unit, it can sell for $20 per unit. Product B has a fixed cost of $8,000 and a variable cost of $9 per unit, it can sell for $30 per unit. Company plans to produce 381 units of either A or B. Which product should be produced?arrow_forwardA contractor has agreed to build 10 dog houses in 20 days at a price of $800 per unit. 10 days later, the contractor has finished 6 dog houses with an actual total cost of $5,200. What is the cost variance CV (CV = BCWP-ACWP)? $800 C$400 $-1,200 $600arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY