a)
To estimate: The time taken to complete fourth unit with 72% of learning.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
To estimate: The time taken to complete fourth unit with 87% of learning.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
c)
To estimate: The time taken to complete fourth unit with 95% of learning.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
EBK OPERATIONS MANAGEMENT
- If 315 labor hours were required to produce the 1st unit in a production run and 137 labor hours were required to produce the 9th unit, what was the learning-curve rate during production?arrow_forwardCompany Z is just starting to make a brand new product it has never made before. It has completed two units so far. The first unit took 12 hours to complete and the next unit took 11 hours. Based only on this information, what would be the estimate of the learning percentage in this process?arrow_forwardIt takes Boeing 29,454 hours to produce the fifth 787 jet. The learning factor is 80%. Time required for the production of the twelfth 787: 12th unit time:arrow_forward
- The 4th unit of a 10-unit job took seven hours to complete. The 6th unit has been worked on for two hours, but is not yet finished. Estimate the additional amount of time needed to finish the 6th unit if the work has a 65% learning curve slope O a. 6.143 hours O b. 5.114 hours O c. 3.441 hours O d. 3.058 hours O e. 4.143 hoursarrow_forwardIf the first unit of a product took 25 minutes to produce and the learning curve rate is 80%, how much time will the production of the 100th unit take?arrow_forwardThe time to assemble the first unit on a production line is 12. hours. The learning rate is 0.94. Approximately how long will it take for the seventh unit to be assembled? The number of hours needed for the seventh unit to be assembled is ? hours. (Round to one decimal place.)arrow_forward
- If a company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours respectively. What is the appropriate learning curve? Explain and show your answer.arrow_forwardOmega Technology is starting production of a new supercomputer for use in large research universities. It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent. How many labor hours should it expect in manufacturing the second unit?arrow_forwardLearning Curves 1. Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 54 hours to complete. d) What is the average time per unit for producing the last 10 units (#31 - #40)?arrow_forward
- Use learning curve theory to predict the number of repetitions (units) that will be neededfor a trainee to achieve a unit time of 6 minutes if the trainee took 10 minutes to do the firstunit and a learning curve of 90 percent is operative.a. Use the learning table.b. Use the log formula.arrow_forwardA manager wants to estimate the remaining time that will be needed to complete a five-unit job. The initial unit of the job required 12 hours, and the work has a learning percentage of 77. Estimate the total time remaining to complete the job.arrow_forwardA manager wants to determine an appropriate learning percentage for processing insurance claims for storm damage. Toward that end, times have been recorded for completion of each of the first six repetitions.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.