a)
To determine: The duration needed to finish last unit.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
To determine: The duration needed to finish tenth unit.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
c)
To estimate: The average time per unit for 25 units.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
EBK OPERATIONS MANAGEMENT
- 1 unit of a toy production takes 1080 hours, and the learning curve rate is 72% than what is the time taken for 4 units of production through cumulative average time method ?arrow_forwardAn activity is known to have an 80 percent learning curve. It has taken a worker 10 hoursto produce the first unit. Determine expected completion times for these units: the 2nd, 4th,8th, and 16th (note successive doubling in the unit column).arrow_forwardBeth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 18 transplants under great scrutiny and at no cost to the patients. The very first transplant, just completed, required 28 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: Unit number 5 75% Unit time: .513 Total time: 3.459 80% Unit number 5 Unit time: .596 Total time: 3.738 85% Unit number 5 Unit time: .686 Total time: 4.031 Unit number 18 75% Unit time: .301 Total time: .8.245 Unit number 18 80% Unit time: 3.94 Total Time: 9.716 Unit number 18 85% Unit time: .508 Total time: 11.405 a) the 5th transplant = 14.36 hours b) the first 5 transplant = ? hours (round your response to two decimal places)arrow_forward
- If the 80% learning curve applies, what wil be the cumulative average time to produce three units if first unit takes 100hoursarrow_forwardAqeel bought 6 bookcases for his place. Each required unpacking of parts and assembly, which included some nailing and bolting. Aqeel completed the first bookcase in 5 hours and the second in 4 hours. 1-What is his learning rate (k)? 2-What is his learning-curve value of b? 3-Assuming that the same rate continues, how long will the 3rd, 4th, 5th, and 6th bookcases take? Y3 = hours Y4 = hours Y5 = hours Y6 = hours 5-How long will take him to finish all the 6 cases? It will take him hours.arrow_forwardIf it took 410 hours to produce the first unit of a product, and the learning curve is 90%, how long will it take to produce units 12 through 25???arrow_forward
- A company estimates that it will take 20 hours and 42 direct labor hours to construct the 50th and 5th respectively, under an 80% learning curve. how long does it take to make the first unit in the batch?arrow_forwardSuppose the 1st unit takes 15 hours to be produced and the learning rate is 82% , find time taken for 4th unit using incremental method ?arrow_forwardA company estimates that it will take 20 hours and 42 direct labor hours to construct the 50th and 5th respectively, under an 80% learning curve. how long does it take to make the first unit in the batch? Please please correct answer dont copypastearrow_forward
- The fifth unit of a 10-unit job took five hours to complete. The sixth unit has been worked on fortwo hours, but is not yet finished. Estimate the additional amount of time needed to finish the10-unit job if the work has a 75 percent learning ratearrow_forwardAn aircraft company has an order to refurbish the interiors of 18 jet aircraft. The work has a learning curve percentage of 80. On the basis of experience with similar jobs, the industrial engineering department estimates that the first plane will require 300 hours to refurbish. Estimate the amount of time needed to complete:a. The fifth planeb. The first five planesc. All 18 planesarrow_forwardThe first unit of a job took 40 hours to complete. The work has a learning percentage of 88. The manager wants time estimates for units 2, 3, 4, and 5. Develop those time estimates.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.