EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
expand_more
expand_more
format_list_bulleted
Question
Chapter 8, Problem 2CQD
Summary Introduction
To find: The number of people needed for the outgoing wire process using assembly line balancing methods for the current staffing level of 11 full time equivalent employees.
Introduction:The cash movement operating unit is responsible for transferring money from bank to any of its customers.The number of employees are 11.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A paced assembly line has been devised to manufacture calculators, as the following data show:
LOADING...
Station
Work Element Assigned
Work Element Time (min)
S1
A
4.0
S2
D, E
0.9,
1.5
S3
C
5.0
S4
B, F, G
1.1,
1.0,
1.3
S5
H, I, J
1.1,
0.5,
1.8
S6
K
4.0
a. What is the maximum hourly output rate from this line?
(Hint:
The line can only go as fast as its slowest workstation.)
The maximum hourly output rate is
nothing
calculators per hour. (Enter your response as an integer.)
B. What cycle time corresponds to this maximum output rate?
C. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each? 10-hour shift?
D. What is the line's efficiency?
A paced assembly line has been devised to manufacture calculators, as the following data show:
Station
Work ElementAssigned
Work ElementTime (min)
S1
S2
S3
S4
S5
S6
A
D,E
C
B,F,G
H,I,J
K
2.7
0.6, 0.9
3.0
0.7, 0.7, 0.9
0.7, 0.3, 1.2
2.4
a. What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)b. What cycle time corresponds to this maximum output rate?c. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?d. What is the line’s efficiency?
An assembly line must be designed to produce 40 containers per hour. The following data give the necessary information
Table 1
TASK
IMMEDIATE PREDECESSOR
TASK TIME (sec)
A
None
60
B
A
12
C
B
35
D
A
55
E
D
10
F
E
50
G
F, C
5
Draw the precedence diagram.
Compute the cycle time (in seconds) to achieve the desired output rate.
What is the theoretical minimum number of stations?
Assign the tasks to the workstation?
What is the efficiency of the line?
Calculate the idle time
Knowledge Booster
Similar questions
- An assembly plant for the Blood Pressure RX, a portableblood pressure device, has 400 minutes available daily in theplant for the device, and the average demand is 80 units per day.Final assembly requires 6 separate tasks. Information concerningthese tasks is given in the following table. a) Draw a precedence diagram of this operationb) Given the demand, what is the cycle time for this operation?c) What is the theoretical minimum number of workstations?f d) Assign tasks to workstations.e) What is the overall actual efficiency of the assembly line?arrow_forwardSuppose the times for the individual operations for the in-line skate assembly are as follows: Task Description Time (sec) 1 Assemble wheels, bearings, and axle hardware 11 2 Assemble brake housing and pad 8 3 Complete wheel assembly 20 4 Inspect wheel assembly 13 5 Assemble boot 18 6 Join boot and wheel subassemblies 7 7 Add line and final assembly 10 8 Perform final inspection 10 Consider the production line achieving an output rate of 180 per hour below. Using the proposed design, calculate the total time and idle time for each workstation. If your answer is zero, enter "0". Round your answers to the nearest whole number. Station Tasks Total Time, seconds Idle Time, seconds A 1 and 2 B 3 C 5 D 4 and 6 E 7 and 8 Total What is the assembly line efficiency? Round your answer to one decimal place. %arrow_forwardGordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A − 4 10 8 B − − 5 9 C − − − 9 D − − − − Workpieces moved per week between work areas are: A B C D A − 900 700 600 B − − 400 300 C − − − 600 D − − − − It costs Gordon $3 to move 1 work piece 1 foot. The weekly total material handling cost of the layout =....... $nothing (enter your response as a whole number). The weekly total material handling cost of the layout =....... nothing dollars (enter your response as a whole number).arrow_forward
- Management wants to design an assembly line that will turn out 800videotapes per day. There will be eight working hours in each day. The industrial engineeringstaff has assembled the information below: Task Time (min.) Immediate Follower a .2 b,d b .2 f c .4 b,e d .1 e e .3 f f .2 h g .1 h h .2 i i .6 none A) Determine the optimum cycle time (i.e., actual operating time/desired output).B) What is the minimum number of stations needed?C) Assign tasks to work stations.D) What is the efficiency of this assembly line?arrow_forwardAn assembly line must be designed to produce 40 containers per hour. The following data give the necessary information Table 1 TASK IMMEDIATE PREDECESSOR TASK TIME (sec) A None 60 B A 12 C B 35 D A 55 E D 10 F E 50 G F, C 5 Draw the precedence diagram. ii. Compute the cycle time (in seconds) to achieve the desired output rate. iii. What is the theoretical minimum number of stations? iv. Assign the tasks to workstation? v. What is the efficiency of the line? PLEASE ANSWER THE FOLLOWING QUESTIONS: iV, & v.arrow_forwardIn what ways does technology have an impact on process selection? How can technology impact layout decisions?arrow_forward
- Given in the following table are the tasks necessary forfinal assembly of a hospital bed, the length of time needed to perform each task, and the operations that must be com-pleted prior to subsequent operations. Construct a prece-dence diagram and balance the assembly line for a desired cycle time of 14 minutes. Draw a schematic diagram of thebalanced line. How many beds can actually be assembledin an eight-hour period?arrow_forwardAn assembly line is to be designed to operate 7½ hours per day and supply a steady demand of 300 units per day. Here are the tasks and their performance times: TASK PRECEDING TASKS PERFORMANCETIME (SECONDS) A — 70 B — 40 C — 45 D A 10 E B 30 F C 20 G D 60 H E 50 I F 15 J G 25 K H, I 20 L J, K 25 What is the workstation cycle time required to meet the desired output rate? What is the theoretical minimum number of workstations required to meet the desired output rate? Note: Round up your answer to the next whole number. Assign tasks to workstations using the longest operating time. What is the efficiency of your line balance, assuming it is running at the cycle time determined in part b? Note: Round your answer to 1 decimal place. Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 71/2 hours per day. Note: Round your answer for cycle time down to the nearest whole number. Round your…arrow_forwardColeman Rich, Ltd., has received the followingorders: The entire fabrication for these units is scheduled on onemachine. There are 2,250 usable minutes in a week, and eachunit will take 65 minutes to complete. Develop a capacityplan, using lot splitting, for the 10-week time periodarrow_forward
- (3) The following information is given about an assembly line. The desired output rate is 360 units per 8-hour day. Task Time (sec) Immediate Predecessor(s) A 30 - B 25 A C 40 A, B D 45 B E 25 B F 28 C, E G 16 D H 40 F, G a. How many stations are required for the most efficient balance you can achieve? b. Balance the line according to the most following tasks rule. c. What is the idle time per unit for your solution? d. Identify the bottleneck for your solution.arrow_forwardThe following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 20 — B 7 A C 20 B D 22 B E 15 C F 10 D G 16 E, F H 8 G The workday is seven hours long. The demand for completed product is 750 per day. Find the cycle time required to meet the desired output rate. Note: Round your answer to 1 decimal place. What is the theoretical number of workstations required to meet the desired output rate? Note: Round up your answer to the next whole number. Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and the idle time for each such task. Note: Round your answers to 1 decimal place. What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)? Note: Round your answer to 1 decimal place. Suppose that demand rose from 750 to 800 units per day. Determine the cycle time. (Use the…arrow_forwardMonique Food Processing Company produces light snacks that can be heated in a microwave. The following steps are included in the process: Steps Description Capacity (Units/Hour) 1 Prepare food 200 2 Measure and place in plastic pouch 175 3 Prepare cardboard box 200 4 Insert pouch into box 300 5 Shrink-wrap box 200 What are the key factors that determine when to add capacity? Why would an organization want to reduce its capacity?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.