EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 6PA
(a)
Summary Introduction
Interpretation: Minimum and maximum cycle time are to be calculated.
Concept Introduction:
The minimum cycle time is similar to the longest task time in the pool of tasks needed to produce the products, whereas maximum cycle time refers to the sum of all task time needed to produce finished goods.
(b)
Summary Introduction
Interpretation: Daily outputthat will be acquired by those cycle times are to be calculated.
Concept Introduction:
The minimum cycle time is similar to the longest task time in the pool of tasks needed to produce the products, whereas maximum cycle time refers to the sum of all task time needed to produce finished goods.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the totaltime for all tasks is 18 minutes. The line will operate for 450 minutes per day.a. What are the minimum and maximum cycle times?
An assembly line with 50 activities is to be balanced. The total amount of time to complete all 50 activities is 60 minutes. The longest activity takes 1.8 minutes and the shortest takes 0.6 minute. The line will operate for 540 minutes per day.
What are the maximum and minimum cycle times? Round your answers to one decimal place.
Maximum cycle time: minutes
Minimum cycle time: minutes
How much daily output will be achieved by each of those cycle times? Round your answers to the nearest whole number.
Daily output achieved by maximum cycle time: units/day
Daily output achieved by minimum cycle time: units/day
Balance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an 8-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case.
Fill in the table below for a shift output of 60 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
Workstation
Tasks
Total Time
Idle Time
1
2
3
4
Total
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Fill in the table below for a shift output of 40 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number.
Workstation
Tasks
Total Time
Idle Time
1
2
3
Total
What is the assembly-line efficiency? Round your answer to one decimal place.
%
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved in the production of a case of Mint Chocolate Chip Cookies. 27 seconds 0.3333 seconds 18 seconds 14 seconds 56 seconds 20 secondsarrow_forwardBill builds benches in a small shop and he plans to operate five 8-hour days perweek. Each bench has two ends and a top. It takes 5 minutes to cut and sand eachend and 2 minutes to make each top. Assembly requires 8 minutes per bench, andpainting requires 5 minutes per bench. Bill has one employee who makes the topsand ends. Bill will do the final assembly and painting. He also plans 1 hour per dayfor setup and teardown for each department.a. How many benches should he plan to build per week?b. How many hours per week are required for each person?c. Suggest ways to increase the number of benches produced per weekarrow_forwardA product is completed when 18 tasks are done. These tasks are assigned to 6 workstations (each workstation handling several tasks) in an assembly line set up. All workstations work the same amount of time (= cycle time), and move the (partial) product to the next workstation, and repeat this process. The last workstation generates the finished product. We need 1200 units made every day (= 8 hours). If we run this line with a cycle time of 0.3 minutes, what is the most amount of work (in minutes) that can be done on this product? (Give the answer with one decimal place)arrow_forward
- You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. What is the resulting line's efficiency?arrow_forwardAssume that Company F produces a variety of smart phones sequentially on three machines. The times required on each machine for one typical racket are as follows: M1: 3 minutes M2: 8 minutes, M3: 2 minutes, M4: 5 minutes. The throughput time for a smart phone is : 2 minutes 4.5 minutes 9 minutes 18 minutesarrow_forwardThe desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME(SECONDS) IMMEDIATEPREDECESSOR A 35 — B 25 A C 35 A D 55 B E 5 B F 15 C G 30 E-D H 5 F-G b. What is the workstation cycle time? c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.)arrow_forward
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear What is the maximum possible output of the line? What is the theoretical minimum number of workstations using the cycle time computed in” b “above Assign tasks to workstations using the cycle time in “b” above.arrow_forward(Please do not give solution in image format thanku) Develope a 3 level work breakdwon structure (including level 1,2 and 3) the work break down structure is based on the following project. Improving Customer Service Response Time for a clothing company. additional informationa can be added to the work break down struture to create the different levels The motivation behind this project is to improve customer satisfaction by reducing response time for customer service inquiries. Currently, customers are waiting an average of 48 hours to receive a response to their inquiries, resulting in frustration and dissatisfaction. By implementing a new customer service ticketing system and training customer service agents on effective communication and problem-solving techniques, response time can be reduced to 24 hours or less.arrow_forwardYou have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly line balancing procedure. The cycle time is 5 minutes, and the sum of all the tasks required ok the line is 25 minutes. What is the value of the resulting line’s efficiency?arrow_forward
- given information: which step is in bottleneck=30 min for tan leather 60/30=2 briefcases per hr are processed at the bottleneck workstation per hour throughput time of the overall process Throughput = 75 minutes PLEASE answer the following 3 questions: If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process. Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process. Answer parts a through d again based on the new process created in part e?arrow_forwardProvide the following values: PV, EV, AC, CPI, SPI, EAC, ETC, BAC Each of the iterations of four that each will take 20 days to complete at a cost of $20,000 per iteration. Today is the end of what should be iteration three. The current status of the project is as follows: Iteration One complete, spent $20,000 Iteration Two complete, spent $25,000 Iteration Three half done, spent $17,000 Iteration Four Not started.arrow_forwardThe trim line at PW is a small subassembly line that, along with other such lines, feeds into the final chassis line. The entire assembly line, which consists of more than 900 workstations, is to make PW’s new E cars. The trim line itself involves only 13 work elements and must handle 20 cars per hour. Work-element data are as follows: Work Element Time (Sec) Immediate Predecessor(s) A B C DE F G H I J K L M 1.8 0.4 1.6 1.5 0.7 0.5 0.8 1.4 1.4 1.4 0.5 1.0 0.8 None None None A A E B C D F,G H J I,K,L a. Draw a precedence diagram.b. What cycle time (in minutes) results in the desired output rate?c. What is the theoretical minimum number of stations?d. Use the longest work element decision rule to balance the line and calculate the efficiency of your solution.e. Use the most followers work element decision rule to balance the line and calculate the efficiency of your solution.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science