Chapter 8, Problem 6PSB
Problem 21-6BA Materials, labor, and overhead variances recorded and analyzed C1 P5
Kenya Company’s
Standard direct materials cost ……………………………………………… | $130,000 |
Direct materials quantity variance (favorable) …………………………….. | 5,000 |
Direct materials price variance (favorable)………………………………… | 1,500 |
Actual direct labor cost ……………………………………………………. | 65,000 |
Direct labor efficiency variance (favorable) ………………………………... | 3,000 |
Direct labor rate variance (unfavorable) …………………………………….. | 500 |
Actual overhead cost ………………………………………………………… | 250,000 |
Volume variance (unfavorable) ………………………………………………. | 12,000 |
Controllable variance (unfavorable) ………………………………………… | 8,000 |
Required
- Prepare journal entries dated June 30 to record the company’s costs and variances for the month. (Do not prepare the
journal entry to close the variances.) Check (1) Dr. Work in process Inventory (for overhead), $230,000
- Identify the variances that would attract the attention of a manager who uses management by exception. Describe what action(s) the manager should consider.
Analysis Component
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 8 Solutions
Managerial Accounting
Ch. 8 - Prob. 1MCQCh. 8 - Prob. 2MCQCh. 8 - Prob. 3MCQCh. 8 - A Company’s standard for a unit of its single...Ch. 8 - Prob. 5MCQCh. 8 - Prob. 1DQCh. 8 - Prob. 2DQCh. 8 - Prob. 3DQCh. 8 - Prob. 4DQCh. 8 - Prob. 5DQ
Ch. 8 - Prob. 6DQCh. 8 - Prob. 7DQCh. 8 - Prob. 8DQCh. 8 - Prob. 9DQCh. 8 - Prob. 10DQCh. 8 - Prob. 11DQCh. 8 - Prob. 12DQCh. 8 - Prob. 13DQCh. 8 - Prob. 14DQCh. 8 - Prob. 15DQCh. 8 - Prob. 16DQCh. 8 - Prob. 17DQCh. 8 - Prob. 18DQCh. 8 - Prob. 1QSCh. 8 - Prob. 2QSCh. 8 - Prob. 3QSCh. 8 - Prob. 4QSCh. 8 - Prob. 5QSCh. 8 - Prob. 6QSCh. 8 - Prob. 7QSCh. 8 - Prob. 8QSCh. 8 - Prob. 9QSCh. 8 - Materials cost variances P2 Juan Company’s output...Ch. 8 - Prob. 11QSCh. 8 - Prob. 12QSCh. 8 - Prob. 13QSCh. 8 - Prob. 14QSCh. 8 - Prob. 15QSCh. 8 - Prob. 16QSCh. 8 - A Preparing overhead entries P5 Refer to the...Ch. 8 - A Total variable overhead cost variance P4 Mosaic...Ch. 8 - A Overhead spending and efficiency variances P4...Ch. 8 - Computing sales price and volume variances A1...Ch. 8 - Sales variances A1 In a recent year, BMW sold...Ch. 8 - Prob. 22QSCh. 8 - Prob. 23QSCh. 8 - Prob. 24QSCh. 8 - Prob. 1ECh. 8 - Prob. 2ECh. 8 - Prob. 3ECh. 8 - Prob. 4ECh. 8 - Prob. 5ECh. 8 - Prob. 6ECh. 8 - Prob. 7ECh. 8 - Exercise 21-8 Standard unit cost; total variance...Ch. 8 - Prob. 9ECh. 8 - Prob. 10ECh. 8 - Prob. 11ECh. 8 - Prob. 12ECh. 8 - Prob. 13ECh. 8 - Exercise 21-14A Materials variances recorded and...Ch. 8 - Prob. 15ECh. 8 - Prob. 16ECh. 8 - Prob. 17ECh. 8 - Prob. 18ECh. 8 - Exercise 21-19 Computation of total overhead rate...Ch. 8 - Exercise 21-20 Computation of volume and...Ch. 8 - Exercise 21-21 Overhead controllable and volume...Ch. 8 - Prob. 22ECh. 8 - Exercise 21-23 Computing and interpreting sales...Ch. 8 - Prob. 1PSACh. 8 - Prob. 2PSACh. 8 - Prob. 3PSACh. 8 - Prob. 4PSACh. 8 - Prob. 5PSACh. 8 - Problem 21-6AA Materials, labor, and overhead...Ch. 8 - Prob. 1PSBCh. 8 - Prob. 2PSBCh. 8 - Prob. 3PSBCh. 8 - Prob. 4PSBCh. 8 - Prob. 5PSBCh. 8 - Problem 21-6BA Materials, labor, and overhead...Ch. 8 - Prob. 8SPCh. 8 - Flexible budgets and standard costs emphasize the...Ch. 8 - Prob. 2AACh. 8 - Prob. 3AACh. 8 - Prob. 1BTNCh. 8 - The reason we use the words favorable when...Ch. 8 - Prob. 3BTNCh. 8 - Prob. 4BTNCh. 8 - Prob. 5BTNCh. 8 - Prob. 6BTN
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Variance interpretation You have been asked to investigate some cost problems in the Assembly Department of Ruthenium Electronics Co., a consumer electronics company. To begin your investigation, you have obtained the following budget performance report for department for the last quarter: The following reports were also obtained: You also interviewed the Assembly Department supervisor. Excerpts from the interview follow: Q: What explains the poor performance in your department? A: Listen, you've got to understand what it's been like in this department recently. Lately, it seems no matter how hard we try, we can't seem to make the standards. I'm not sure what is going on, but we've been having a lot of problems lately. Q: What kind of problems? A: Well, for instance, all this quarter we've been requisitioning purchased parts from the material storeroom, and the pans just didn't fit together very well I'm not sure what is going on. but during most of this quarter we've had to scrap and sort purchased pansjust to get our assemblies put together. Naturally, all this takes time and material. And that's not all. Q: Go on. A: All this quarter, the work that we've been receiving from the Fabrication Department has been shoddy. I mean, maybe around 20% of the stuff that comes in from Fabrication just can't be assembled. The fabrication is all wrong. As a result, we've had to scrap and rework a lot of the stuff. Naturally, this has just shot our quantity variances. Interpret the variance reports in light of the comments by the Assembly Department supervisor.arrow_forwardRecording standards in accounts Cioffi Manufacturing Company incorporates standards in its accounts and identifies variances at the time the manufacturing costs are incurred. Journalize the entries to record the following transactions: A. Purchased 2,450 units of copper tubing on account at 52.00 per unit. The standard price is 48.50 per unit. B. Used 1,900 units of copper tubing in the process of manufacturing 200 air conditioners. Ten units of copper tubing are required, at standard, to produce one air conditioner.arrow_forward
Recommended textbooks for you
- Financial & Managerial AccountingAccountingISBN:9781285866307Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage LearningFinancial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage LearningAccounting (Text Only)AccountingISBN:9781285743615Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
Financial & Managerial Accounting
Accounting
ISBN:9781285866307
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Financial & Managerial Accounting
Accounting
ISBN:9781337119207
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Accounting (Text Only)
Accounting
ISBN:9781285743615
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY