For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. PLEASE FOLLOW THE EXACT TEMPLATE AS SHOWN IN THE SCREENSHOTS. IN THE ACTIVITY BOX PLEASE ALSO WRITE THE DURATION, AND FOLLOW THE CHART TO PROJECT FINISH.
Read the following set of activities carefully. The precedence of all activities is finish to start. Using either ADM or PDM, perform the following tasks.
Using backward pass, calculate latest start and latest finish of each activity. Determine float
Complete the table showing all the information regarding each activity that has been acquired
Activity #
Activity Identifier
Activity Duration
Precedence
1
A
4
None
2
B
7
None
3
C
9
B
4
D
5
C
5
E
6
A, D
6
F
4
C, D, E
7
G
5
F
8
H
2
G
9
I
5
G, H
15-Choose from the following, the cost object for a project.
a.
Smart phones
b.
Placing an order
c.
Dam construction
d.
Utility bill payment
Chapter 8 Solutions
Construction Management
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Don’t round up nor round off. Show complete solutions. Please answer all the questions.arrow_forwardsample of a work breakdown structure on construction of a single storey house applying the 100 rule and also the budget.arrow_forwardAnswer it step-by-step with complete solution and answer all the questions askedarrow_forward
- Response times may vary by subject and question complexity. Median response time is 34 minutes for paid subscribers and may be longer for promotional offers PROVIDE COMPLETE SOLUTIONarrow_forwardPlease give proctor test results and graph.arrow_forwarddevelop a WBS for your assumed building project. Mention duration for each activity of your project and total completion time.arrow_forward
- Please answer the problem ASAP, thank you!arrow_forwardExample 11: - Draw the network diagram using the arrows method for the project whose activities are listed in the table below, then calculate the early and late beginnings and ends, the free and surplus time for the activities, then determine the critical events, the critical path, and the project completion timearrow_forwardAddress each part of the listed questionsarrow_forward
- Need some help figuring out how to start this question, using CSA guidelinesarrow_forwarda. Develop a rough plan / sketch of the construction project based on the assumptions of the construction. The area for each of the project can be assumed suitably as per the norms. b. Identify and develop a comprehensive work break down structure for the project. c. The WBS should be further broken down into around 25 activities d. Assign duration (in days only) for each of the activities with proper justificatione. Link the activities in logical orders. f. Develop a network diagram based on the logical sequence of activities [It can be manually Drawing depending on students activities]. g. Calculate the total duration and identify the critical path for the project. help:)arrow_forwardResponse times may vary by subject and question complexity. Median response time is 34 minutes for paid subscribers and may be longer for promotional of PROVIDE COMPLETE SOLUTIONarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Residential Construction Academy: House Wiring (M...Civil EngineeringISBN:9781285852225Author:Gregory W FletcherPublisher:Cengage Learning
Residential Construction Academy: House Wiring (M...
Civil Engineering
ISBN:9781285852225
Author:Gregory W Fletcher
Publisher:Cengage Learning