Question
Chapter 9, Problem 14P
a)
Summary Introduction
To determine: The theoretical minimum for the smallest number of workstations.
b)
Summary Introduction
To assign: The different tasks to different workstations.
c)
Summary Introduction
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Stanford Rosenberg Computing wants to establish anassembly line for producing a new product, the Personal DigitalAssistant (PDA). The tasks, task times, and immediate predecessorsfor the tasks are as follows: Rosenberg's goal is to produce 180 PDAs per hour.a) What is the cycle time?b) What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?c) Can the theoretical minimum actually be reached when workstations are assigned?
Use the longest work element rule to balance the assembly line described in the following table and Figure so that it will produce 40 units per hour.a. What is the cycle time?b. What is the theoretical minimum number of workstations?c. Which work elements are assigned to each workstation?d. What are the resulting efficiency and balance delay percentages?e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution?
Work Element
Time (Sec)
Immediate Predecessor(s)
A
B
C
D
E
F
G
H
I
J
K
40
80
30
25
20
15
60
45
10
75
15
None
A
A
B
C
B
B
D
E,G
F
H,I,J
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows:
Task
Duration(minutes)
ImmediatePredecessor
a
0.5
-
b
0.4
a
c
0.5
b
d
0.3
-
e
1.8
d
f
1.9
c
g
2
e, f
Do each of the following: a. Determine the number of followers for each task.
(Please answer number of tasks following task for A-G)
Chapter 9 Solutions
Principles Of Operations Management
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Johnson Cogs wants to set up a line to serve 60 customers perhour. The work elements and their precedence relationshipsare shown in the following table.a. What is the theoretical minimum number of stations?b. How many stations are required using the longest workelement decision rule?c. Suppose that a solution requiring five stations is obtained.What is its efficiency?arrow_forwardConsider the relationship chart for the a fast-food restaurant, Assume that the areas required for each department are: Department Area Required (Square feet) (CB) 300 (CF) 200 (PS) 200 (DD) 200 (CS) 300 Assume facility dimension of 6 (horizontal) by 8 (vertical) squares, where each square is 5 feet on a side. As a result, for example the CB department requires 12 squares. Develop a layout for the fast-food restaurant.arrow_forwardA company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,darrow_forward
- Sue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?arrow_forwardJane produces custom greeting cards using six distinct workelements. She would like to produce 10 cards in each 8-hourcard-making session. Figure 5.17 details each work elementand its associated durations in minutes as well as their pre-cedence relationships. a. What cycle time is required to satisfy the required output rate?b. What is the theoretical minimum number of workstationsrequired?c. If Jane identifies a five-station solution, what is the associ-ated efficiency and balance delay?d. If the cycle time increased by 100 percent, would the the-oretical minimum number of workstations also increaseby 100 percent?arrow_forwardAbout the product v process layouts, which statement(s) is correct?1. Process layout is more flexible, and therefore, it is only applicable to a service context. 2. Compared to a product layout, a process layout is located closer to "Project" in a product-process matrix. 3. Product layout is more efficient, and therefore, it is only applicable to a manufacturing context. 4. Compared to a process layout, a product layout is closer to a fixed-position layout in a product-process matrix. 5. None of the statements are correct Note: You need to provide which statements are correct. It can be more than one.arrow_forward
- Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: Task Performance Time (mins) Task Must Follow Task Listed Below A 8 − B 11 A C 10 A, B D 9 B, C E 8 C F 4 D, E A C F B E D In the diagram, there are 6 circles labeled using the letters from A to F. There are 8 of arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: A to B, A to C, B to C, C to D, B to D, C to E, D to F, and E to F. Part 2 a) The theoretical minimum number of workstations=55 (round your response up to the…arrow_forwardWhat is the significant difference between the layout of retail facilities and that of other production facilities?arrow_forwardMaureen Marcy is designing the layout for a new business in town. The Collegiate Spa. From visiting spas in neighboring towns, she has compiled the following data on movement between spa activities. Help Maureen determine where to locate each activity on a 2 × 3 grid so that nonadjacent moves are 1 2 3 4 5 6 1. Relaxation lounge 50 25 75 2. Facial 10 75 3. Massage 30 50 50 4. Power shower 25 5. Mineral bath 50 50 6. Saunaarrow_forward
- Johnson Cogs wants to set up a line to serve 60 customers per hour. The work elements and their precedence relationships are shown in the following table.a. What is the theoretical minimum number of stations?b. How many stations are required using the longest work element decision rule?c. Suppose that a solution requiring five stations is obtained. What is its efficiency? Work Element Time (Sec) Immediate Predecessor(s) A B C D E F G H I J 40 30 50 40 6 25 15 20 18 30 None A A B B C C D,E F,G H,I Total 27arrow_forwardA firm employs 10 programmers, 8 systems analysts, 4 computer engineers, and 3 statisticians. A "team" is to be chosen to handle a new long-term project.The team will consist of 3 programmers, 2 systems analysts, 2 computer engineers and statistician(a)In how many ways can the team be chosen? (B)If the customer insists that one particular engineer with whom he or shehas worked betore be assigned to the project. In how many ways can theteam be chosen?arrow_forwardHren Electronics is in process of setting a new office building. The following tables show the number of expected communications among the four departments and two possible layouts for considerations (tables 2 and 3 show the distance among the departments in the given layout). Calculate a total cost (or total distance traveled) for each layout and provide a recommendation that would minimize the total costs. Table 1. Number of transactions A B C D A 0 75 20 0 B 5 0 300 100 C 10 0 0 0 D 0 20 0 0 Table 2. Layout 1 (Walking distance in meters) A B C D A 0 10 20 30 B 10 0 10 20 C 20 10 0 10 D 30 20 10 0 Table 3 Layout 2 (Walking distance in meters) A B C D A 0 5 30 40 B 5 0 5 20 C 30 5 0 20 D 40 20 20 0arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY