Pearson Etext For Principles Of Operations Management: Sustainability And Supply Chain Management -- Access Card (11th Edition)
11th Edition
ISBN: 9780135639122
Author: Jay Heizer, Barry Render, Chuck Munson
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 9, Problem 17P
a)
Summary Introduction
To draw: The precedence diagram.
b)
Summary Introduction
To assign: The different tasks to different workstations.
c)
Summary Introduction
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
d)
Summary Introduction
To determine: The idle time per cycle.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tailwind, Inc., produces high-quality but expensive training shoes for nmners. The Tailwind shoe, which sells for $210, contains both gas- and liquid-filled compartments to provide morestability and better protection against knee, foot, and back injuries. Manufacturing the shoes requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 60. The information for the tasks is as follows: a) Draw the precedence diagram.b) Assign tasks to thl e minimum feasible number of workstations according to the "ranked positioned weight" decision rule.c) What is the efficiency of the process you completed in (b)?d) What is the idle time per cycle?
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourlyoutput of four units. The department uses a working time of 56 minutes per hour. Assign the tasksshown in the accompanying precedence diagram (times are in minutes) to workstations using thefollowing rules:a. In order of most following tasks. Tiebreaker: greatest positional weight.b. In order of greatest positional weight. Tiebreaker: most following tasks.c. What is the efficiency?
Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01 201 2.13, 2.0, 2.61, 2.71 , and 2.95 minutes for A,B,C,D,E,F, and respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task Adoes not need any predecessorsB requires task A to completed. To start task C and task Deach require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line with ties broken according to longest task time firstthe tasks that will be assigned to the SECOND workstation are
Chapter 9 Solutions
Pearson Etext For Principles Of Operations Management: Sustainability And Supply Chain Management -- Access Card (11th Edition)
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- (a) What is the cycle time necessary to achieve the desired rate of production?(b) Using the longest element rule, create workstations to balance the line,attempting to get as close as possible to the theoretical minimum numberof workstations.(c) What is the efficiency and idle time of the line balance?(d) The company considers that if the lamps are successful with the publicit may need to increase production to 30,000 units. The company thinksthe simplest solution is to obtain two more production lines, thus havingtriple capacity. Another option is to re-balance the line. Considering thata single worker is assigned to a work station, determine which option(more production lines or re-balancing) yields the smallest labour size.arrow_forwardSue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?arrow_forwardThe XYZ company produces all type of office furniture. The “Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long office hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks; Task Time (min) Immediate predecessor A 4 - B 7 - C 6 A, B D 5 C E 6 D F 7 E G 8 E I 6 F, G a) Draw a precedence diagram of this operation b) What is the cycle time for this operation? c) What is the theoretical minimum number of workstations? d) Assign tasks to the workstations e) What is the idle time per cycle? f) What is the efficiency of the assembly line?arrow_forward
- The Sun River beverage company is a regional producer of teas, exotic juices, and energy drinks. With an interest in healthier lifestyles, there has been an increase in demand for its sugar-free formulation. The final packing operation requires 13 tasks. Sun River bottles its sugar-free product 5 hours a day, 5 days a week. Each week, there is a demand for 3,000 bottles of this product. TASK TIME (MINUTES) PRECEDING TASK 1 0.1 — 2 0.1 1 3 0.1 2 4 0.2 2 5 0.1 2 6 0.2 3, 4, 5 7 0.1 1 8 0.1 7 9 0.2 8 10 0.1 9 11 0.2 6 12 0.2 10, 11 13 0.1 12 Using the following data, solve the assembly-line balancing problem and calculate the efficiency of your solution. Use the longest task time for your decision criteria. Note: Round your answer to the nearest whole percent.arrow_forwardAs the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the assembly line that is used to produce a special type of toy. b. Draw the precedence diagram for the problem that you set up in part “a” above. c. Use the example that you set up to demonstrate how you will balance the line. d. Calculate the efficiency of the line.arrow_forwardIllinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Performance Time (mins) Task Must Follow Task Listed Below A 4 − B 6 − C 6 A, B D 5 C E 7 D F 6 E G 7 E H 7 F, G This exercise only contains parts b, c, d, e, f, and g. The cycle time for the production of a chair = 9.69. minutes (round your response to two decimal places). The theoretical minimum number of workstations=5 (round your response up to the next whole number). d) The assignment of tasks to workstations should be: (Hint:…arrow_forward
- A manufacturing company is designing an assembly lineto produce its main product. Th e line should be able to produce60 units per hour. Th e following data in Table 10-16 give thenecessary information. (a) Which task is the bottleneck?(b) Draw a precedence diagram for the above information.(c) Compute the cycle time with a desired output of 60 unitsper hourarrow_forwardA shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:a. Construct the precedence diagram.b. Assign tasks according to the most following tasks rule. Break ties with the greatest positional weight rule.c. Assign tasks according to the greatest positional weight rule. Break ties with the most following tasks rule.d. Compute the balance delay for each rule. Which one yields the better set of assignments in this instance? TaskImmediatePredecessorTaskTimea — 0.5b a 1.4c a 1.2d a 0.7e b, c 0.5f d 1.0g e 0.4h g 0.3i f 0.5j e, i 0.8k h, j 0.9m k 0.3arrow_forwardAlocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performied. The daily demand is 150 toys. Times of the tasks are 2.73, 2.01, 2.13, 2.0, 2.61, 2.71, and 2.95 minutes for A, B, C, D, E, F, and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires taskA to be completed. To start task Cand task D, each require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once taskFis completed.What is the minimum number of workstations needed?arrow_forward
- Use the longest work element rule to balance the assembly line described in the following table and Figure so that it will produce 40 units per hour.a. What is the cycle time?b. What is the theoretical minimum number of workstations?c. Which work elements are assigned to each workstation?d. What are the resulting efficiency and balance delay percentages?e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution? Work Element Time (Sec) Immediate Predecessor(s) A B C D E F G H I J K 40 80 30 25 20 15 60 45 10 75 15 None A A B C B B D E,G F H,I,Jarrow_forwardA DIY product manufacturing company wishes to create a ‘product’ focused layout for the manufacture of their new cordless drill. There order book requires them to produce 480 drills per eight hour day. The assembly operations for the drill and the associated information are given in the table below. Therefore the key tasks are to: Management has decided to cut down 3 seconds from each operation (operation 1 - 8) to improve overall effectiveness. (a) calculate the maximum cycle time (b) calculate the minimum number of work stations (c) produce the precedence diagram (d) produce the line design which achieves the required cycle time (e) calculate balancing lossarrow_forwardVikiki Furniture, Inc. produces all types of office furniture. The "Executive Secretary" is a sofa-bed that has been designed using ergonomics to provide comfort during long work hours. The sofa-bed sells for $138. There are 580 minutes available during the day, and the average daily demand has been 65 items. There are eight tasks: Task performance time (min) task must follow task listed A 4 -- B 7 -- C 6 A, B D 5 C E 6 D F 7 E G 8 E H 6 F, G Total 49 min What is the Cycle time for this operation?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY