Chapter 9, Problem 16P
a)
Summary Introduction
To draw: The precedence diagram.
b)
Summary Introduction
To assign: The different tasks to different workstations.
c)
Summary Introduction
To determine: How the balance could be improved to 100%
d)
Summary Introduction
To determine: The theoretical minimum number of workstations.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following table details the tasks required forIndiana-based Frank Pianki Industries to manufacture a fullyportable industrial vacuum cleaner. The times in the table are inminutes. Demand forecasts indicate a need to operate with a cycletime of 10 minutes.ACTIVITY ACTIVITY DESCRIPTION
IMMEDIATEPREDECESSORS TIMEA Attach wheels to tub — 5B Attach motor to lid — 1.5C Attach battery pack B 3D Attach safety cutoff C 4E Attach fi lters B 3F Attach lid to tub A, E 2G Assemble attachments — 3H Function test D, F, G 3.5I Final inspection H 2J Packing I 2a) Draw the appropriate precedence diagram for this productionline.b) Assign tasks to workstations and determine how much idletime is present each cycle.c) Discuss how this balance could be improved to 100%.d) What is the theoretical minimum number of workstations?
The following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of
11
minutes.
Activity
Activity Description
Performance Time (mins)
Predecessors
A
Attach wheels to tub
5.0
−
B
Attach motor to lid
1.5
−
C
Attach battery pack
2.8
B
D
Attach safety cutoff
4.0
C
E
Attach filters
3.0
B
F
Attach lid to tub
2.0
A, E
G
Assemble attachments
3.0
−
H
Function test
3.7
D, F, G
I
Final inspection
2.0
H
J
Packing
2.0
I
a-b) One of the possible assignment of tasks to workstations is shown correctly in…
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourlyoutput of four units. The department uses a working time of 56 minutes per hour. Assign the tasksshown in the accompanying precedence diagram (times are in minutes) to workstations using thefollowing rules:a. In order of most following tasks. Tiebreaker: greatest positional weight.b. In order of greatest positional weight. Tiebreaker: most following tasks.c. What is the efficiency?
Chapter 9 Solutions
Pearson Etext For Principles Of Operations Management: Sustainability And Supply Chain Management -- Access Card (11th Edition)
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary" is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: Task Performance Time (mins) Task Must Follow Task Listed Below A 4 − B 6 − C 6 A, B D 5 C E 7 D F 6 E G 7 E H 7 F, G This exercise only contains parts b, c, d, e, f, and g. The cycle time for the production of a chair = 9.69. minutes (round your response to two decimal places). The theoretical minimum number of workstations=5 (round your response up to the next whole number). d) The assignment of tasks to workstations should be: (Hint:…arrow_forwardA computer factory in Tangerang plans to increase production line for new products and plan to produce as many as XX0 units per hour. Production process, production time and production process to continue the next production process are described in the table below: (1 day = 8 working hours) production process production time Production process that follows the next production according to the list below A 12 - B 15 A C 8 A D 5 B,C E 20 D a. What is the cycle time for the production of the new product? ( note : in second )b. What is the minimum number of workstations?c. Draw a diagram of the production process.d. Is it with the diagram that you have drawn, the production process can go according to plan? Describe the process from each workstation you've created!arrow_forwardIllinois Furniture, Inc., produces all types of officefurniture. The "Executive Secretary" is a chair that has beendesigned using ergonomics to provide comfort during long workhours. The chair sells for $130. There are 480 minutes availableduring the day, and the average daily demand has been 50 chairs.There are eight tasks: a) Draw a precedence diagram of this operation. •b) What is the cycle time for this operation?c) What is the theoretical minimum number of workstations?d) Assign tasks to workstations.e) What is the idle time per cycle?f) How much total idle time is present in an 8-hour shift?g) What is the efficiency of the assembly line, given your answer in (d)?arrow_forward
- Use the longest work element rule to balance the assembly line described in the following table and Figure so that it will produce 40 units per hour.a. What is the cycle time?b. What is the theoretical minimum number of workstations?c. Which work elements are assigned to each workstation?d. What are the resulting efficiency and balance delay percentages?e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution? Work Element Time (Sec) Immediate Predecessor(s) A B C D E F G H I J K 40 80 30 25 20 15 60 45 10 75 15 None A A B C B B D E,G F H,I,Jarrow_forwardOperations Management PLEASE SHOW AND EXPLAIN ALL STEPS & CALCULATIONS- THANK YOU! ABC Construction has developed the following set of activities for its budgeting process. Activity Predecessor Normal Activity Time (Days) Resulting Activity Time if Activity is Crashed (Days) Total Cost to complete activity in Normal Time Total Cost to complete activity in Crash Time A -- 4 2 $200 $600 B A 6 3 $300 $1200 C A 4 1 $300 $900 D B, C 3 2 $500 $550 E D 4 1 $500 $1700 a) Using the Normal Times, what is the critical path and project completion time for the budgeting process? Also, what is the cost to complete the project based on the Normal Times? b) If we want to reduce the project completion time to the minimum possible time by crashing all activities as needed, what is the new project completion time and what is the new total project cost? c) Modify the problem as follows. There is now an indirect cost of $75 per day, which is in addition to the cost identified above.…arrow_forwardReferring to the table below obs Work Center 1 ( in Days ) Work Center 2 ( in Days ) Due Dates 1 6 2 10 2 5 4 12 3 5 6 15 4 3 4 8 5 2 1 7 a. What is the ECT and idle time using Johnson’s Rule? Show the drawing of the WC. b. What is the ECT and idle time using EDD as a basis for sequencing? Show the drawing of the WC c. Compare the results and make a recommendation as the best way to do the sequence of jobsarrow_forward
- The Sail-Sea is a boat manufacturer. The assembly location is available for production of 60 boats for240 minutes per day.Given the information in the table,a) Draw the precedence diagramb) Fins the minimum number of workstations needed to produce the required daily demand. task performance time(min) task must follow task listed below a 1 - b 1 a c 2 a d 1 c e 3 c f 1 c g d, e, f h 2 b i 1 g, harrow_forwardUse the information in the table below (image 1): a. Construct the Precedence Diagram. b.The productive operating time is 55 minutes per hour for an 8-hour work. Compute the cycle time, CT, needed to obtain 50 units per hour. OT=_____ D= ________ CT= ____________ c. Determine the minimum number of workstation, Nmin. d. Assign tasks to workstations using the longest task-time Use the table format below. (IMAGE 2) e. Compute the Percentage Idle Time. f. Compute the Efficiency of the line. g. Draw the Balanced Line.arrow_forwardThe desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME(SECONDS) IMMEDIATEPREDECESSOR A 35 — B 25 A C 35 A D 55 B E 5 B F 15 C G 30 E-D H 5 F-G b. What is the workstation cycle time? c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.)arrow_forward
- Table 10-23 shows the tasks required to assemble analuminum storm door and the length of time needed to completeeach task. (a) Calculate the cycle time needed to produce 480 doors inan eight-hour work day.(b) What is the minimum number of workstations that can beused on the line and still achieve the desired productionrate? Balance the line and calculate its effi ciency.(c) What is the maximum output possible with these data?Th e minimum?arrow_forwardUsing AOA, diagram the network describedbelow for Lillian Fok’s construction project. Calculate itscritical path. How long is the minimum duration of thisnetwork?arrow_forwardSince Jack believes that Work Center 3 is his bottleneck, hehas asked you to do the following:(a) Calculate the percentage of planned output needed tocomplete the planned inputs (planned input 1 backlog/planned output) at Work Center 3.(b) Calculate the percentage of planned input that actuallyhappened (actual input 1 backlog/planned input 1backlog).(c) Calculate the percentage of available output that wasactually accomplished (actual output/planned output) atWork Center 3.(d) Given your results, do you believe that Jack is correct inassuming that Work Center 3 is his bottleneck? Justifyyour answer.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY