Chapter 9, Problem 18P
a)
Summary Introduction
To draw: The precedence diagram and assign tasks to 5 workstations.
b)
Summary Introduction
To determine: The efficiency.
Introduction:
Efficiency:
Efficiency is the measure of what is actually produced as opposed to what can be theoretically produced with the same amount of resources.
c)
Summary Introduction
To determine: The theoretical minimum number of workstations.
d)
Summary Introduction
To determine: The idle time per boat.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
I’m looking for part f and part f only: the efficiency of the assembly line with 5 work stations. All of the other parts are already answered and stated in the images. Thanks
What are advantages and disadvantages of work cells?
What is a heuristic? Name several that can be used in assembly-line balancing.
The following tasks are to be performed on an assembly line:
TASK
SECONDS
TASKS THAT MUST PRECEDE
A
20
—
B
7
A
C
20
B
D
22
B
E
15
C
F
10
D
G
16
E, F
H
8
G
The workday is seven hours long. The demand for completed product is 750 per day.
Find the cycle time required to meet the desired output rate.
Note: Round your answer to 1 decimal place.
What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and the idle time for each such task.
Note: Round your answers to 1 decimal place.
What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)?
Note: Round your answer to 1 decimal place.
Suppose that demand rose from 750 to 800 units per day. Determine the cycle time. (Use the…
Chapter 9 Solutions
Pearson Etext For Principles Of Operations Management: Sustainability And Supply Chain Management -- Access Card (11th Edition)
Ch. 9 - Prob. 1EDCh. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - Prob. 9DQ
Ch. 9 - Prob. 10DQCh. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Prob. 17DQCh. 9 - Prob. 18DQCh. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Prob. 3PCh. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Adam Munson Manufacturing, in Gainesville,...Ch. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Prob. 9PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Prob. 14PCh. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - Prob. 16PCh. 9 - Prob. 17PCh. 9 - Prob. 18PCh. 9 - Prob. 19PCh. 9 - Prob. 20PCh. 9 - Prob. 21PCh. 9 - Prob. 22PCh. 9 - Prob. 23PCh. 9 - Prob. 25PCh. 9 - Prob. 26PCh. 9 - Prob. 27PCh. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Henry Coupe, the manager of a metropolitan branch...Ch. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- T. Smunt Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three assembly operations (the assembly operations are “parallel”). See attached image with outline a. Which operation is the bottleneck? b. What is the throughput time (time from start to finish for one unit) of for the overall system? c. If the firm operates 8 hours per day, 22 days per month, what is the monthly capacity of the manufacturing process? d. Suppose that a second drilling machine is added, and it takes the same time as the original drilling machine. What are the new bottleneck operation and the bottleneck time? e. Suppose that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new throughput time? f. Suppose that a second drilling machine is added, and it takes the same time as the…arrow_forwardHow do mixed-model assembly lines differ from traditional assembly lines? What additional decisions arerequired?arrow_forwardThe hierarchy of components, their description, and the quantity of each needed to make one unit of a product are documented in: Select one: a. an engineering drawing. b. a list of group technology. c. a roadmap. d. a list of materials. and. a work order.arrow_forward
- You've just been assigned the job of setting up an electric fan assembly line with the following tasks and precedence relationships The assemtly line wil be nunning 8 hours per day and 5 days per week, The demand forast is 600 Items per week. Your goal is to minimie the numbor of workstations necesary to complete enough units to satisfy the demand forecast. What is the takt time (in minutes) needed to produce the required number of units? (Integer Answer, do not put anything other than numbers.) What is the theoretical minimum number of workstations that you will need (apply the round-up rule)? (Integer Answer, do not put anything other than numbers.)arrow_forwardA paced assembly line has been devised to manufacture calculators, as the following data show: Station Work ElementAssigned Work ElementTime (min) S1 S2 S3 S4 S5 S6 A D,E C B,F,G H,I,J K 2.7 0.6, 0.9 3.0 0.7, 0.7, 0.9 0.7, 0.3, 1.2 2.4 a. What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)b. What cycle time corresponds to this maximum output rate?c. If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?d. What is the line’s efficiency?arrow_forwardA manufacturing plant has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three one of the three assembly operations (the assembly operations are ‘parallel’). Use diagram titled "q3" attached as an image a) What is the bottleneck operation? b) What is the throughput time for the overall system? c) If the firm operates 10 hours a day, 21 days a month, what is the monthly and yearly capacity of the manufacturing process? d) Supposed that a second drilling machine is added, and it takes the same time as the original drilling machine. What is the new bottleneck time of the system? e) What is the new throughput time if the second drilling machine is added? f) What is the new hourly capacity if the second drilling machine is added?arrow_forward
- The following production flow shows Parts E, I, and N; Subassembly O; and the final assembly for Product P.A to B to C to D to EF to G to H to IJ to K to L to M to NE and I to ON and O to PB involves a bottleneck operation, and M involves a CCR.a. Draw the process flow.b. Where would you locate buffer inventories?c. Where would you place inspection points?d. Where would you stress the importance of quality production?arrow_forwardA production process at Raider Red Manufacturing is shown below. There are five parallel Sawing operations, five parallel Sanding operations, two parallel Welding operations, and four parallel Assembly operations. Find the throughput of the overall system in minutes per unit.arrow_forwardExplain what is meant by assembly line operations ?arrow_forward
- (3) The following information is given about an assembly line. The desired output rate is 360 units per 8-hour day. Task Time (sec) Immediate Predecessor(s) A 30 - B 25 A C 40 A, B D 45 B E 25 B F 28 C, E G 16 D H 40 F, G a. How many stations are required for the most efficient balance you can achieve? b. Balance the line according to the most following tasks rule. c. What is the idle time per unit for your solution? d. Identify the bottleneck for your solution.arrow_forwardAn assembly plant for the Blood Pressure RX, a portableblood pressure device, has 400 minutes available daily in theplant for the device, and the average demand is 80 units per day.Final assembly requires 6 separate tasks. Information concerningthese tasks is given in the following table. a) Draw a precedence diagram of this operationb) Given the demand, what is the cycle time for this operation?c) What is the theoretical minimum number of workstations?f d) Assign tasks to workstations.e) What is the overall actual efficiency of the assembly line?arrow_forwardYou have started your own business. Please explain your Business with a detail Operational Diagram with evidences?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY