The preinduction physical examination given by the U.S. Army involves the following seven activities:
ACTIVITY | AVERAGE TIME (MIN) |
Medical history | 10 |
Blood tests | 8 |
Eye examination | 5 |
Measurements (e.g., weight, height, blood pressure) | 7 |
Medical examination | 16 |
Psychological interview | 12 |
Exit medical evaluation | 10 |
These activities can be performed in any order, with two exceptions: Medical history must be taken first, and Exit medical evaluation is last at present, there are three paramedics and two physicians on duty during each shift. Only physicians can perform exit evaluations and conduct psychological interviews. Other activities can be carried out by either physicians or paramedics.
- a. Develop a layout and balance the line.
- b. How many people can be processed per hour?
- c. Which activity accounts for the current bottleneck?
- d. What is the total idle time per cycle?
- e. If one more physician and one more paramedic can be placed on duty, how would you redraw the layout? What is the new throughput?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Twelve tasks, with times and precedence requirements as shown in the following table, are tobe assigned to workstations using a cycle time of 1.5 minutes. Two heuristic rules will be tried:(1) greatest positional weight, and (2) most following tasks.In each case, the tiebreaker will be shortest processing time.
TaskLength(minutes)ImmediatePredecessora 0.1 —b 0.2 ac 0.9 bd 0.6 ce 0.1 —f 0.2 d, eg 0.4 fh 0.1 gi 0.2 hj 0.7 ik 0.3 jl 0.2 k
a. Draw the precedence diagram for this line.b. Assign tasks to stations under each of the two rules.c. Compute the percentage of idle time for each rule
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows:
Task
Duration(minutes)
ImmediatePredecessor
a
0.5
-
b
0.4
a
c
0.5
b
d
0.3
-
e
1.8
d
f
1.9
c
g
2
e, f
Do each of the following: a. Determine the number of followers for each task.
(Please answer number of tasks following task for A-G)
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Task
Duration(minutes)
ImmediatePredecessor
a
0.2
-
b
0.4
a
c
0.2
b
d
0.4
-
e
1.2
d
f
1.2
c
g
1.0
e, f
Click here for the Excel Data File
Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.)
b. Determine the minimum number of stations needed. (Round your answer to the next whole number.)
c. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
d. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.…
Chapter 9 Solutions
OPERATIONS MGMT. INSTANT ACCESS
Ch. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...Ch. 9 - Prob. 10DQ
Ch. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - After an extensive product analysis using group...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 18PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 20PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - As the Cottrell Bicycle Co. of St. Louis completes...Ch. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 1.6VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A local bakery makes custom cakes for special eventssuch as weddings and graduations. Making cakes is a two-step process of baking and decorating. The bakery has received eight orders, and the times required in hours for baking and decorating for each order are given in the following table:Cake Orders Baking DecoratingA 3 4B 1 2C 4 7D 2 4E 5 10F 2 6G 5 7H 6 13Determine a sequence that will minimize the makespan time.Construct a chart of the resulting sequence, and determine the idle time in te decoration process.arrow_forwardThe Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been completed, activities B and C can be performed independently of each other; however, activity D can be started only if both activities B and C have been completed. Based on his inspection of the car, Jensen believes that the following time estimates (in days) are applicable: Activity Optimistic Most Probable Pessimistic A 3 4 8 B 3 4 5 C 5 7 9 D 4 5 12 Jensen estimates that the parts needed to restore the body will cost $4000…arrow_forwardThe Porsche Shop, founded in 1985 by Dale Jensen, specializes in the restoration of vintage Porsche automobiles. One of Jensen's regular customers asked him to prepare an estimate for the restoration of a 1964 model 356SC Porsche. To estimate the time and cost to perform such a restoration, Jensen broke the restoration process into four separate activities: disassembly and initial preparation work (A), body restoration (B), engine restoration (C), and final assembly (D). Once activity A has been completed, activities B and C can be performed independently of each other; however, activity D can be started only if both activities B and C have been completed. Based on his inspection of the car, Jensen believes that the following time estimates (in days) are applicable: Activity Optimistic Most Probable Pessimistic A 3 4 8 B 3 4 5 C 5 7 9 D 4 5 12 Jensen estimates that the parts needed to restore the body will cost $4000…arrow_forward
- Udesign is a plant producing mass production dresses. The following table shows the tasks needed to be preformed, their task times and proceeding tasks. It is required to produce 30 dresses per hour. Task Immediate predecessor Task time (sec) A - 30 B - 40 C - 20 D A 100 E B,D 25 F C,D 50 G D,E,F 50 H G 90 a- Compute the cycle time and minimum number of workstations required b- Draw the precedence diagram c- What is the maximum output for this line d- Assign tasks to workstations using most number of followers e- Compute efficiency of such linearrow_forwardWilliam, a project manager, has a workload of 25,000 hours that needs to be completed in 30 weeks. He has a team of 20 people who work five 8-hour days per week. He notices that in the 30-week period, there are three holidays and 6 members have each requested 8 days off. Given this information, William is _____ short of completing his workload. Question options: 23,136 hours 1,864 hours 480 hours 1,480 hours 384 hoursarrow_forwardManagers at the First Community Bank are attempting to shorten the time it takes customers with approvedloan applications to get their paperwork processed. The flowchart for this process, consisting of several differ-ent activities, each performed by a different bank employee, is shown in Figure 5.1. Approved loan applicationsfirst arrive at activity or Step 1, where they are checked for completeness and put in order. At Step 2, the loansare categorized into different classes according to the loan amount and whether they are being requested forpersonal or commercial reasons. While credit checking commences at Step 3, loan application data are enteredin parallel into the information system for record-keeping purposes at Step 4. Finally, all paperwork for setting upthe new loan is finished at Step 5. The time taken in minutes is given in parentheses.Which single step is the bottleneck, assuming that market demand for loan applications exceeds the ca-pacity of the process? The management…arrow_forward
- Managers at the First Community Bank are attempting to shorten the time it takes customers with approved loan applications to get their paperwork processed. The flowchart for this process, consisting of several different activities, each performed by a different bank employee, is shown in Figure. Approved loan applications first arrive at activity or Step 1, where they are checked for completeness and put in order. At Step 2, the loans are categorized into different classes according to the loan amount and whether they are being requested for personal or commercial reasons. While credit checking commences at Step 3, loan application data are entered in parallel into the information system for record-keeping purposes at Step 4. Finally, all paperwork for setting up the new loan is finished at Step 5. The time taken in minutes is given in parentheses.Which single step is the bottleneck, assuming that market demand for loan applications exceeds the capacity of the process? The management…arrow_forwardA mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. Activity Time (minutes) A. Property survey 24 B. Credit report 19 C. Title search 18 D. Final decision 20 The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. Under this setting, what would be the maximum number of loan applications the office can process per day? Numbers only, keep three decimals if not exact, either round up or down is okarrow_forwardDayagsky Construction Firm, Inc. will soon begin to work on a building for US tea that was initially started by another firm that has gone out of business. The construction firm’s schedule of activities and related expected completion time for US tea project are presented in the following time table: Activity Code Activity Description Estimated Time (in weeks) A - B Obtain on-site work permits 2 B – E Repair damages done by vandals 8 B – C Inspect construction materials left on site 1 C – E Order and receive construction materials 2 C – D Apply for waiver to…arrow_forward
- The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job ▼ E A C B D ▼ A E B C D ▼ D B C E A ▼ E A B D C ▼ E D A B Carrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs, the…arrow_forwardThe Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its bottleneck operation. The time since the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Job Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) A 8 3 23 B 6 10 15 C 4 8 6 D 2 4 12 E 1 6 9 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Using the FCFS (first come, first served) decision rule for sequencing the jobs, the order is: Sequence 1 2 3 4 5 Job A B C D E Using the EDD (earliest due date) decision rule for sequencing the jobs, the…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY