Chapter 9, Problem 3P
Use the project activities that follow to determine the following:
- a. Construct a Gantt chart; indicate the project completion time and slack for each activity.
- b. Construct the CPM/PERT network, compute the length of each path in the network, and indicate the critical path.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.Use Table B1 and Table B2.
Activity
ImmediatePredecessor
Estimated Times(weeks)
A
—
2-4-6
D
A
6-8-10
E
D
7-9-12
H
E
2-3-5
F
A
3-4-8
G
F
5-7-9
B
—
2-2-3
I
B
2-3-6
J
I
3-4-5
K
J
4-5-8
C
—
5-8-12
M
C
1-1-1
N
M
6-7-11
O
N
8-9-13
End
H, G, K, O
If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation to 2 decimal places and Probability to 4 decimal places.)
Path
Mean
Std. Dev.
a-d-e-h
24.33 Numeric Response1. Edit Unavailable.24.33correct.
1.35 Numeric Response2. Edit Unavailable.1.35correct.
a-f-g
15.50 Numeric…
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.Use Table B1 and Table B2.
Activity
ImmediatePredecessor
Estimated Times(weeks)
A
—
2-4-6
D
A
6-8-10
E
D
7-9-12
H
E
2-3-5
F
A
3-4-8
G
F
5-7-9
B
—
2-2-3
I
B
2-3-6
J
I
3-4-5
K
J
4-5-8
C
—
5-8-12
M
C
1-1-1
N
M
6-7-11
O
N
8-9-13
End
H, G, K, O
If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation, z-value to 2 decimal places and Probability to 4 decimal places.)
Path
Mean
Std. Dev.
a-d-e-h
a-f-g
b-i-j-k
c-m-n-o
Probability ($1,000) ______________________________ Probability…
A project's activities must be completed in the sequence indicated below.
Activity
Immediately Preceding Activity
Duration in Weeks
A
-
3
B
-
20
C
-
15
D
-
10
E
-
5
F
A
4
G
D
3
H
D, E
10
I
F
3
J
B
10
K
G, H
7
L
B, I
5
The project ends with the intersection of activities: C, J, K and L
1- Use CPM to construct (Draw) the project Network and find the critical path.
2- How long is the project expected to take
Chapter 9 Solutions
OPERATIONS AND SUPPLY CHAIN MANAGEMENT
Ch. 9 - Why is CPM/PERT a popular and widely applied...Ch. 9 - What is the purpose of a CPM/PERT network?Ch. 9 - Why are dummy activities used in a CPM/PERT...Ch. 9 - What is the critical path, and what is its...Ch. 9 - What is slack, and how is it computed?Ch. 9 - How are the mean activity times and activity...Ch. 9 - How is total project variance determined in...Ch. 9 - What is the purpose of project crashing analysis?Ch. 9 - Describe the process of manually crashing a...Ch. 9 - Which method for determining activity time...
Ch. 9 - Explain how a Gantt chart differs from a CPM/PERT...Ch. 9 - Discuss the relationship of direct and indirect...Ch. 9 - Describe the limitations and disadvantages of...Ch. 9 - Describe the difference between activity-on-node...Ch. 9 - Identify and briefly describe the major elements...Ch. 9 - Select an everyday project you are familiar with...Ch. 9 - Prepare a WBS for a spaghetti with meatballs...Ch. 9 - Construct a Gantt chart for the project described...Ch. 9 - Construct a Gantt chart for the project described...Ch. 9 - Use the project activities that follow to...Ch. 9 - Construct a network from the information in the...Ch. 9 - For the network in Problem 9.4, determine the...Ch. 9 - Given the following network with activity times in...Ch. 9 - Given the following network with activity times in...Ch. 9 - A marketing firm is planning to conduct a survey...Ch. 9 - In one of the little-known battles of the Civil...Ch. 9 - A group of developers is building a new shopping...Ch. 9 - The management of a factory is going to erect a...Ch. 9 - Given the following network and probabilistic...Ch. 9 - The Farmers American Bank of Leesburg is planning...
Additional Business Textbook Solutions
Find more solutions based on key concepts
Consider the sales data for Computer Success given in Problem 7. Use a 3-month weighted moving average to forec...
Operations Management: Processes and Supply Chains (11th Edition)
The best fits using exponential smoothing, trend analysis, and linear regression for the given data. Introducti...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
The following gives the number of paints of type B blood used at Woodlawn Hospital in the past 6 weeks. a. Fore...
Operations Management: Sustainability and Supply Chain Management (12th Edition)
The following gives the number of paints of type B blood used at Woodlawn Hospital in the past 6 weeks. a. Fore...
Operations Management
What is precedent, and how does it affect common law?
Business in Action
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The activities in the following table describe the construction of a new house. Construct the associated project network ACTIVITY PREDECESSORS DURATION (WEEKS) a Create a spreadsheet to calculate and summarize the earliest and latest start and finish times, the slack for each activity, and the critical activities. (USING EXCEL ONLY, Vlookup, ISERR etc functions) b. Make a gantt chart.arrow_forwardBased on the given set of activities answer the following: 1. Develop a precedence for each of the activity based on the information provided in the case. 2. Draw a network diagram and also calculate the forward and the backward pass for each of the activities. 3. Identify the paths as well as the critical path for the given project and also determine the slack time for each activity. Note: This question is related to Project Management Course.arrow_forwardConstruct a project network for the following project. The project is completed when activities F and G are both complete. Activity A B C D E F G Immediate Predecessor _ _ A A C,B C,B D,Earrow_forward
- A plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below.ActivityDuration (days)Preceding activitiesA3NoneB3NoneC4AD9AE4B and CRequired:1. Draw a network diagram representing the sequence of activities and the dependence between them.2. Determine how long it will take to complete the job by conducting the forward pass3. By conducting the backward pass, identify the critical path and the non-critical path(s).Note:The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.arrow_forward1. A project has been defined to contain the following list of activities along with their required times for completion. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.arrow_forwardThe fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in Chicago, their durations, and what activities each must precede: a) Draw an AOA diagram of the project, including activity durations.b) Define the critical path, listing all critical activities in chronological order.c) What is the project completion time (in weeks)?d) What is the slack (in weeks) associated with any and all noncritical paths through the project?arrow_forward
- The Industrial and Systems Engineering Department at Sun University is moving from its old building to a new building. The move must be completed within the 14-day period between semesters. A list of tasks (activities) has been prepared. The activities and precedence requirements are presented in the table below. Three time estimates (in days) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) Perform a forward pass and backward pass through the network to determine the critical path, and the expected duration of the project (b) What completion time should the department specify in its proposal in order to be 85% sure that it will complete the project on time? Activity Activity description Immediate predecessor Optimistic time (days) Most likely time (days) Pessimistic time (days) 1 Initiate move - 0 0 0 2 Prepare new building space 1 2 4 6 3 Pack faculty files and books 1 3 4 5 4…arrow_forwardDO THE FOLLOWING:1. Draw a network diagram representing the project. Put the node numbers in circles and draw arrowsfrom node to node, labelling each arrow with the activity letter and estimated time.2. Identify all the paths on the network diagram and note how long they are.3. What is the critical path for this project and how long is it?4. What is the shortest possible time needed to complete this project?arrow_forwardThe following table lists the activities for a small part of a project with various durations and dependencies. Fill in the PERT Average duration column.arrow_forward
- Canesta Company is working on a project with the following network: a) Determine the earliest and latest activity times and slack for each activity. b) Determine the duration of the project and the critical path.arrow_forwardBased on the given set of activities answer the following: 1. Develop a precedence for each of the activity based on the information provided in the case. 2. Draw a network diagram and also calculate the forward and the backward pass for each of the activities. 3. Identify the paths as well as the critical path for the given project and also determine the slack time for each activity.arrow_forwardConstruct a Gantt chart for the following set of activities and indicate the project completion time and slack for each activity:arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY