Question
Chapter 9, Problem 7MC
To determine
Direct material price variance is the difference between the actual purchase price of raw material and budgeted purchase price of the raw material.
Direct material quantity variance means the difference of actual quantity usage of raw material in the production and budgeted raw material usage in the production. If the actual usage is higher than budgeted then this variance is unfavorable variance.
To choose:
The correct option that indicates the direct material price (F) variance and unfavorable direct material quantity variance.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Connect 1-Semester Access Card for Managerial Accounting
Ch. 9 - Briefly describe the difference between budgetary...Ch. 9 - What are standard costs? When are they set?Ch. 9 - Prob. 3QCh. 9 - Prob. 4QCh. 9 - Prob. 5QCh. 9 - Prob. 6QCh. 9 - Prob. 7QCh. 9 - Prob. 8QCh. 9 - Prob. 9QCh. 9 - How do the master budget, flexible budget, and...
Ch. 9 - Prob. 11QCh. 9 - What type of variance is calculated by comparing...Ch. 9 - Prob. 13QCh. 9 - Prob. 14QCh. 9 - Prob. 15QCh. 9 - Prob. 16QCh. 9 - Prob. 17QCh. 9 - Prob. 18QCh. 9 - What are the two variable overhead variances? What...Ch. 9 - Prob. 20QCh. 9 - Prob. 21QCh. 9 - Prob. 22QCh. 9 - Prob. 23QCh. 9 - Prob. 1MCCh. 9 - Prob. 2MCCh. 9 - Variances are always noted as favorable or...Ch. 9 - What type of budget is ail integrated set of...Ch. 9 - Prob. 5MCCh. 9 - Prob. 6MCCh. 9 - Prob. 7MCCh. 9 - Prob. 8MCCh. 9 - Prob. 9MCCh. 9 - Prob. 10MCCh. 9 - Prob. 1MECh. 9 - Creating Grading Scale Based on Ideal, Tight but...Ch. 9 - Prob. 3MECh. 9 - Prob. 4MECh. 9 - Calculating Unknown Values for Direct Labor...Ch. 9 - Prob. 6MECh. 9 - Prob. 7MECh. 9 - Prob. 8MECh. 9 - Prob. 9MECh. 9 - Prob. 10MECh. 9 - Prob. 11MECh. 9 - Prob. 12MECh. 9 - Preparing Journal Entries to Record Direct Labor...Ch. 9 - Prob. 1ECh. 9 - Prob. 2ECh. 9 - Interpreting Direct Materials Price, Quantity...Ch. 9 - Calculating Direct Materials and Direct Labor...Ch. 9 - Calculating Direct Materials and Direct Labor...Ch. 9 - Prob. 6ECh. 9 - Prob. 7ECh. 9 - Prob. 8ECh. 9 - Prob. 9ECh. 9 - Preparing Journal Entries to Record Direct...Ch. 9 - Prob. 11ECh. 9 - Calculating Fixed Manufacturing Overhead Spending,...Ch. 9 - Prob. 13ECh. 9 - Prob. 14ECh. 9 - Prob. 15ECh. 9 - Prob. 16ECh. 9 - Prob. 17ECh. 9 - Determining Actual, Standard Costs, and Variances...Ch. 9 - Prob. 1.1GAPCh. 9 - Prob. 1.2GAPCh. 9 - Prob. 1.3GAPCh. 9 - Prob. 2.1GAPCh. 9 - Prob. 2.2GAPCh. 9 - Prob. 2.3GAPCh. 9 - Prob. 3.1GAPCh. 9 - Prob. 3.2GAPCh. 9 - Prob. 3.3GAPCh. 9 - Prob. 4GAPCh. 9 - Prob. 5.1GAPCh. 9 - Prob. 5.2GAPCh. 9 - Prob. 5.3GAPCh. 9 - Prob. 6.1GAPCh. 9 - Prob. 6.2GAPCh. 9 - Prob. 6.3GAPCh. 9 - Prob. 7.1GAPCh. 9 - Prob. 7.2GAPCh. 9 - Prob. 7.3GAPCh. 9 - Preparing Journal Entries to Record Fixed...Ch. 9 - Prob. 9.1GAPCh. 9 - Prob. 9.2GAPCh. 9 - Prob. 10.1GAPCh. 9 - Prob. 10.2GAPCh. 9 - Prob. 1.1GBPCh. 9 - Prob. 1.2GBPCh. 9 - Prob. 1.3GBPCh. 9 - Prob. 2.1GBPCh. 9 - Prob. 2.2GBPCh. 9 - Prob. 2.3GBPCh. 9 - Prob. 3.1GBPCh. 9 - Prob. 3.2GBPCh. 9 - Prob. 3.3GBPCh. 9 - Prob. 4GBPCh. 9 - Prob. 5.1GBPCh. 9 - Prob. 5.2GBPCh. 9 - Prob. 5.3GBPCh. 9 - Prob. 6.1GBPCh. 9 - Prob. 6.2GBPCh. 9 - Prob. 6.3GBPCh. 9 - Prob. 7.1GBPCh. 9 - Prob. 7.2GBPCh. 9 - Prob. 7.3GBPCh. 9 - Prob. 8GBPCh. 9 - Prob. 9.1GBPCh. 9 - Prob. 9.2GBPCh. 9 - Calculating Variable Manufacturing Overhead, Fixed...Ch. 9 - Prob. 9.4GBPCh. 9 - Prob. 9.5GBPCh. 9 - Prob. 9.6GBPCh. 9 - Prob. 10.1GBPCh. 9 - Prob. 10.2GBP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Madison Company uses the following rule to determine whether direct labor efficiency variances ought to be investigated. A direct labor efficiency variance will be investigated anytime the amount exceeds the lesser of 12,000 or 10 percent of the standard labor cost. Reports for the past five weeks provided the following information: Required: 1. Using the rule provided, identify the cases that will be investigated. 2. Suppose that investigation reveals that the cause of an unfavorable direct labor efficiency variance is the use of lower quality direct materials than are usually used. Who is responsible? What corrective action would likely be taken? 3. Suppose that investigation reveals that the cause of a significant favorable direct labor efficiency variance is attributable to a new approach to manufacturing that takes less labor time but causes more direct materials waste. Upon examining the direct materials usage variance, it is discovered to be unfavorable, and it is larger than the favorable direct labor efficiency variance. Who is responsible? What action should be taken? How would your answer change if the unfavorable variance were smaller than the favorable?arrow_forwardSommers Company uses the following rule to determine whether materials usage variances should be investigated: A materials usage variance will be investigated anytime the amount exceeds the lesser of 12,000 or 10% of the standard cost. Reports for the past 5 weeks provided the following information: Required: 1. Using the rule provided, identify the cases that will be investigated. 2. CONCEPTUAL CONNECTION Suppose investigation reveals that the cause of an unfavorable materials usage variance is the use of lower-quality materials than are normally used. Who is responsible? What corrective action would likely be taken? 3. CONCEPTUAL CONNECTION Suppose investigation reveals that the cause of a significant unfavorable materials usage variance is attributable to a new approach to manufacturing that takes less labor time but causes more material waste. Examination of the labor efficiency variance reveals that it is favorable and larger than the unfavorable materials usage variance. Who is responsible? What action should be taken?arrow_forwardRefer to the information for Cinturon Corporation on the previous page. Required: 1. Break down the total variance for labor into a rate variance and an efficiency variance using the columnar and formula approaches. 2. CONCEPTUAL CONNECTION As part of the investigation of the unfavorable variances, the plant manager interviews the production manager. The production manager complains strongly about the quality of the leather strips. He indicates that the strips are of lower quality than usual and that workers have to be more careful to avoid a belt with cracks and more time is required. Also, even with extra care, many belts have to be discarded and new ones produced to replace the rejects. This replacement work has also produced some overtime demands. What corrective action should the plant manager take?arrow_forward
- Which of the following is the most likely explanation for an unfavorable materials usage variance and a favorable labor wage variance? a. The new labor contract increased wages. b. Higher quality materials were purchased, resulting in less waste. c. The company experience labor turnover and newer, less experienced workers were hired. d. A new supplier offered a lower price for materials.arrow_forwardRefer to the information for Cinturon Corporation on the previous page. Required: 1. Break down the total variance for materials into a price variance and a usage variance using the columnar and formula approaches. 2. CONCEPTUAL CONNECTION Suppose the Boise plant manager investigates the materials variances and is told by the purchasing manager that a cheaper source of leather strips had been discovered and that this is the reason for the favorable materials price variance. Quite pleased, the purchasing manager suggests that the materials price standard be updated to reflect this new, less expensive source of leather strips. Should the plant manager update the materials price standard as suggested? Why or why not?arrow_forwardVariance interpretation Vanadium Audio Inc. is a small manufacturer of electronic musical instruments. The plant manager received the following variable factory overhead report for the past month of operations: Actual units produced: 15,000 (90% of practical capacity) The plant manager is not pleased with the 12,320 unfavorable variable factory overhead controllable variance and has come to discuss the matter with the controller. The following discussion occurred: Plant Manager: I just received this factory report for the latest month of operations. Im not very pleased with these figures. Before these numbers go to headquarters, you and I need to reach an understanding. Controller: Go ahead. Whats the problem? Plant Manager: Whats the problem? Well, everything. Look at the variance. Its too large. If I understand the accounting approach being used here, you are assuming that my costs are variable to the units produced. Thus, as the production volume declines, so should these costs. Well, I dont believe these costs are variable at all. I think they are fixed costs. As a result, when we operate below capacity, the costs really dont go down. Im being penalized for costs I have no control over. I need this report to be redone to reflect this fact. If anything, the difference between actual and budget is essentially a volume variance. Listen, I know that youre a team player. You really need to reconsider your assumptions on this one. Assume you are the controller. Write a memo responding to the plant manager.arrow_forward
- Ed Co. manufactures two types of O rings, large and small. Both rings use the same material but require different amounts. Standard materials for both are shown. At the beginning of the month, Edve Co. bought 25,000 feet of rubber for $6.875. The company made 3,000 large O rings and 4,000 small O rings. The company used 14,500 feet of rubber. A. What are the direct materials price variance, the direct materials quantity variance, and the total direct materials cost variance? B. If they bought 10,000 connectors costing $310, what would the direct materials price variance be for the connectors? C. If there was an unfavorable direct materials price variance of $125, how much did they pay per toot for the rubber?arrow_forwardSitka Industries uses a cost system that carries direct materials inventory at a standard cost. The controller has established these standards for one ladder (unit): Sitka Industries made 3,000 ladders in July and used 8,800 pounds of material to make these units. Smith Industries bought 15,500 pounds of material in the current period. There was a $250 unfavorable direct materials price variance. A. How much in total did Sitka pay for the 15,500 pounds? B. What is the direct materials quantity variance? C. What is the total direct material cost variance? D. What ii 9,500 pounds were used to make these ladders, what would be the direct materials quantity variance? E. It there was a $340 favorable direct materials price variance, how much did Sitka pay for the 15,500 pounds of material?arrow_forwardMarten Company has a cost-benefit policy to investigate any variance that is greater than 1,000 or 10% of budget, whichever is larger. Actual results for the previous month indicate the following: The company should investigate: a. neither the materials variance nor the labor variance. b. the materials variance only. c. the labor variance only. d. both the materials variance and the labor variance.arrow_forward
- Carlo Lee Corp. has established the following standard cost per unit: Although 10,000 units were budgeted, only 8,800 units were produced. The purchasing department bought 55,000 lb of materials at a cost of $123,750. Actual pounds of materials used were 54,305. Direct labor cost was $186,550 for 18,200 hours worked. Required: Make journal entries to record the materials transactions, assuming that the materials price variance was recorded at the time of purchase. Make journal entries to record the labor variances.arrow_forwardA manufacturer planned to use $45 of variable overhead per unit produced, but in the most recent period, it actually used $47 of variable overhead per unit produced. During this same period, the company planned to produce 200 units but actually produced 220 units. What is the variable overhead spending variance?arrow_forwardIn all of the exercises involving variances, use F and U to designate favorable and unfavorable variances, respectively. E8-1 through E8-5 use the following data: The standard operating capacity of Tecate Manufacturing Co. is 1,000 units. A detailed study of the manufacturing data relating to the standard production cost of one product revealed the following: 1. Two pounds of materials are needed to produce one unit. 2. Standard unit cost of materials is 8 per pound. 3. It takes one hour of labor to produce one unit. 4. Standard labor rate is 10 per hour. 5. Standard overhead (all variable) for this volume is 4,000. Each case in E8-1 through E8-5 requires the following: a. Set up a standard cost summary showing the standard unit cost. b. Analyze the variances for materials and labor. c. Make journal entries to record the transfer to Work in Process of: 1. Materials costs 2. Labor costs 3. Overhead costs (When making these entries, include the variances.) d. Prepare the journal entry to record the transfer of costs to the finished goods account. Standard unit cost; variance analysis; journal entries 1,000 units were started and finished. Case 1: All prices and quantities for the cost elements are standard, except for materials cost, which is 8.50 per pound. Case 2: All prices and quantities for the cost elements are standard, except that 1,900 lb of materials were used.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license