a)
To determine: The time taken for first 3 corneal transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
To determine: The time taken for first 6 corneal transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time taken for first 8 corneal transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
d)
To determine: The time taken for first 16 corneal transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Want to see the full answer?
Check out a sample textbook solutionChapter E Solutions
OPERATIONS MANAGEMENTW/OML LAB >C<
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 41 hours. The contractor estimates a 90 percent learning rate. Part 2 a. How long do you estimate the time required to install the second pool? enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardAssuming an 80 percent learning rate, if the 4th unit takes 100 hours to produce, the 16th unit should take how long to produce?arrow_forwardThe time to assemble the first unit on a production line is 12. hours. The learning rate is 0.94. Approximately how long will it take for the seventh unit to be assembled? The number of hours needed for the seventh unit to be assembled is ? hours. (Round to one decimal place.)arrow_forward
- If the first unit of a product took 25 minutes to produce and the learning curve rate is 80%, how much time will the production of the 100th unit take?arrow_forwardThe time to asaemble the first unit on a production line is 19 hours. The learning rate is 0.85. Approximately how long will it take for the fifth unit to be assembled?arrow_forwardMa1. DRILL is a company specialized in the design and fabrication of oil drilling rigs. The sales department just received two orders from two companies A and B. The production manager of DRILL decided to deliver the first 3 fabricated rigs to Company A and the next 4 fabricated rigs (rigs 4 to 7) to company B. It took DRILL company 50,000 labor-hours to manufacture the first oil drilling rig. Assume that DRILL experiences a learning rate of 90%. At a labor rate of $100 per hour, what is the labor cost that should be charged to each company (A&B)?arrow_forward
- Omega Technology is starting production of a new supercomputer for use in large research universities It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent How many labor hours should it expect the second unit to require to manufacture?arrow_forwardSuppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions: If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 it takes hours For x = 3 it takes hours If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 and a 65% LC, it takes hours For x = 3 and a 65% LC, it takes hours For x = 2 and a 95% LC, it takes hours For x = 3 and a 95% LC, it takes hoursarrow_forwardIf a company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours respectively. What is the appropriate learning curve? Explain and show your answer.arrow_forward
- McDonald's, the fast-food restaurant, is known for high employee turnover, high quality, and low costs. Using your knowledge of the learning phenomenon, how does McDonald's get high quality and low costs when it has so much employee turnover?arrow_forwardLearning Curves 1. Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 54 hours to complete. d) What is the average time per unit for producing the last 10 units (#31 - #40)?arrow_forwardLearning Curves 1. Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 54 hours to complete. a) What is the learning rate? b) What is the estimated time for the 40th unit? c) What is the estimated total time for producing all 40 units? d) What is the average time per unit for producing the last 10 units (#30 - #40)?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.