a)
To determine: The time taken for completing the 1st unit.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
To determine: The time taken for completing the 8th unit.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time taken for completing all the 8 units.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Want to see the full answer?
Check out a sample textbook solutionChapter E Solutions
OPERATIONS MANAGEMENTW/OML LAB >C<
- A job is known to have a learning percentage equal to 82. If the first unit had a completion time of20 hours, estimate the times that will be needed to complete the third and fourth units.arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forwardAn aircraft company has an order to refurbish the interiors of 18 jet aircraft. The work has a learning curve percentage of 80. On the basis of experience with similar jobs, the industrial engineering department estimates that the first plan will require 300 hours to refurbish. Estimate the amount of time needed to complete: The 5th plane, The first 5 planes, All 18 planes. For a, use logarithmic approach formula, for b and c, use learningcurve approach formula.arrow_forward
- Aqeel bought 6 bookcases for his place. Each required unpacking of parts and assembly, which included some nailing and bolting. Aqeel completed the first bookcase in 5 hours and the second in 4 hours. 1-What is his learning rate (k)? 2-What is his learning-curve value of b? 3-Assuming that the same rate continues, how long will the 3rd, 4th, 5th, and 6th bookcases take? Y3 = hours Y4 = hours Y5 = hours Y6 = hours 5-How long will take him to finish all the 6 cases? It will take him hours.arrow_forwardThe product TRX takes 9.99 hours for production of 1 unit, where learning curve rate is 77% and what will be the total time taken by 8th unit of product TRX using incremental unit time method ?arrow_forwardProduction Airplanes is negotiating a contract for the production of 20 small jet aircraft. The initial jet required the equivalent of 400 days of direct labor. The learning percentage is 80 percent. Estimate the expected number of days of direct labor fora. The 20th jetb. All 20 jetsc. The average time for 20 jetsarrow_forward
- NUBD Company is planning to introduce a new product with an 90% learning rate for production for batches of 1,000 units. The variable labor costs are 30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are 10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 2,000 units based on the cumulative average-time learning curve?arrow_forwardIn yuyox ltd the first 71 units takes 92 hours to be produced where learning curve is 83% , calculate how much time it will take to produce 568 units using the wrights model ?arrow_forwardNUBD Company is planning to introduce a new product with an 85 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 2,000 units based on the cumulative average-time learning curve?arrow_forward
- The first item of a batch took 5 hours to produce. If the learning parameter is 80%, how much time would it take to produce the first seven items.arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardA company estimates that it will take 20 hours and 42 direct labor hours to construct the 50th and 5th respectively, under an 80% learning curve. how long does it take to make the first unit in the batch? Please please correct answer dont copypastearrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.