Question
Chapter E, Problem 9P
Summary Introduction
To determine: The time taken to prepare the 15th lecture.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A subcontractor is responsible for outfitting six satellites that will be used for solar research. Fourof the six have been completed in a total of 600 hours. If the crew has a 75 percent learning curve,how long should it take them to finish the last two units?
A subcontractor is responsible for outfitting six satellites that will be used for solar research. Fourof the six have been completed in a total of 600 hours. If the crew has a 75 percent learning curve, how long should it take them to finish the last two units?
The company rtx ltd. takes 27 hours to produce 6 units of a product and learning curve rate is 88%, compute the total time for 18 units of product using cumulative average method ?
Chapter E Solutions
By Jay Heizer Barry Render Operations Management, Sustainability and Supply Chain Management (11th) [Paperback]
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 26PCh. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Similar questions
- The product TRX takes 9.99 hours for production of 1 unit, where learning curve rate is 77% and what will be the total time taken by 8th unit of product TRX using incremental unit time method ?arrow_forwardThe product tesla takes 89.88 hours for production of 1 unit, where learning curve rate is 87% and what will be the total time taken by 16th unit of product tesla using incremental unit time method ?arrow_forwardIn yuyox ltd the first 71 units takes 92 hours to be produced where learning curve is 83% , calculate how much time it will take to produce 568 units using the wrights model ?arrow_forward
- The fifth unit of a 25-unit job took 14.5 hours to complete. If a 90 percent learning curve is appropriate:a. How long should it take to complete the last unit?b. How long should it take to complete the 10th unit?c. Estimate the average time per unit for the 25 units.arrow_forwardGiven the following information from an assembly task: First cycle time: 35 seconds Learning rate of 90% a. Determine the predicted performance time of the 200th b. Determine the number of cycles it will take to reach the standard time of 14 secondsarrow_forwardoperations management (learning curves) In Alcc ltd. The first 18 units takes 17 hours for production with learning curve rate is 74% , calculate how much time it wilm take to produce 272 units using wright model ?arrow_forward
- A company estimates that it will take 20 hours and 42 direct labor hours to construct the 50th and 5th respectively, under an 80% learning curve. how long does it take to make the first unit in the batch? Please please correct answer dont copypastearrow_forwardA company estimates that it will take 20 hours and 42 direct labor hours to construct the 50th and 5th respectively, under an 80% learning curve. how long does it take to make the first unit in the batch?arrow_forwardAn assembly operation has a 90 percent learning curve. The line has just begun work on a new item; the initial unit required 28 hours. Estimate the time that will be needed to complete:a. The first five unitsb. Units 20 through 25arrow_forward
- Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 18 transplants under great scrutiny and at no cost to the patients. The very first transplant, just completed, required 28 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: Unit number 5 75% Unit time: .513 Total time: 3.459 80% Unit number 5 Unit time: .596 Total time: 3.738 85% Unit number 5 Unit time: .686 Total time: 4.031 Unit number 18 75% Unit time: .301 Total time: .8.245 Unit number 18 80% Unit time: 3.94 Total Time: 9.716 Unit number 18 85% Unit time: .508 Total time: 11.405 a) the 5th transplant = 14.36 hours b) the first 5 transplant = ? hours (round your response to two decimal places)arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forwardNational Company is planning to introduce a new product with an 85 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative average time per batch using the incremental unit-time learning curve for 2,000 units?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.