Summary Introduction
To determine: The time taken for completing all the 7 units.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Hanna’s Super Service Burgers and Fries fast-food restaurant trains its new employees (all of which are part-time)for three days to assemble its different burgers. The mosttime-consuming item to assemble is the Super MegaBurger because it includes a lot of ingredients. After threedays of training, an employee can assemble his or her firstMega-Burger as a regular employee in an average of 126seconds. The learning curve for this assembly operation isestimated to be 85%, and no additional learning will takeplace after assembly of the eightieth Mega-Burger. Determine how many seconds will be required for an employeeto assemble his or her eightieth Mega-Burger.
A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 21 hours. The contractor estimates a 90 percent learning rate.
Part 2
a. How long do you estimate the time required to install the second pool?
enter your response here
hours. (Enter your response rounded to two decimal places.)
Part 3
b. How long do you estimate the time required to install the fourth pool?
enter your response here
hours. (Enter your response rounded to two decimal places.)
If the first unit of a product took 25 minutes to produce and the learning curve rate is 80%, how much time will the production of the 100th unit take?
Chapter E Solutions
By Jay Heizer Barry Render Operations Management, Sustainability and Supply Chain Management (11th) [Paperback]
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 26PCh. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Suppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions: If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 it takes hours For x = 3 it takes hours If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 and a 65% LC, it takes hours For x = 3 and a 65% LC, it takes hours For x = 2 and a 95% LC, it takes hours For x = 3 and a 95% LC, it takes hoursarrow_forwardManceville Air has just produced the first unit of a large industrial compressor that incorporated new technology in the control circuits and a new internal venting system. The first unit took 116 hours of labor to manufacture. The company knows from past experience that this labor content will decrease significantly as more units are produced. In reviewing past production data, it appears that the company has experienced a 80% learning curve when producing similar designs. The company is interested in estimating the total time to complete the next 7 units. Your job as the production cost estimator is to prepare the estimate. Refer to table below: 80% 80% 85% Unit Number (N) Unit Time Total Time Unit Time 85% Total Time 90% Unit Time 90% Total Time 8 .512 5.346 .614 5.936 .729 6.574 Total manufacturing time for the= Manufacturing time for the last 7 units (i.e., units 2 thru 8)=arrow_forwardWhat is an example of the learning curve for a business operation where the average costs were reduced due to cumulative production experience?arrow_forward
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 41 hours. The contractor estimates a 90 percent learning rate. Part 2 a. How long do you estimate the time required to install the second pool? enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardIf a company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours respectively. What is the appropriate learning curve? Explain and show your answer.arrow_forwardIf it took 410 hours to produce the first unit of a product, and the learning curve is 90%, how long will it take to produce units 12 through 25???arrow_forward
- Omega Technology is starting production of a new supercomputer for use in large research universities. It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent. How many labor hours should it expect in manufacturing the second unit?arrow_forwardYou are asked to do a learning curve analysis as part of your internship project, but you discover that the data is pretty slim. Unfortunately you don't have time to do more field work and you have to come up with the best estimate based on the available data. Here's what you know: It took 98.71 minutes to complete the seventh unit and only 89.35 minutes to complete the twelfth unit. What is your best estimate of the Learning Rate for this process?arrow_forwardThe fifth unit of a 10-unit job took five hours to complete. The sixth unit has been worked on fortwo hours, but is not yet finished. Estimate the additional amount of time needed to finish the10-unit job if the work has a 75 percent learning ratearrow_forward
- A job is known to have a learning percentage equal to 82. If the first unit had a completion time of20 hours, estimate the times that will be needed to complete the third and fourth units.arrow_forwardOmega Technology is starting production of a new supercomputer for use in large research universities It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent How many labor hours should it expect the second unit to require to manufacture?arrow_forwardAssuming an 80 percent learning rate, if the 4th unit takes 100 hours to produce, the 16th unit should take how long to produce?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.