Concept explainers
a)
To determine: The time taken for the 5th liver transplant.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
To determine: The time taken for first 5 transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
c)
To determine: The time taken for the 18th liver transplant.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
d)
To determine: The time taken for all 18 transplants.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Want to see the full answer?
Check out a sample textbook solutionChapter E Solutions
By Jay Heizer Barry Render Operations Management, Sustainability and Supply Chain Management (11th) [Paperback]
- National Company is planning to introduce a new product with an 90 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the total labor cost for the cumulative total time using the incremental unit-time learning curve to produce 2,000 units?arrow_forwardNUBD Company is planning to introduce a new product with an 90% learning rate for production for batches of 1,000 units. The variable labor costs are 30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are 10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 2,000 units based on the cumulative average-time learning curve?arrow_forwardAqeel bought 6 bookcases for his place. Each required unpacking of parts and assembly, which included some nailing and bolting. Aqeel completed the first bookcase in 5 hours and the second in 4 hours. 1-What is his learning rate (k)? 2-What is his learning-curve value of b? 3-Assuming that the same rate continues, how long will the 3rd, 4th, 5th, and 6th bookcases take? Y3 = hours Y4 = hours Y5 = hours Y6 = hours 5-How long will take him to finish all the 6 cases? It will take him hours.arrow_forward
- Do you think learning curve analysis has an application in a service business like a restaurant? Why or why not?arrow_forwardYou need to develop a labor time estimate for a customer order of 50 network installations. It is estimated that the first installation will require 75 labor hours and a learning curve of 85 percent is expected. a. How many labor hours are required for the 25th installation?b. How many labor hours are required to complete all 50 installations? c. If the average labor cost is $28 per hour, what is the total labor cost for installing all the networks?d. How many workers are needed to complete the job in a week? Assuming each worker works 8 hours per day 5 days per week. Show breakdown of workarrow_forwardLearning curve analysis has an application in a service business like a restaurant? Why or why not?arrow_forward
- The fifth unit of a 25-unit job took 14.5 hours to complete. If a 90 percent learning curve is appropriate:a. How long should it take to complete the last unit?b. How long should it take to complete the 10th unit?c. Estimate the average time per unit for the 25 units.arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardOn RainTite Window’s manual assembly line, a newemployee can usually assemble their first window unit in30 minutes. Management assumes a 90 percent learning rate.a. How long should a new employee take to assemble theirsecond window if management is correct in their assump-tion? How long should the 16th window take?b. On RainTite’s semi-automated line, a new employeetakes 45 minutes to assemble their first window; however,the learning rate is 75 percent. At how many windowsproduced will the semi-automated line’s employee takeless time to produce a window than an employee on themanual line?arrow_forward
- In essay form,,, what do you think is the relevance of learning curve to work productivity? Thank youuuuu :(((arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forwardA subcontractor is responsible for outfitting six satellites that will be used for solar research. Fourof the six have been completed in a total of 600 hours. If the crew has a 75 percent learning curve,how long should it take them to finish the last two units?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.