Question
Chapter 10, Problem 19P
a
Summary Introduction
Interpretation:
Concept Introduction:
The first-come, first-served (FCFS) rule gives the job arriving at the workstation first the highest priority.
The earliest due date (EDD) rule gives the job with the earliest due date based on assigned due dates the highest priority.
b
Summary Introduction
To determine:
Performance of the two rules.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers.
Job
Date job received
Productiondays needed
Date job due
BR-02
228
15
300
CX-01
225
25
270
DE-06
230
35
320
RG-05
235
40
360
SY-11
231
30
310
a. Complete the following table. (Show your supporting calculations.)
b.Which dispatching rule has the best score for flow time?
c. Which dispatching rule would you select? Support your decision.
Currently a company that designs Web sites has six customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table.
Job
Time Since Order Arrived
(days ago)
Processing Time
(days)
Due Date
(days from now)
A
6
18
48
B
4
22
52
C
1
30
70
D
10
14
28
E
7
12
56
F
5
20
62
Develop a schedule by using the first-come, first-served (FCFS) rule and calculate the average flow time and average days past due for the schedule.
Develop a schedule by using the earliest due date (EDD) rule and calculate the average flow time and average days past due for the schedule.
Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.
A customer calls requesting that a service technician be sent to her residence immediately to fix her cable box. It is late in the evening, and service technicians cannot be sent out at this time. You see that she has an appointment for a service technician to be sent tomorrow, but she is becoming more upset because she thinks her need is urgent.
Chapter 10 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 10 - List the types of costs incurred when employees...Ch. 10 - Prob. 2DQCh. 10 - Prob. 3DQCh. 10 - Explain why management should be concerned about...Ch. 10 - The Barberton Municipal Division of Road...Ch. 10 - Bob Canton’s golf camp estimates the following...Ch. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Management at the Kerby Corporation has determined...Ch. 10 - Gretchen’s Kitchen is a fast-food restaurant...
Ch. 10 - Prob. 7PCh. 10 - Tax Prep Advisers, Inc. has forecasted the...Ch. 10 - Climate Control, Inc. makes expedition-quality...Ch. 10 - Prob. 11PCh. 10 - Gemini Inc. is using the Sales and Operations...Ch. 10 - Gerald Glynn manages the Michaels Distribution...Ch. 10 - Cara Ryder manages a ski school in a large resort...Ch. 10 - Prob. 15PCh. 10 - Prob. 17PCh. 10 - The Hickory Company manufactures wooden desks....Ch. 10 - Prob. 19PCh. 10 - The Mowry Machine Shop still has five jobs to be...Ch. 10 - If we use the same number of workers in each...Ch. 10 - Prob. 2AMECh. 10 - Prob. 3AMECh. 10 - Suppose the overtime cost is $3,300. What happens...Ch. 10 - Suppose the undertime cost is the same as the...Ch. 10 - Prob. 6AMECh. 10 - Prob. 1VCCh. 10 - Does Starwood employ a chase, level, or mixed...Ch. 10 - How would staffing for the opening of a new hotel...Ch. 10 - Explain the alternatives available to Darlene Fry...Ch. 10 - Prob. 2C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Six patients are waiting in a hospital emergency room to receive care for various complaints, ranging from a sprained ankle to a gunshot wound. The patients are numbered in the sequence that they arrived and are given a priority weighting based on the severity of the problem. There is only one doctor available.Consider the situation of the emergency room mentioned. Determine the sequence in which patients should be treated in order to minimize the weighted value of the mean flow time.arrow_forwardThe day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due days. Make a comment.arrow_forwardCurrently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table. The customers are ready to be scheduled today, which is the start of day 190. Customer Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Upper AA 6 18 66 Upper BB 3 24 58 Upper CC 2 32 100 Upper DD 10 22 26 Upper EE 8 12 50 a. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average days past due. Part 2 Using the FCFS (first come, first served) decision rule for sequencing the customers, the order is: Sequence 1 2 3 4 5 Customer D E A B C Part 3 Using…arrow_forward
- where the consulting company has five jobs in its backlog. Create a schedule usingthe EDD rule, calculating the average days past due and flow time. In this case, does EDD outperformthe FCFS rule?arrow_forwardThe first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD. Job ProcessingTime at EngineLathe (hours) TimeRemainingUntil Due Date(days) Number ofOperationsRemaining Shop TimeRemaining(days) CR S/RO 1 2 3 4 2.3 10.5 6.2 15.6 15 10 20 8 10 2 12 5 6.1 7.8 14.5 10.2 2.46 1.28 1.38 0.78 0.89 1.10 0.46 -0.44arrow_forwardClasses are scheduled. After students request courses, a programme will determine the optimum schedule. The school thinks it can't find the best schedule soon. Instead, they use a simpler method to construct a reasonable but non-optimal schedule quicker. Which principle does this option demonstrate?arrow_forward
- Mike’s Auto Body Shop has five cars waiting to be repaired. The shop is quite small, so only one car can be repaired at a time. The number of days required to repair each car and the promised date for each are given in the following table. (given) Mike has agreed to provide a rental car to each customer whose car is not repaired on time. Compare the performance of the four sequencing rules FCFS, SPT, EDD, and CR relative to minimizing average tardiness.arrow_forwardA mortgage service office has the following four activities involved in approving a loan application. Note that a working day is 8 hours and there are 60 minutes in one hour. Activity Time (minutes) A. Property survey 24 B. Credit report 19 C. Title search 18 D. Final decision 20 The office has three employees, activities A, B and C are combined together and assigned to two employees, while the other employee is responsible for the last activity D. Under this setting, what would be the maximum number of loan applications the office can process per day? Numbers only, keep three decimals if not exact, either round up or down is okarrow_forwardIn a few words, explain how to prevent a process getting starved in priority scheduling.arrow_forward
- On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .arrow_forwardEight jobs have arrived in the following order: Job Processing Time Due Date 1 7 23 2 3 9 3 5 8 4 2 11 5 6 16 6 9 18 7 14 40 8 4 31 Find and compare the performance measures for the following sequencing rules using the Excel Sequencing template. Round your answers to two decimal places. Process in the order they have arrived Flow Time Lateness Tardiness Averagearrow_forwardThe Neptune’s Den Machine Shop specializes in overhauling outboard marine engines. Some engines require replacement of broken parts, whereas others need a complete overhaul. Currently, five engines with varying problems are awaiting service. The best estimates for the labor times involved and the promise dates (in number of days from today) are shown in the following table. Customers usually do not pick up their engines early.Engine Time Since Order Arrived (days) Processing Time, Including Setup (days) Promise Date (days from now) Engine Time Since OrderArrived (days) Processing Time,Including Setup (days) Promise Date (daysfrom now) 50-hp Evinrude 7-hp Johnson 100-hp Mercury 50-hp Honda 75-hp Nautique 4 6 8 1 15 5 4 10 1 3 8 15 12 20 10 a. Develop separate schedules by using the SPT and EDD rules.b. Compare the two schedules on the basis of average flow time, percentage of past due jobs, and maximum past due days for any engine.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY