Question
Book Icon
Chapter 10, Problem 8PA

(a)

Summary Introduction

Interpretation:The maximum capacity of store per day needs to be calculated with the help of given data.

Concept Introduction: Capacity measurement is an important concept which helps companies to make long term and short-term decisions related to capacity and thus plan for contingencies.

(a)

Expert Solution
Check Mark

Explanation of Solution

A.

Given Information:

There are 5 regular lines ad 1 express lines.

Average time a customer spends in a regular line = 11 min which means that one regular line can handle 5.45 customers per day.

Average time a customer spends in an express line = 4 min which means that one express line can handle 15 customers per day.

Shift duration = 12 hours per day

Thus,

The capacity of 5 regular lines = 5.45 × 12 × 5 = 327 customers per day

The capacity of 1 express lines = 15 × 12 × 1 = 180 customers per day

Therefore, the maximum capacity of store = (327 + 180) = 507 customers per day.

B.

Summary Introduction

Interpretation:The maximum capacity of store per day needs to be calculated with the help of given data.

Concept Introduction: Capacity measurement is an important concept which helps companies to make long term and short-term decisions related to capacity and thus plan for contingencies.

B.

Expert Solution
Check Mark

Explanation of Solution

Given Information:

There are 5 regular lines ad 1 express lines.

Average time a customer spends in a regular line = 11 min which means that one regular line can handle 5.45 customers per day.

Average time a customer spends in an express line = 4 min which means that one express line can handle 15 customers per day.

Shift duration = 12 hours per day

The store’s capacity by day of the week is as follows:

    PeriodMonday
    HoursNo. of lines openCapacity (customers per day)
    9-12 noon31
    5.45 × 3 × 1 = 16.35
    12-4 PM42
    5.45 × 4 × 2 = 43.6
    4-6 PM23
    5.45 × 2 × 3 = 32.7
    6-9 PM34
    5.45 × 3 × 4 = 65.4
    Total Capacity of Regular Line (Customers per day)158.05

Since the express line is always open, and the capacity is 180 customers per day.

Therefore, the maximum capacity on Monday is 338 customers per day.

Also, the maximum capacity on Tuesday, Wednesday and Thursday will be 338 customers per day as same number of regular lines are open as on Monday.

    PeriodFriday
    HoursNo. of lines openCapacity (customers per day)
    9-12 noon33
    5.45 × 3 × 3 = 49.05
    12-4 PM43
    5.45 × 4 × 3 = 65.4
    4-6 PM25
    5.45 × 2 × 5 = 54.5
    6-9 PM35
    5.45 × 3 × 5 = 81.75
    Total Capacity of Regular Line (Customers per day)250.7

Since the express line is always open, and the capacity is 180 customers per day.

Therefore, the maximum capacity on Friday is 431 customers per day.

    PeriodSaturday
    HoursNo. of lines openCapacity (customers per day)
    9-12 noon35
    5.45 × 3 × 5 = 81.75
    12-4 PM45
    5.45 × 4 × 5 = 109
    4-6 PM23
    5.45 × 2 × 3 = 32.7
    6-9 PM33
    5.45 × 3 × 3 = 49.05
    Total Capacity of Regular Line (Customers per day)272.5

Since the express line is always open, and the capacity is 180 customers per day.

Therefore, the maximum capacity on Saturday is 452.5 customers per day.

    PeriodSunday
    HoursNo. of lines openCapacity (customers per day)
    9-12 noon32
    5.45 × 3 × 2 = 32.7
    12-4 PM44
    5.45 × 4 × 4 = 87.2
    4-6 PM22
    5.45 × 2 × 2 = 21.8
    6-9 PM31
    5.45 × 3 × 1 = 16.35
    Total Capacity of Regular Line (Customers per day)158.05

Since the express line is always open, and the capacity is 180 customers per day.

Therefore, the maximum capacity on Sunday is 338.5 customers per day.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Worthington Hills grocery store has five regular checkout lines and one express line (12 items or less). Based on a sampling study, it takes 12 minutes on the average for a customer to go through the regular line and 6 minutes to go through the express line. The store is open from 9 a.m. to 9 p.m. daily. What is the store's maximum capacity (customers processed per day)? Round your answer down to the nearest whole number.   customers processed per day What is the store's capacity by day of the week if the five regular checkout lines operate according to the schedule below (the express line is always open)? Do not round intermediate calculations. Round your answers down to the nearest whole number.   Hours/Day Mon Tue Wed Thur Fri Sat Sun 9–12 a.m. 1  2 1 2 3 4 2 12-4 p.m. 2  2 2 2 3 5 3 4–6 p.m. 4 * 4 4 3 5 3 2 6-9 p.m. 5  4 4 4 4 3 1 * A "3" means 3 regular checkout lines are open on Monday from 4 to 6 p.m.   The store's capacity by day of the week (customers per…
Worthington Hills grocery store has five regular checkout lines and one express line (12 items or less). Based on a sampling study, it takes 15 minutes on the average for a customer to go through the regular line and 6 minutes to go through the express line. The store is open from 9 a.m. to 9 p.m. daily. What is the store's maximum capacity (customers processed per day)? Round your answer down to the nearest whole number.  customers processed per day What is the store's capacity by day of the week if the five regular checkout lines operate according to the schedule below (the express line is always open)? Do not round intermediate calculations. Round your answers down to the nearest whole number.   Hours/Day Mon Tue Wed Thur Fri Sat Sun 9–12 a.m. 1  2 1 2 4 4 2 12-4 p.m. 2  2 3 2 3 4 5 4–6 p.m. 4* 3 5 4 5 3 4 6-9 p.m. 4  3 4 3 4 4 1 * A "3" means three regular checkout lines are open on Monday from 4 to 6 p.m.   The store's capacity by day of the week (customers per…
The company has the following information about its two service departments and two production departments, Cutting and Assembly: Departments SquareFeet Number ofEmployees Maintenance Department 500    20 Cafeteria Department 1,400    10 Cutting Department 1,500    60 Assembly Department 7,100    20 What is the percentage (proportional) usage of the Maintenance Department by the Cutting Department?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY