Textbook Question
Book Icon
Chapter 11, Problem 11.12SE

Calculate and interpret overhead variances (Learning Objective 6)

Assume that the Janis Corporation’s manufacturing facility actually incurred $2,980,000 of manufacturing overhead for the year. Total fixed manufacturing overhead was budgeted at $3,010,000. Using a standard costing system, the company allocated $2,941,000 of fixed manufacturing overhead to production.

Requirements

  1. 1. Calculate the total fixed manufacturing overhead variance. What does this tell managers?
  2. 2. Determine the fixed overhead budget variance. What does this tell managers?
  3. 3. Determine the fixed overhead volume variance. What does this tell managers?
  4. 4. Doublecheck: Do the two variances (computed in Requirements 2 and 3) sum to the total overhead variance computed in Requirement 1?
Blurred answer
Students have asked these similar questions
MANAGEMENT ACCOUNTING & CONTROL STANDARD COSTS AND VARIANCE ANALYSIS LEARNING ACTIVITY 1     Torres Company has established standard costs for the cabinet department, in which one size of MX cabinet is made. The standard costs of producing one of these MX cabinets are shown below:   Standard Cost Card – MX Cabinet Direct Material: Lumber 50 board ft at P 4 200 Direct Labor: 8 hours at P 10 80 Overhead Costs: Variable – 8 hrs at P5 40                                Fixed – 8 hrs at P3 24 Total Standard Unit Cost 344   During June 2018, 500 of these cabinets were produced. The cost of operations during the month are shown below. There is no work in process at the beginning and end of the month.   Direct material purchased: 30,000 bf at P4.10 123,000 Direct materials used: 24,000 board ft   Direct labor: 4,200 hrs at P9.50 39,900 Overhead Costs : Variable Costs 22,000                                 Fixed Costs 11,000…
ShawnTech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:                                            Fixed element per month  variable element per student variable element per course revenue $0 $354 $0 faculty wages $0 $0 $2,300 course supplies $0 $48 $40 administrative expenses $41,700 $13 $21          In October, the school budgeted for 1,400 students and 127 courses. The actual activity for the month was 1,500 students and 129 courses. Prepare a report showing the school's activity variances for October. Label each variance as favorable (F) or unfavorable (U).
Roberds Tech is a for-profit vocational school. The school bases its budgets on two measures of activity (i.e., cost drivers), namely student and course. The school uses the following data in its budgeting:   Fixed element per month Variable element per student Variable element per course Revenue $ 0 $ 298 $ 0 Faculty wages $ 0 $ 0 $ 3,100 Course supplies $ 0 $ 52 $ 40 Administrative expenses $ 26,500 $ 27 $ 52 In March, the school budgeted for 1,910 students and 88 courses. The school's income statement showing the actual results for the month appears below: Roberds Tech Income Statement For the Month Ended March 31 Actual students 1,810 Actual courses 91 Revenue $ 411,340 Expenses:   Faculty wages 214,950 Course supplies 62,590 Administrative expenses 84,562 Total expense 362,102 Net operating income $ 49,238 Required: Prepare a flexible budget performance report showing both the school's activity variances and revenue and spending…

Chapter 11 Solutions

Managerial Accounting (5th Edition)

Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
FINANCIAL ACCOUNTING
Accounting
ISBN:9781259964947
Author:Libby
Publisher:MCG
Text book image
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Text book image
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Text book image
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Text book image
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Text book image
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY