MANAGERIAL ACCOUNTING-ACCESS
MANAGERIAL ACCOUNTING-ACCESS
17th Edition
ISBN: 9781259727795
Author: HILTON
Publisher: MCG
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 44P

For each of the following independent Cases A and B, fill in the missing information. The company budgets and applies production overhead costs on the basis of direct-labor hours. (U denotes unfavorable variance; F denotes favorable variance.)

Chapter 11, Problem 44P, For each of the following independent Cases A and B, fill in the missing information. The company

Expert Solution & Answer
Check Mark
To determine

Calculate the missing amount for each of the given independent case A and B.

Explanation of Solution

Flexible Budget: A flexible budget is a budget that is prepared for different levels of the output. In other words, it is a budget that adjusts according to the changes in the volume of the activity. The main purpose of preparing flexible budget is to determine the differences among standard and actual result.

Calculate the missing amount for each of the given independent case A and B as follows:

ParticularsCase ACase B
1. Standard variable overhead rate$2.50 per hour

$4.00 per hour

(13)

2. Standard fixed overhead rate

$7.00 per hour

(2)

$9.00 per hour

(14)

3. Total standard overhead rate

$9.50 per hour

(3)

$13.00 per hour
4. Flexible budget for variable overhead$ 90,000

$ 6,400

(15)

5. Flexible budget for fixed overhead$ 210,000

$ 18,000

(16)

6. Actual variable overhead

$ 98,050

(4)

$ 8,000

(17)

7. Actual fixed overhead$ 207,000

$ 19,080

(18)

8. Variable overhead spending variance$5,550 U$2,000 U
9. Variable overhead efficiency variance

$2,500 U

(5)

$400 F
10. Fixed overhead budget variance

$3,000 F

(6)

$1,080 U
11. Fixed overhead volume variance

-$42,000

(7)

$3,600 U
12. Under (over) applied variable overhead$8,050 Under applied (8)$1,600 Under applied (19)
13. Under (over) applied fixed overhead$45,000 over applied (9)$4,680 under applied (21)
14. Budgeted production (in units)5,000 units1,000 units (22)
15. Standard direct labor hours per unit6 hours per unit2 hours per unit
16. Actual production (in units)6,000 units (10)800 units (23)
17. Standard direct labor hours allowed for actual production36,000 hours1,600 hours
18. Actual direct labor hours37,000 hours1,500 hours
19. Applied variable overhead$ 90,000 (11)$ 6,400 (24)
20. Applied fixed overhead$ 252,000 (12)$ 14,400 (25)

Table (1)

Working note (1):

Calculate the budgeted direct labor hours for Case A.

Budgeted direct labor hours = (Budgeted production×Standard direct labor hours per unit)=5,000 units×6 hours per unit=30,000 hours

Working note (2):

Calculate the standard fixed overhead rate for Case A.

Standard fixed overhead rate = Budgeted fixed overhead Budgeted direct labor hours=$210,00030,000 hours (1)=$7 per hour

Working note (3):

Calculate the total standard overhead rate for Case A.

Standard overhead rate = [Variable overhead rate + Fixed overhead rate]=$2.50+$7.00=$9.50

Working note (4):

Calculate the actual variable overhead for Case A.

Variable overhead spending variance} = (Actual variable overhead[Actual direct labor hours×Standard variable overhead rate])$5,500U=(Actual variable overhead(37,000hours ×$2.50))Actual variable overhead = $98,050

Working note (5):

Calculate the variable overhead efficiency variance for Case A.

Variable overhead efficiency variance }(Actual quantityStandard quantity)×Standard variable rate=(37,000 hours36,000hours)×$2.50=$2,500U

Working note (6):

Calculate the fixed overhead budget variance for Case A.

Fixed overhead budget variance} = (Actual fixed overheadBudgeted fixed overhead)=$207,000$210,000=$3,000 F

Working note (7):

Calculate the fixed overhead volume variance for Case A.

Fixed overhead volume variance} =( Budgeted fixed overheadApplied fixed overhead)=$210,000(36,000 hours×$7)=($42,000)

Working note (8):

Calculate the under applied variable overhead for Case A.

Underapplied variable overhead = [Actual variable overheadApplied variable overhead]=$98,050(36,000 hours×$2.50)=$8,050 Underapplied

Working note (9):

Calculate the over applied fixed overhead for Case A.

Over applied fixed overhead = (Actual fixed overhead Applied fixed overhead)=$207,000(36,000 hours×$7)=$45,000 overapplied

Working note (10):

Calculate the actual production for Case A.

Actual production = Standard allowd direct labor hoursStandard hours per unit=36,000units6=6,000 units

Working note (11):

Calculate the applied variable overhead for Case A.

Applied variable overhead = (Standard hours ×Standard variable rate)=36,000 hours×$2.50=$90,000

Working note (12):

Calculate the applied fixed overhead for Case A.

Applied fixed overhead = Standard hour ×Fixed overhead rate=36,000 hours×$7=$252,000

Working note (13):

Calculate the variable overhead efficiency variance for Case B.

Variable overhead efficiency variance}=(Actual quantityStandard quantity)×Standard variable rate$400F=(1,500 hours1,600 hours)×Standard variable rateStandard variable rate = $4

Working note (14):

Calculate the standard fixed overhead rate for Case B.

Standard fixed overhead rate} = (Total stanard overhead rateStandard variable rate)=$13$4=$9

Working note (15):

Calculate the flexible budget for variable overhead for Case B.

Flexible budget for variable overhead} = Standard quantity ×Standard variable rate=1,600 hours×$4=$6,400

Working note (16):

Calculate the flexible budget for fixed overhead for Case B.

Flexible budget for fixed overhead }= Applied fixed overhead+Volume variance=(1,600 hours×$9)+$3,600=$18,000

Working note (17):

Calculate the actual variable overhead for Case B.

Actual variable overhead = (Applied variable + Spending varaince + Efficiency variance)=(1,600 hours×$4)+$2,000 U$400 F=$8,000

Working note (18):

Calculate the actual fixed overhead for Case B.

Actual fixed overhead = (Budgeted fixed overhead+Fixed overhead budget variance)=$18,000+$1,080U=$19,080

Working note (19):

Calculate the under applied variable overhead for Case B.

Underapplied varaible overhead =( Spending variance + Efficiency variance)=$2,000 U$400 F=$1,600 Underapplied

Working note (20):

Calculate the under applied fixed overhead for Case B.

Underapplied fixed overhead = [Fixed overhead budget variance+Volume variance]=$1,080U+$3,600=$4,680 Underapplied

Working note (21):

Calculate the budgeted direct labor hours for Case B:

Budgeted direct labor hours} = Budgeted fixed overheadFixed overhead rate=$18,000$9=2,000 hours

Working note (22):

Calculate the budgeted production for Case B:

Budgeted production = Budgeted direct labor hoursStandard hours per unit=2,000 hours (21)2 hours per unit =1,000 units

Working note (23):

Calculate the actual production for Case B:

Actual production = Standard allowed hoursStandard hours per unit=1,600 hours2 hours per units=800 units

Working note (24):

Calculate the applied variable overhead for Case B:

Applied variable overhead = Standard hours×Standard variable rate=1,600 hours×$4=$6,400

Working note (25):

Calculate the applied fixed overhead for Case B:

Applied fixed overhead = (Standard hours×Standard fixed overhead rate)=1,600 hours×$9=$14,400

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!

Chapter 11 Solutions

MANAGERIAL ACCOUNTING-ACCESS

Ch. 11 - What is the fixed-overhead budget variance?Ch. 11 - What is the correct interpretation of the...Ch. 11 - Describe a common but misleading interpretation of...Ch. 11 - Draw a graph showing budgeted and applied fixed...Ch. 11 - What types of organizations use flexible budgets?Ch. 11 - What is the conceptual problem of applying fixed...Ch. 11 - Distinguish between the control purpose and the...Ch. 11 - Why are fixed-overhead costs sometimes called...Ch. 11 - Draw a graph showing both budgeted and applied...Ch. 11 - Give one example of a plausible activity base to...Ch. 11 - Explain how an activity-based flexible budget...Ch. 11 - Crystal Glassware Company has the following...Ch. 11 - Refer to the data in the preceding exercise. Use...Ch. 11 - Crystal Glassware Company has the following...Ch. 11 - The following data are the actual results for...Ch. 11 - Evening Star, Inc. produces binoculars of two...Ch. 11 - The controller for Rainbow Childrens Hospital,...Ch. 11 - You recently received the following note from the...Ch. 11 - You brought your work home one evening, and your...Ch. 11 - Refer to DCdesserts.coms activity-based flexible...Ch. 11 - Montoursville Control Company, which manufactures...Ch. 11 - Prob. 33ECh. 11 - The following data pertain to Aurora Electronics...Ch. 11 - Calgary Paper Company produces paper for...Ch. 11 - Gibralter Insurance Company uses a flexible...Ch. 11 - Country time Studios is a recording studio in...Ch. 11 - Newark Plastics Corporation developed its overhead...Ch. 11 - Johnson Electrical produces industrial ventilation...Ch. 11 - Fall City Hospital has an outpatient clinic....Ch. 11 - Maxwell Company uses a standard cost accounting...Ch. 11 - Mark Fletcher, president of SoftGro, Inc., was...Ch. 11 - LawnMate Company manufactures power mowers that...Ch. 11 - For each of the following independent Cases A and...Ch. 11 - Prob. 45PCh. 11 - Prob. 46PCh. 11 - WoodCrafts, Inc. is a manufacturer of furniture...Ch. 11 - Rutherford Wheel and Axle, Inc. has an automated...Ch. 11 - Chillco Corporation produces containers of frozen...Ch. 11 - Montreal Scholastic Supply Company uses a...Ch. 11 - College Memories, Inc. publishes college...Ch. 11 - While Mountain Sled Company manufactures childrens...Ch. 11 - Cleveland Computer Accessory Company (CCAC)...Ch. 11 - Prob. 54CCh. 11 - Prob. 55C
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Accounting (Text Only)
Accounting
ISBN:9781285743615
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY