Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)
5th Edition
ISBN: 9781305084766
Author: Saeed Moaveni
Publisher: Cengage Learning
bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 9P

Calculate the R-value for the following materials:

a. 4 in. thick brick

b. 10 cm thick brick

c. 12 in. thick concrete slab

d. 20 cm thick concrete slab

e. 1 cm thick human fat layer

(a)

Expert Solution
Check Mark
To determine

Find the R-value for 4in thick brick.

Answer to Problem 9P

The R-value for 4in thick brick is 0.10m2KW.

Explanation of Solution

Given data:

The thickness of the brick, L=4in.

From table 11.3 in the textbook, the thermal conductivity of the brick, k=1.0Wmk.

Formula used:

The formula to find R-value is,

R=Lk (1)

Here,

L is the thickness of the material, and

k is the thermal conductivity of the material.

Calculation:

Substitute 4in for L, and 1.0Wmk for k in equation (1) to find R,

R=4in1.0Wmk[1in=0.0254m]=(4in)(0.0254m1in)1.0Wmk=(4×0.0254)m1.0WmkR=0.10m2KW

Therefore, R-value for 4in thick brick is 0.10m2KW.

Conclusion:

Hence, the R-value for 4in thick brick is 0.10m2KW.

(b)

Expert Solution
Check Mark
To determine

Find the R-value for 10cm thick brick.

Answer to Problem 9P

The R-value for 10cm thick brick is 0.10m2KW.

Explanation of Solution

Given data:

The thickness of the brick, L=10cm.

Calculation:

Substitute 10cm for L, and 1.0Wmk for k in equation (1) to find R,

R=10cm1.0Wmk[1m=100cm]=(10cm)(1m100cm)1.0Wmk=0.1m1.0WmkR=0.10m2KW

Therefore, R-value for 10cm thick brick is 0.10m2KW.

Conclusion:

Hence, the R-value for 10cm thick brick is 0.10m2KW.

(c)

Expert Solution
Check Mark
To determine

Find the R-value for 12in thick concrete slab.

Answer to Problem 9P

The R-value for 12in thick concrete slab is 0.22m2KW.

Explanation of Solution

Given data:

The thickness of the concrete slab, L=12in.

From Table 11.3 in the textbook, the thermal conductivity of the concrete slab, k=1.4Wmk.

Calculation:

Substitute 12in for L, and 1.4Wmk for k in equation (1) to find R,

R=12in1.4Wmk[1in=0.0254m]=(12in)(0.0254m1in)1.4Wmk=(12×0.0254)m1.4WmkR=0.22m2KW

Therefore, R-value for 12in thick concrete slab is 0.22m2KW.

Conclusion:

Hence, the R-value for 12in thick concrete slab is 0.22m2KW.

(d)

Expert Solution
Check Mark
To determine

Find the R-value for 20cm thick concrete slab.

Answer to Problem 9P

The R-value for 20cm thick concrete slab is 0.14m2KW.

Explanation of Solution

Given data:

The thickness of the concrete slab, L=20cm.

Calculation:

Substitute 20cm for L, and 1.4Wmk for k in equation (1) to find R,

R=20cm1.4Wmk[1m=100cm]=20cm×1m100cm1.4Wmk=0.2m1.4WmkR=0.14m2KW

Therefore, R-value for 20cm thick concrete slab is 0.14m2KW.

Conclusion:

Hence, the R-value for 20cm thick concrete slab is 0.14m2KW.

(e)

Expert Solution
Check Mark
To determine

Find the R-value for 1cm thick human fat layer.

Answer to Problem 9P

The R-value for 1cm thick human fat layer is 0.05m2KW.

Explanation of Solution

Given data:

The thickness of the human fat layer, L=1cm.

From table 11.3 in the textbook, the thermal conductivity of the human fat layer, k=0.2Wmk.

Calculation:

Substitute 1cm for L, and 0.2Wmk for k in equation (1) to find R,

R=1cm0.2Wmk[1m=100cm]=(1cm)(1m100cm)0.2Wmk=0.01m0.2WmkR=0.05m2KW

Therefore, R-value for 1cm thick human fat layer is 0.05m2KW.

Conclusion:

Hence, the R-value for 1cm thick human fat layer is 0.05m2KW.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The capacities of two hemispherical tanks are in the ratio of 64:125. If 4.8 kg of paint is required to paint the outer surface of the smaller tank, then how many kg of paint will be needed to paint the outer surface of the larger tank? a. 4.6 b. 7.5 c. 6.4 d. 5.7
During the winter season, a young chemical engineer observed a snow from a pavement that is being scooped up to a height of 10 ft by an endless bucket-scoop, and is then dropped into a container. He noticed that, at the highest point, the snow moves at 3 ft/s. A total of 33 hp is needed to scoop snow at the rate of 100 lb/s. Assuming a loss of 10% due to friction, calculate the work done and the percentage of total work need to melt and break up the snow.
1. A certain material having a specific gravity of 3.52 in a 250 mL beaker was found to have weigh 484 g. What is the porosity of the material? a. 0.68     b. 0.38     c. 0.45    d. 0.29 2. The width of an apron conveyer with a capacity of 75 tons/hr and speed of 50 A. 220 mm   B. 370 mm C. 070 mm      D. 460 mm 3. The diffusivity of water in air at 10 deg. F and 1 atm in cm2/sec is A. 0.256    B. 0.273     C. 0.404     D. 0.581

Chapter 11 Solutions

Engineering Fundamentals: An Introduction to Engineering (MindTap Course List)

Knowledge Booster
Background pattern image
Civil Engineering
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Engineering Fundamentals: An Introduction to Engi...
Civil Engineering
ISBN:9781305084766
Author:Saeed Moaveni
Publisher:Cengage Learning
Text book image
Sustainable Energy
Civil Engineering
ISBN:9781337551663
Author:DUNLAP, Richard A.
Publisher:Cengage,
Aggregates: Properties; Author: nptelhrd;https://www.youtube.com/watch?v=49yGZYeokKM;License: Standard YouTube License, CC-BY