Chapter 12, Problem 16P
a)
Summary Introduction
To determine: The machine and labor capacity requirement and total load.
Introduction: Capacity utilization refers to the effective use of the resource or the supply. It is the action of practically using the available materials.
b)
Summary Introduction
To determine: The feasibility of the schedule and evaluate the projected loading for first three days of the week.
Introduction: Capacity utilization refers to the effective use of the resource or the supply. It is the action of practically using the available materials.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Green Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/25 of a day and 1/60 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop.
A T1 truck and a C1 car yield profits of $300 and $220, respectively, per vehicle sold.
The optimum solution is:
Number of trucks to be produced per day = ? (round your response to two decimal places).
Green Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes 1/25 of a day and 1/60 of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes 1/45 of a day to assemble either type of vehicle in the assembly shop.
A T1 truck and a C1 car yield profits of $300 and $220, respectively, per vehicle sold.
The aim of the objective function for Green Vehicle Inc. should be to Maximize the objective value.
Part 2
The optimum solution is:
Number of trucks to be produced per day = ?
enter your response here
Green Vehicle Inc., manufactures electric cars and small delivery trucks. It has just opened a new factory where the C1 car and the T1 truck can both be manufactured. To make either vehicle, processing in the assembly shop and in the paint shop are required. It takes
1/40
of a day and
1/75
of a day to paint a truck of type T1 and a car of type C1 in the paint shop, respectively. It takes
1/45
of a day to assemble either type of vehicle in the assembly shop.
A T1 truck and a C1 car yield profits of
$275
and
$225,
respectively, per vehicle sold.
The aim of the objective function for Green Vehicle Inc. should be to
Maximize
the objective value.
The optimum solution is:
Number of trucks to be produced per day =
nothing
(round your response to two decimal places).
Chapter 12 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
Ch. 12.11 - What is ERP?Ch. 12.11 - What are the three main reasons firms adopt ERP?Ch. 12.11 - What are some hidden costs of ERP?Ch. 12.11 - How does ERP fit with e-commerce and supply chain...Ch. 12 - Contrast independent and dependent demand.Ch. 12 - When is MRP appropriate?Ch. 12 - Briefly define or explain each of these terms: a....Ch. 12 - Prob. 4DRQCh. 12 - Prob. 5DRQCh. 12 - What is meant by the term safety time?
Ch. 12 - Prob. 7DRQCh. 12 - Briefly discuss the requirements for effective...Ch. 12 - Prob. 9DRQCh. 12 - How can the use of MRP contribute to productivity?Ch. 12 - Prob. 11DRQCh. 12 - What is lot sizing. what is its goal, and why is...Ch. 12 - Contrast planned-order receipts and scheduled...Ch. 12 - If seasonal variations are present, is their...Ch. 12 - Prob. 15DRQCh. 12 - What are some unforeseen costs of ERP?Ch. 12 - What trade-offs are involved in the decision to...Ch. 12 - Who in the organization needs to be involved in...Ch. 12 - Prob. 3TSCh. 12 - Prob. 1CTECh. 12 - Give one example of unethical behavior involving...Ch. 12 - a. Given the following diagram for a product,...Ch. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Eighty units of end item E are needed at the...Ch. 12 - a. One hundred twenty units of end item Z are...Ch. 12 - A table is assembled using three components, as...Ch. 12 - Eighty units of end item X are needed at the...Ch. 12 - Oh No!, Inc., sells three models of radar detector...Ch. 12 - Assume that you are the manager of a shop that...Ch. 12 - Assume that you are the manager of Assembly, Inc....Ch. 12 - Determine material requirements plans for pans N...Ch. 12 - A firm that produces electric golf carts has just...Ch. 12 - Refer to Problem 12. Assume that unusually mild...Ch. 12 - Using the accompanying diagram, do the following:...Ch. 12 - A company that manufactures paving material for...Ch. 12 - Prob. 16PCh. 12 - The MRP Department has a problem. Its computer...Ch. 12 - Develop a material requirements plan for component...Ch. 12 - How many wheels sets should the manager order?Ch. 12 - When should the wheel sets be ordered?Ch. 12 - Prob. 2.1CQCh. 12 - Prob. 1OTQCh. 12 - Prob. 2OTQCh. 12 - Suppose the company has just received an order for...Ch. 12 - Prob. 4OTQCh. 12 - Prob. 5OTQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A company produces two products, A and B, which have profits of $9 and $7, respectively. Each unit of product must be processed on two assembly lines, where the required production times are as follows: Product Line 1 Line 2 A 12 4 B 4 8 Total hours 60 40 1) solve by the Simplex methodarrow_forwardThe Monroe Logistics Company would like to schedule its drivers to minimize the number of drivers used to cover the requirements over all seven days of the week. The company has 6 cabs but needs all six of them on duty only on Fridays. The estimated requirements are as follows: Day Mon Tue Wed Thu Fri Sat Sun Requirements 6 4 4 4 6 3 3 Prepare a schedule that minimizes the total number of drivers needed and minimizes the amount of slack capacity. In case of ties for assignment, it is preferred to give weekend days off. Identify the slack capacity for each day of the week. In addition, please identify the number of people working less than full-time (i, e., working less than five days a week. This is employee scheduling program. No employee can be off on Friday and please do not change the requirement in the question. Thank you.arrow_forwardPart A is processed on a MILLING machine; Part B is processed on a LATHE machine. Two parts (A and B) are then assembled on an ASSEMBLY machine. Standard times, scrap rates, efficiency, and availability of each machine and the assembly are given in the table below. Determine the number of milling (M), the lathe (L) and the assembly (A) machines needed to produce 100 good parts from this production system during and 8-hour (480 minutes) shift. (Note: Round up the number of parts processed on each station and then round up the number of machines needed).arrow_forward
- A manufacturing system is used to produce a product.Each unit of product must be processed sequentially through workstations.V -----> W -----> X -----> Y The capacity of each workstation are as follows:Workstation V, 16 units per hour,Workstation W, 22 units per hour, Workstation X, 13 units per hour,Workstation Y, 18 units per hour. The raw material is always available in the front of workstation V. The manufacturing system has a cycle time of __________ minutes per unit. Use at least 4 decimals.You must show your calculation steps and brief explanation on your Excel spreadsheets.arrow_forwardA college provides free tutoring services for its students 7 days a week, and the daily requirements for tutors are: Day M T W Th F S Su Requirements 5 4 7 3 6 3 4 Find the minimum number of tutors required if each tutor works 4 days a week and has 3 consecutive days off. Give preference to Saturday and Sunday off in case of a tie. (Hint: Look for group of 3 days with the lowest requirements). Specify the work schedule for each tutor. How much slack does your schedule generate for each day?arrow_forwardThe Johnny Ho Manufact uring Company in Columbus, Ohio, is putting out four new electronic components. Each of Ho's four plants has the capacity to add one more productto its current line of electronic parts. The unit-manufacturing costs for producing the different parts at the four plants are shown in the accompanying table. How should Ho assign the new products to the plants to minimize manufacturing costs?arrow_forward
- A producer has three products, A, B, and C, which are composed from many of the same raw materials and subassemblies by the same skilled workforce. Each unit of product A uses 15 units of Raw Material X, one Purge System Subassembly, one Case, one Power Cord, three Labour Hours in the Assembly Department, and one Labour Hour in the Finishing Department. Each unit of product B uses 10 units of Raw Material X, five units of Raw Material Y, two Purge System Subassemblies, one Case, one Power cord, five Labour Hours in the Assembly Department, and 90 minutes in the Finishing Department. Each unit of product C uses five units of Raw Material X, 25 units of Raw Material Y, two Purge System Subassemblies, one Case, a Power Cord, seven Labour Hours in the Assembly Department, and Three Labour Hours in the Finishing Department. Labour between the Assembly and Finishing departments is not transferable, but workers within each department work on any of the three products. There are three…arrow_forwardA producer has three products, A, B, and C, which are composed from many of the same raw materials and subassemblies by the same skilled workforce. Each unit of product A uses 15 units of Raw Material X, one Purge System Subassembly, one Case, one Power Cord, three Labour Hours in the Assembly Department, and one Labour Hour in the Finishing Department. Each unit of product B uses 10 units of Raw Material X, five units of Raw Material Y, two Purge System Subassemblies, one Case, one Power cord, five Labour Hours in the Assembly Department, and 90 minutes in the Finishing Department. Each unit of product C uses five units of Raw Material X, 25 units of Raw Material Y, two Purge System Subassemblies, one Case, a Power Cord, seven Labour Hours in the Assembly Department, and Three Labour Hours in the Finishing Department. Labour between the Assembly and Finishing departments is not transferable, but workers within each department work on any of the three products. There are three…arrow_forwardPlease formulate the problem as AN OPTIMIZATION MODEL only and I will finish the rest. Health Center is planning to open its facilities 24 hours a day and wants to determine an optimal schedule. for their nurses. A nurse's work schedule is 8 hours in a row and can only start at the beginning of each shift. The personnel requirement for each shift is shown in Table 1. Table 1 – Personnel Requirementarrow_forward
- A restaurant operates from 8 a.m. to 8 p.m. and employs both full-time and part-time workers. Full-time workers work from 8 a.m. to 6 p.m., 9 a.m. to 7 p.m., or 10 to 8 p.m. and are paid $140 per day. Part-time workers work either 12 p.m. to 6 p.m. or 1 p.m. to 7 p.m. and are paid $85 per day. The number of employees needed every hour is as follows. Develop a work schedule that minimizes daily labor costs. What is the optimal minimum cost? 8-9A 7 9-10A 8 10-11A 8 11A-12P 6 12-1P 7 1-2P 8 2-3P 10 3-4P 9 4-5P 9 5-6P 8 6-7P 3 7-8P 2arrow_forwardBaking dog treats in her kitchen has been a simple process for Emma to manage. She has two ovens, one sink, a refrigerator, and enough room for two people to work at the same time. However, when Emma moves her business out of her home, she will have a commercial kitchen that can accommodate as many as six people working simultaneously. She had never thought of her business as “production” until the real estate agent who showed her the space asked how many production workers she needs to accommodate. At that point, Emma realized she would be running a production system. Even worse, she realized that she had never even visited a manufacturing facility or set foot on a real production floor. How will she ever manage this process?arrow_forwardFive workers are available to perform four jobs. Thetime it takes each worker to perform each job is given inTable 65. The goal is to assign workers to jobs so as tominimize the total time required to perform the four jobs.Use the Hungarian method to solve the problem.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.