Question
Book Icon
Chapter 12, Problem 25P

a

Summary Introduction

Interpretation:

Number of days required to produce Product A, B and C.

Concept Introduction: Lean operation is a process in which a business should focus on continuous improvement with minimum resources and elimination of wastage. It is a process which is adopted by businesses to work efficiently and wastage must be reduced to the maximum level. Its main focus is to create customer satisfaction and eliminate implicit cost. Its principal is to smoothen the manufacturing process so that the operation of the business can be efficiently done. Moreover, the delegation of work is important rather than having a workload at the same team so that perfection can be attained.

a

Expert Solution
Check Mark

Explanation of Solution

If the company is adopting traditional schedule, the number of days required to produce Product A are:

Number of days required to produce product A is calculated by dividing the total number of boxes to be produced in a year for Product A and the number of boxes that can be produced in a day.

  NumberofdaysrequiredtoproduceProductA=(TotalnumberofboxesforProductAtobeproducedinayear)Productionperday

            = 1,500boxes16boxes =93.75days

Hence, number of days required to produce Product A will be 93.75 days.

If the company is adopting traditional schedule, number of days required to produce Product B is as follows:

Number of days required to produce Product B is calculated by dividing the total number of boxes to be produced in a year for Product B and the number of boxes that can be produced in a day.

  NumberofdaysrequiredtoproduceProductB=(Totalnumnerofboxesforproductbtobeproducedinayear)Productionperday

  NumberofdaysrequiredtoproduceProductB=2,00016boxes

  NumberofdaysrequiredtoproduceProductB=125days

Hence, number of days required to produce Product B will be 125 days.

If the company is adopting traditional schedule, number of days required to produce product C are:

  NumberofdaysrequiredtoproduceProductC=(TotalnumnerofboxesforproductCtobeproducedinayear)Productionperday

  NumberofdaysrequiredtoproduceProductC=50016boxes

  NumberofdaysrequiredtoproduceProductC=31.25days

b

Summary Introduction

Interpretation:

Number of each product produced when mixed-model is adopted.

Concept Introduction: Lean operation is a process in which a business should focus on continuous improvement with minimum resources and elimination of wastage. It is a process which is adopted by businesses to work efficiently and wastage must be reduced to the maximum level. Its main focus is to create customer satisfaction and eliminate implicit cost. Its principal is to smoothen the manufacturing process so that the operation of the business can be efficiently done. Moreover, the delegation of work is important rather than having a workload at the same team so that perfection can be attained.

b

Expert Solution
Check Mark

Explanation of Solution

Daily production of Product A when mixed-schedule model is adopted.

Number of product A that should be produced in a day can be computed by multiplying the daily number of production with the ratio between total numbers of Product A required to be produced in a year with total production in a year. Total production for a year will include Product A, Product B and Product C to be produced in a year. Hence, the total production in a year will be 4000 boxes).

  DailyproductionofProductA=Dailyproduction×(NumberofProductAtobeproducedinayear)Totalproductioninayear

  DailyproductionofProductA=16boxes×1,500boxes4,000boxes=16boxes×0.375boxes=6boxes

Hence, the daily production of Product A will be 6 boxes.

Daily production of Product B when mixed-schedule model is adopted.

Number of product B that should be produced in a day can be computed by multiplying the daily number of production with the ratio between total numbers of Product B required to be produced in a year with total production in a year. Total production for a year will include Product A, Product B and Product C to be produced in a year. Hence, the total production in a year will be 4000 boxes).

  DailyproductionofProductA=16boxes×2,000boxes4,000boxes=16boxes×0.5boxes=8boxes

Hence, the daily production of Product A will be 8 boxes.

Daily production of Product C when mixed-schedule model is adopted.

Number of product C that should be produced in a day can be computed by multiplying the daily number of production with the ratio between total numbers of Product C required to be produced in a year with total production in a year. Total production for a year will include Product A, Product B and Product C to be produced in a year. Hence, the total production in a year will be 4000 boxes).

  DailyproductionofProductA=16boxes×500boxes4,000boxes=16boxes×0.125boxes=2boxes

Hence, the daily production of Product C will be 2 boxes.

c

Summary Introduction

Interpretation:

Sequence of production of products during a day.

Concept Introduction: Lean operation is a process in which a business should focus on continuous improvement with minimum resources and elimination of wastage. It is a process which is adopted by businesses to work efficiently and wastage must be reduced to the maximum level. Its main focus is to create customer satisfaction and eliminate implicit cost. Its principal is to smoothen the manufacturing process so that the operation of the business can be efficiently done. Moreover, the delegation of work is important rather than having a workload at the same team so that perfection can be attained.

c

Expert Solution
Check Mark

Explanation of Solution

Company B can adopt the following order for daily mix to complete the production:

Company B has to produce 6 Boxes of Product A, 8 boxes of product B and 2 boxes of product C in a day. Hence, company B can produce the product in a following manner.

Product B, Product A, Product B, Product A, Product B, Product A, Product B, Product C, Product B, Product A, Product B, Product A, Product B, Product A, Product B, Product C.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The recipe for a fruit smoothie requires 2 cups of fruit per 6 cups of yogurt to maintain a 1/3 ratio. While making the fruit smoothie, Suzy accidentally puts 3 cups of fruit into the pitcher. How many cups of yogurt should be put out n the pitcher to maintain the ratio of 1/3?
The recipe for a fruit smoothie requires 2 cups of fruit per 6 cups of yogurt to maintain a 1/3 ratio. While making the fruit smoothie, Suzy accidentally puts 3 cups of fruit into the pitcher. How many cups of yogurt should Suzy add to the pitcher to maintain the 1/3 ratio?
A Company produces a component for use in the aerospace industry. The component consists of three parts (A, B and C), which are purchased externally and cost 50c, 60c and 70c per piece respectively. Parts A and B are assembled first on assembly line 1, which produces 150 components per hour. Part C undergoes a drilling operation before being finally assembled with the output from assembly line 1. There are six drilling machines in total, but only three are currently operational. Each drilling machine drills part C at a rate of 30 parts per hour. The final assembly line has a production capacity of 100 components per hour. At present, components are produced eight hours a day, five days a week. If the need arises, management can add a second shift of eight hours for the assembly lines only. The cost of assembly labour is 40c per assembly operation for each assembly line; the cost of drilling labour is 20c per part. For drilling, the cost of electricity is 10c per part. The overhead cost…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.