EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 13, Problem 10PA

(a)

Summary Introduction

Interpretation: The number of transfer slips that are needed on Friday is to be determined.

Concept Introduction:

The concept of dependent demand will be useful in this problem. Knowing the demand for an end item, and the quantity of the component parts per unit of end item, it is possible to determine the number of component parts required.

(b)

Summary Introduction

Interpretation: The number of withdrawals slips that are needed on Friday is to be determined.

Concept Introduction:

The concept of dependent demand will be useful in this problem. Knowing the demand for an end item, and the quantity of the component parts per unit of end item, it is possible to determine the number of component parts required.

(c)

Summary Introduction

Interpretation: The number of deposits slips that should be ordered is to be determined.

Concept Introduction:

The concept of dependent demand will be useful in this problem. Knowing the demand for an end item, and the quantity of the component parts per unit of end item, it is possible to determine the number of component parts required.

(d)

Summary Introduction

Interpretation: The end item and the component part in this bank example are to be determined.

Concept Introduction:

The concept of dependent demand will be useful in this problem. Knowing the demand for an end item, and the quantity of the component parts per unit of end item, it is possible to determine the number of component parts required.

(e)

Summary Introduction

Interpretation: The implications of having too many or too few deposit, withdrawal and transfer slips are to be determined.

Concept Introduction:

The concept of dependent demand will be useful in this problem. Knowing the demand for an end item, and the quantity of the component parts per unit of end item, it is possible to determine the number of component parts required.

Blurred answer
Students have asked these similar questions
Print Item Equivalent Units of Production Data for the two departments of Kimble & Pierce Company for June of the current fiscal year are as follows:   Drawing Department Winding Department Work in process, June 1 10,000 units, 38% completed 4,000 units, 35% completed Completed and transferred to next   processing department during June 60,000 units 60,500 units Work in process, June 30 11,500 units, 70% completed 3,500 units, 60% completed Production begins in the Drawing Department and finishes in the Winding Department. a.  If all direct materials are placed in process at the beginning of production, determine the direct materials and conversion equivalent units of production for June for the Drawing Department. If an amount is zero, enter in "0". Drawing Department Direct Materials and Conversion Equivalent Units of Production For June   Whole Units Direct MaterialsEquivalent Units ConversionEquivalent Units Inventory in process, June 1 fill…
As the production planner for Xiangling Hu​ Products, Inc., you have been given a bill of material for a bracket that is made up of a​ base, 1 spring​, and 3 clamps. The base is assembled from 2 clamps and 2 housings. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand.   This exercise contains only parts b and c. The product structure is as​ follows:   Bracket Base(1) Clamp(2) Handle(1) Casting(2) Spring(1) Housing(2) Shaft(2) Clamp(3) Bearing(1) Handle(1) Casting(2)   ​b) Determine the gross quantities needed of each item if you are to assemble 50 brackets.   ​Base: ? ​Spring: ? ​Clamp: ? ​Housing: ? ​Handle: ? ​Casting: ? ​Bearing: ? ​Shaft: ?
Canine Kennels Company (CKC) manufactures two different types of dog chew toys (A and B, sold in 1,000-count boxes) that are manufactured and assembled on three different workstations (W, X, and Y) using a small-batch process (see the figure below). Batch setup times are negligible. The flowchart denotes the path each product follows through the manufacturing process, and each product's price, demand per week, and processing times per unit are indicated as well. Purchased parts and raw materials consumed during production are represented by inverted triangles. CKC can make and sell up to the limit of its demand per week; no penalties are incurred for not being able to meet all the demand. Each workstation is staffed by a worker who is dedicated to working on that workstation alone and is paid $6 per hour. Total labor costs per week are fixed. Variable overhead costs are $3,500/week. The plant operates one 8-hour shift per day or 40 hours/week. Which of the three workstations, W, X, or…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY