Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 14, Problem 13P
Summary Introduction
Interpretation: Critical ratio for the job alpha which requires 2 weeks of work and is due in 4 weeks.
Concept Introduction:
Critica ratio refers to the rule that merges the issue of due date and processing time together into one single value used to settle through the waiting jobs. It is also considered as a dynamic priority rule, in which the value changes as time passes, hence, the
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using Johnson's rule for 2-machine scheduling, the sequence is:
Scheduled Order
Job
1
▼
B
C
E
F
A
D
Part 2
2
▼
F
C
A
D
B
E
Part 3
3
▼
A
B
D
F
C
E
Part 4
4
▼
E
D
C
B
F
A
Part 5
5
▼
F
C
D
A
E
B
Part 6
6
▼
D
C
F
B
E
A
Part 7
For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) =
enter your response here
hours (enter your response as a whole number).
...
Question content area right
Part 1
Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows:
Job
Operation 1 (hours)
Operation 2 (hours)
A
4
8
B
10
5
C
3
11
D…
If the time remaining to complete a job is 10 days and the lead time remaining is 12 days, whatis the critical ratio? Is the order ahead of schedule, on schedule, or behind schedule?
First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day
4.
Job
D
was scheduled to begin early on day
2
and take
7.5
days. As of now (the review point after day
4),
it is 2 days ahead of schedule.
Job
E
should begin on day
1
and take
4
days. It was on time.
Job
F
was to begin on day
2,
but maintenance forced a delay of
0.5
day.
The job should now take
5
full days. It is now on schedule.
Job
G
is a day behind schedule. It started at the beginning of day
2
and should require
7
days to complete.
Add the actual progress to the Gantt schedule shown on the right (on which the planned timings have been already plotted as blue lines).
Using the line drawing tool, plot the actual progress showing the actual start and the expected finish on top of (overlapping) the maroon dashed line provided just above the job number for each of the tasks.
Chapter 14 Solutions
Practical Operations Management
Ch. 14 - Prob. 1DQCh. 14 - Prob. 2DQCh. 14 - Prob. 3DQCh. 14 - Prob. 4DQCh. 14 - Prob. 5DQCh. 14 - Prob. 1PCh. 14 - Prob. 2PCh. 14 - Prob. 3PCh. 14 - Prob. 4PCh. 14 - Prob. 6P
Ch. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - Prob. 15PCh. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Prob. 18PCh. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Prob. 23PCh. 14 - Prob. 24PCh. 14 - Prob. 25PCh. 14 - Prob. 26PCh. 14 - Prob. 27PCh. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Prob. 1.1QCh. 14 - Prob. 1.2QCh. 14 - Prob. 1.3QCh. 14 - Prob. 1.4Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Job 3 has recently been enlarged by adding task #4. According to the graph, job #3 has beenarrow_forwardAssume that operations on a work package were expected to cost $1,500 to complete the package. They were originally scheduled to have been finished today. At this point, however, we have actually expended $1,200, and we estimate that we have completed four-fifths of the work. What is the Cost-Schedule Index? (0.5) What does it indicate? (0.5) Show all your work and explain.arrow_forwardRon Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a) Today, which is the end of day 7, Ron is reviewing the Ganttchart depicting these schedules:• Job # 151 was scheduled to begin on day 3 and to ta ke6 days. As of now, it is I day ahead of schedule.• Job# 177 was scheduled to begin on day J and take 4 days.It is currently on time.• Job #1 79 was scheduled to start on day 7 and take 2 days. Itactually got started on day 6 and is progressing according toplan.• Job #211 was scheduled to begin on day 5, but missingequipment delayed it until day 6. It is progressing asexpected and should take 3 days.• Job #215 was scheduled to begin on day 4 and take 5 days.It got sta rted on time but has since fallen behind 2 days.Draw the Gantt scheduling chart for the activities described.b) Ron now wants to use a Ga ntt load chart to see how muchwork is scheduled in each of his three work teams: Able,Baker, and Charlie. Five jobs constitute the current…arrow_forward
- What does it mean for a process to be "starved" according to the priority scheduling method? What are some ways that this may be avoided?arrow_forwardAt the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the beginning of the day 1 (today, which is a work day). All of the jobs are due at various times today. Your job is to evaluate four common sequencing rules. JOB DUE (IN HOURS) DURATION (HOURS REQUIRED) A 8 (this job is due in 8 hours) 1.65 B 5.5 (this job is due in 5.5 hours) 1.20 C 4.5 (this job is due after lunch in 4.5 hours) 0.85 D 6 (this job is due in 6…arrow_forwardWhat are the objectives of work center scheduling?arrow_forward
- Are production lines scheduled off a single pacing process, with appropriate inventory levels at each stage?arrow_forwardThe following table contains information regarding jobs that are to be scheduled through one machine: Job Processing Time (Days) Due date A 4 20 B 12 30 C 2 15 D 11 16 E 10 18 F 3 5 G 6 9 Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus 4: What are the mean flow time and average lateness for each of the schedule above? Qus 5: Which priority rule is appropriate for job scheduling? Justify your answer.arrow_forward. A work center has the following open and planned orders for week 4. Calculate thetotal standard time required (load).arrow_forward
- You have prepared the following schedule for a project in which the key resource is a backhoe. This schedule is contingent on having 3 backhoes. You receive a call from your partner, Brooker, who desperately needs 1 of your backhoes. You tell Brooker you would be willing to let him have the backhoe if you are still able to complete your project in 11 months. Develop a resource schedule to see if it is possible to complete the project in 11 months with only 2 backhoes. Activities 5 and 6 require 2 backhoes, while activities 1, 2, 3, and 4 require 1 backhoe. No splitting of activities is possible.arrow_forwardThe Mowry Machine Shop still has five jobs to be processedas of 8 a.m. today (day 23) at its bottleneck operation. The daywhen the order arrived, processing time, and promised duedates are given in the following table. The jobs are listed inthe order of arrival.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of averageflow time and average days past due.b. Which rule gives the best schedule, in your judgment?Why?arrow_forwardUsing the FCFS rule for scheduling, the sequence is ▼ 1-3-2 3-1-2 1-2-3 2-1-3 2-3-1 3-2-1 . Part 2 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 3 Using Johnson's rule for 2-machine scheduling, the sequence is ▼ 3-1-2 1-2-3 2-1-3 3-2-1 2-3-1 1-3-2 . Part 4 For the schedule developed using the Johnson's rule, the total length of time taken to complete the three suits (including delivery) = enter your response here hours (enter your response as a whole number). Part 5 Of the two developed schedules, ▼ Johnson's the FCFS rule gets the schedule finished sooner. ... Question content area right Part 1 Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY