Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 14, Problem 17P
Summary Introduction
To develop: A net materials requirement plan based on the actual inventory and new
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering.
b. Choose correct time phased-structures
c. Develop a net material requirements plan for F (enter your responses as whole numbers).
Upton Enterprises produces a variety of switches. Below, you will find a bill-of-material file for their simplest switch: Part A. The number in the parentheses represents the number of units required for the upper level. LT stands for the lead time, measured in weeks.Assuming that Upton Enterprises has none of Switch A in inventory, and the inventory levels of Parts B, C, D, E, and F are also zero, how many weeks would it take to produce 100 units of Switch A?
What would be the total requirement for part E?
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and\ 1 housing. Each clamp has 1 handle and 2 castings.Each housing has 1 bearing and 2 shafts.There is no inventory on hand.
C) Compute the net quantities needed if there are 25 of the base and 75 of the clamp in stock.
(Product structure picture attached)
Base = (?) units
Spring = (?) units
Clamp = (?) units
Housing = (?) units
Handle = (?) units
Casting = (?) units
Bearing = (?) units
Shaft = (?) units
Chapter 14 Solutions
Principles Of Operations Management
Ch. 14 - Ethical Dilemma For many months your prospective...Ch. 14 - What is the difference between a gross...Ch. 14 - Prob. 2DQCh. 14 - What are the similarities between MRP and DRP?Ch. 14 - How does MRP II differ from MRP?Ch. 14 - Which is the best lot-sizing policy for...Ch. 14 - What impact does ignoring carrying cost in the...Ch. 14 - MRP is more than an inventory system; what...Ch. 14 - What are the options for the production planner...Ch. 14 - Master schedules are expressed in three different...
Ch. 14 - What functions of the firm affect an MRP system?...Ch. 14 - Prob. 11DQCh. 14 - Prob. 12DQCh. 14 - Prob. 13DQCh. 14 - Prob. 14DQCh. 14 - As an approach to inventory management, how does...Ch. 14 - Prob. 16DQCh. 14 - Use the Web or other sources to: a) Find stories...Ch. 14 - Prob. 18DQCh. 14 - Prob. 19DQCh. 14 - You have developed the following simple product...Ch. 14 - You are expected to have the gift bags in Problem...Ch. 14 - Prob. 3PCh. 14 - Your boss at Xiangling Hu Products, Inc., has just...Ch. 14 - The demand for subassembly S is 100 units in week...Ch. 14 - Prob. 6PCh. 14 - Prob. 7PCh. 14 - Prob. 8PCh. 14 - Prob. 9PCh. 14 - Prob. 10PCh. 14 - Prob. 11PCh. 14 - Prob. 12PCh. 14 - Prob. 13PCh. 14 - Prob. 14PCh. 14 - You are product planner for product A (in Problem...Ch. 14 - Prob. 16PCh. 14 - Prob. 17PCh. 14 - Heather Adams, production manager for a Colorado...Ch. 14 - Prob. 19PCh. 14 - Prob. 20PCh. 14 - Prob. 21PCh. 14 - Prob. 22PCh. 14 - Data Table for Problems 14.22 through 14.25 ...Ch. 14 - Develop a POQ solution and calculate total...Ch. 14 - Using your answers for the lot sizes computed in...Ch. 14 - M. de Koster, of Rene Enterprises, has the master...Ch. 14 - Grace Greenberg, production planner for Science...Ch. 14 - Prob. 28PCh. 14 - Prob. 29PCh. 14 - Prob. 30PCh. 14 - Courtney Kamauf schedules production of a popular...Ch. 14 - Using the data for the coffee table in Problem...Ch. 14 - Prob. 1CSCh. 14 - Prob. 2CSCh. 14 - Prob. 1.1VCCh. 14 - Prob. 1.2VCCh. 14 - Prob. 1.3VCCh. 14 - Prob. 2.1VCCh. 14 - Prob. 2.2VCCh. 14 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- “How many dozen should I put in the proofer?” asked Elizabeth, the new baker at the Sands Cafeteria. Rami El‐Hussieny was the day shift operations manager, and, unfortunately, he did not know how to answer Elizabeth's question. What she wanted to know was simple enough: How many dozen rolls should be placed in the proofer in anticipation of the night's dinner business? The problem was that the frozen dinner roll dough used at the Sands Cafeteria needed to be proof for at least 2 hours prior to being baked for 15 minutes. If too many rolls were proofed, they would never be needed, but they would still have to be baked and made into bread dressing or even tossed out. If too few dozen were proofed and the night was busier than anticipated, they would run out of “Fresh Baked Rolls” (one of the restaurant's signature items), and Rami knew that the night manager would be really upset. It was a daily guess, and sometimes Rami missed the guess! He wondered if a prebaked roll with a shelf life…arrow_forwardShown below is a partially completed MPS record for ball bearings. Part 2 a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity on Hand: 400 Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 350 350 450 250 300 250 350 400 350 Customer orders (booked) 300 350 250 300 150 150 150 150 100 50 Projected on-hand inventory enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here enter your response here MPS quantity 500 enter your response here enter your response here enter your response here enter your…arrow_forwardInput Area Cost Per Hour $1500.00 Outage Duration (hours) 3 Output Area Total Cost for Outage $4500.00 One-Variable Data Table: Cost Outage Impact Analysis Duration (hr) (Cost) 1 $1500.00 1.5 $2250.00 2 $3000.00 2.5 $3750.00 3 $4500.00 3.5 $5250.00 4 $6000.00 4.5 $6750.00 5 $7500.00 Given the data above Which What If Analysis tool is the worksheet using? Provide a description of the What If Analysis tool and why it was used in the worksheet. Interpret what the data means. Discuss what it means for the business.arrow_forward
- A book publisher has i xed costs of $300,000 and variable costs per book of $8.00. Thebook sells for $23.00 per copy.a. How many books must be sold to break even?b. If the i xed cost increased, would the new break-even point be higher or lower?c. If the variable cost per unit decreased, would the new break-even point be higher or lower?arrow_forwardA metal fabrication shop has a single punch press. There are currently three partsthat the shop has agreed to produce that require the press, and it appears that theywill be supplying these parts well into the future. You may assume that the press isthe critical resource for these parts, so that we need not worry about the interactionof the press with the other machines in the shop. The relevant information here is: Part Number Demand/year Set up Cost ($) Cost per Unit ($) Production rate/year 1 2,500 80 16 45,000 2 5,500 120 18 40,000 3 1,450 60 22 26,000 Holding costs are based on an 18 percent annual interest rate, and the products are to be produced in sequence on a rotation cycle. Setup times can be considered negligible. What is the optimal lot size of part 2?arrow_forwardProduction data show 35,920 units were transferred out of a stage of production and 6,150 units remained in ending WIP inventory that was 100% complete to material and 35% complete to conversion. The unit material cost is $5 for material and $8 for conversion. What is the amount of inventory transferred out and remaining in ending work in process inventory? Round to the whole unit and whole dollar, no decimals. Complete the tables below: Equivalent units data Units Materials Conversion Transferred out 35,920 Ending inventory 6,150 Units accounted for, equivalent units Cost data Transferred out $ Ending work in process: materials Ending work in process: conversion Ending work in process: total Costs to account for $ please fill in the blank boxesarrow_forward
- Production data show 35,920 units were transferred out of a stage of production and 6,150 units remained in ending WIP inventory that was 100% complete to material and 35% complete to conversion. The unit material cost is $5 for material and $8 for conversion. What is the amount of inventory transferred out and remaining in ending work in process inventory? Round to the whole unit and whole dollar, no decimals. Complete the tables below: Equivalent units data Units Materials Conversion Transferred out 35,920 Ending inventory 6,150 Units accounted for, equivalent units Cost data Transferred out $ Ending work in process: materials Ending work in process: conversion Ending work in process: total Costs to account for $ please fill in the information in the grid exactly as providedarrow_forwardMicrosurfacing is part of a pavement restoration and maintenance program that seals the surface of a street that has minor cracking to prevent water from penetrating into the base material. The annual cost of the equipment (truck, tank, valves, etc.) is $109,000 per year and the material cost is $2.75 per square yard. Alternatively, regular street resurfacing requires equipment that has a first cost of $225,000 with a 15-year life and no salvage value. The variable cost for regular resurfacing is $13 per square yard. At an interest rate of 8% per year, how many square yards per year must be resurfaced for the two methods to break even?arrow_forwardWould critical ratio be better utilized as a static ratio or a dynamic ratio, and why?arrow_forward
- Will’s Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component R is made from 2 units of component X and 2 unit of component Y. Component T is made from 1 unit of component V and 2 units of component Z. Calculate the gross requirements for each of the components when the company plans to build 70 of its Q Model if you have these inventories: 70 units of component T and 110 units of component R, using the given information: Item Usage per Parent Q - R 2 S 2 T 1 X 2 Y 2 V 1 Z 2 Q R S T X Y V Z Put the answers down into the table: (If answer is zero, please enter 0, do not leave any fields blank.) Product Gross Requirements Q…arrow_forward12-2. What would efficient reverse management imply for the pricing of the Cowboys Stadium parking lot on typical game day? How about for the Super Bowl? How about for the many smaller events that fill less that half the lot?arrow_forwardA publisher for a promising new novel figures fixed costs (overhead, advances, promotion, copy editing, typesetting, and so on) at $63,000 and variable costs (printing, paper, binding, shipping) $1.30 for each book produced. If the book is sold to distrubutors for $18 each, how many must be produced and sold for the publisher to break even? The publisher must produce and sell ____ books to break even.? Round to the nearest integer as needed. Thanks!@@##arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.