Concept explainers
a)
To construct: A product structure.
Introduction:
Product structure:
The product structure is a visual representation of the components needed for a product assembly and the sequence at which they must be developed. It will clearly depict the parents and children components at each level.
a)
Answer to Problem 13P
Product structure:
Explanation of Solution
Given information:
- 1000 20” fans due in week 7.
- Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
- Housing assembly is made of frame, two supports, and a handle.
- Fan assembly is made up of a hub and five blades.
- Electrical unit consists of a motor, switch and a knob.
Component | Lead time | On-hand inventory | Lot size |
|
20" Fan | 1 | 100 | ||
Housing | 1 | 100 | ||
Frame | 2 | |||
Supports (2) | 1 | 50 | 100 | |
Handle | 1 | 400 | 500 | |
Grills (2) | 2 | 200 | 500 | |
Fan assembly | 3 | 150 | ||
Hub | 1 | |||
Blades (5) | 2 | 100 | ||
Electrical unit | 1 | |||
Motor | 1 | |||
Switch | 1 | 20 | 12 | |
Knob | 1 | 25 | 200 in week 2 |
Product structure:
The product is a 20” fan. It is made of four components. Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit. Housing assembly is made of frame, two supports, and a handle. Fan assembly is made up of a hub and five blades. Electrical unit consists of a motor, switch and a knob.
b)
To construct: A time-phased product structure.
Introduction:
Time-phased product structure:
The time-phased product structure will represent the product visually with the details of when each component must begin production. It should be done to ensure that all the components are on time.
b)
Answer to Problem 13P
Time-phased product structure:
Explanation of Solution
Given information:
- 1000 20” fans due in week 7.
- Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
- Housing assembly is made of frame, two supports, and a handle.
- Fan assembly is made up of a hub and five blades.
- Electrical unit consists of a motor, switch and a knob.
Component | Lead time | On-hand inventory | Lot size | Scheduled receipt |
20" Fan | 1 | 100 | ||
Housing | 1 | 100 | ||
Frame | 2 | |||
Supports (2) | 1 | 50 | 100 | |
Handle | 1 | 400 | 500 | |
Grills (2) | 2 | 200 | 500 | |
Fan assembly | 3 | 150 | ||
Hub | 1 | |||
Blades (5) | 2 | 100 | ||
Electrical unit | 1 | |||
Motor | 1 | |||
Switch | 1 | 20 | 12 | |
Knob | 1 | 25 | 200 in week 2 |
Time-phased product structure:
The end product is the fan which must be ready at week 7. All the other components must be completed on week 6. The components at the lower level must be completed first before proceeding to the higher levels. Each component at each level is begun depending on the lead time of the product.
The products are started in advance so that they are developed and ready on time so that the dependent parent will be ready to develop its product. The process is repeated until all the subassemblies are ready to make the final product.
c)
To develop: A net requirements plan.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
c)
Explanation of Solution
Given information:
- 1000 20” fans due in week 7.
- Each fan is made of a housing assembly, two grills, fan assembly and an electrical unit.
- Housing assembly is made of frame, two supports, and a handle.
- Fan assembly is made up of a hub and five blades.
- Electrical unit consists of a motor, switch and a knob.
Component | Lead time | On-hand inventory | Lot size | Scheduled receipt |
20" Fan | 1 | 100 | ||
Housing | 1 | 100 | ||
Frame | 2 | |||
Supports (2) | 1 | 50 | 100 | |
Handle | 1 | 400 | 500 | |
Grills (2) | 2 | 200 | 500 | |
Fan assembly | 3 | 150 | ||
Hub | 1 | |||
Blades (5) | 2 | 100 | ||
Electrical unit | 1 | |||
Motor | 1 | |||
Switch | 1 | 20 | 12 | |
Knob | 1 | 25 | 200 in week 2 |
Net requirements plan:
20’’ Fan:
Week | ||||||||||||
20" Fan | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 1,000 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | |||||||||||
Net requirement | 900 | |||||||||||
Planned order receipt | 900 | |||||||||||
Planned order release | 900 |
Week 7:
The gross requirement is 1,000 (1 assembly). The on hand inventory is 100. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 6 which will be the planned order receipt in week 7.
Housing:
Week | ||||||||||||
Housing | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (100) | 100 | |||||||||||
Net requirement | 800 | |||||||||||
Planned order receipt | 800 | |||||||||||
Planned order release | 800 |
Week 6:
The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 100. Hence, the net requirement is 800. The lead time is 1 week. Therefore, the planned order release will be 800 in week 5 which will be the planned order receipt in week 6.
Grills:
Week | ||||||||||||
Grills | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 1,800 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (200) | 200 | 400 | ||||||||||
Net requirement | 1,600 | |||||||||||
Planned order receipt | 2,000 | |||||||||||
Planned order release | 2,000 |
Week 6:
The gross requirement is 1,800 (2 assembly) derived from the planned order release of 20” fan. The on hand inventory is 200. Hence, the net requirement is 1,600. The lead time is 2 weeks. Therefore, the planned order release will be 2,000 (Lot Size = 500) in week 4 which will be the planned order receipt in week 6. The excess inventory will be available at week 7.
Fan assembly:
Week | ||||||||||||
Fan assembly | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (150) | 150 | |||||||||||
Net requirement | 750 | |||||||||||
Planned order receipt | 750 | |||||||||||
Planned order release | 750 |
Week 6:
The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 150. Hence, the net requirement is 750. The lead time is 2 weeks. Therefore, the planned order release will be 750 in week 4 which will be the planned order receipt in week 6.
Electrical unit:
Electrical Unit | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 900 | |||||||||||
Planned order receipt | 900 | |||||||||||
Planned order release | 900 |
Week 6:
The gross requirement is 900 (1 assembly) derived from the planned order release of 20” fan. The on hand inventory is 0. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 5 which will be the planned order receipt in week 6.
Frame:
Frame | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 800 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 800 | |||||||||||
Planned order receipt | 800 | |||||||||||
Planned order release | 800 |
Week 5:
The gross requirement is 800 (1 assembly) derived from the planned order release of Housing. The on hand inventory is 0. Hence, the net requirement is 800. The lead time is 2 weeks. Therefore, the planned order release will be 800 in week 3 which will be the planned order receipt in week 5.
Supports:
Week | ||||||||||||
Supports | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 1,600 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (50) | 50 | |||||||||||
Net requirement | 1,550 | |||||||||||
Planned order receipt | 1,600 | |||||||||||
Planned order release | 1,600 |
Week 5:
The gross requirement is 1,600 (2 assembly) derived from the planned order release of Housing. The on hand inventory is 50. Hence, the net requirement is 1,550. The lead time is 1 week. Therefore, the planned order release will be 1,600 (Lot size = 100) in week 4 which will be the planned order receipt in week 5. The excess inventory is available at week 6.
Handle:
Week | ||||||||||||
Handle | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 800 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (400) | 400 | 100 | ||||||||||
Net requirement | 400 | |||||||||||
Planned order receipt | 500 | |||||||||||
Planned order release | 500 |
Week 5:
The gross requirement is 800 (1 assembly) derived from the planned order release of Housing. The on hand inventory is 400. Hence, the net requirement is 400. The lead time is 1 week. Therefore, the planned order release will be 500 (Lot size = 500) in week 4 which will be the planned order receipt in week 5. The excess inventory is available at week 6.
Hub:
Week | ||||||||||||
Hub | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 750 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 750 | |||||||||||
Planned order receipt | 750 | |||||||||||
Planned order release | 750 |
Week 3:
The gross requirement is 750 (1 assembly) derived from the planned order release of fan assembly. The on hand inventory is 0. Hence, the net requirement is 750. The lead time is 1 week. Therefore, the planned order release will be 750 in week 2 which will be the planned order receipt in week 3.
Blades:
Week | ||||||||||||
Blades | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 3,750 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | 50 | ||||||||||
Net requirement | 3,750 | |||||||||||
Planned order receipt | 3,800 | |||||||||||
Planned order release | 3,800 |
Week 3:
The gross requirement is 3,750 (5 assembly) derived from the planned order release of fan assembly. The on hand inventory is 0. Hence, the net requirement is 3,750. The lead time is 2 weeks. Therefore, the planned order release will be 3,800 (Lot size = 100) in week 1 which will be the planned order receipt in week 3. The excess inventory will be available at week 4.
Motor:
Week | ||||||||||||
Motor | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (0) | 0 | |||||||||||
Net requirement | 900 | |||||||||||
Planned order receipt | 900 | |||||||||||
Planned order release | 900 |
Week 5:
The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 0. Hence, the net requirement is 900. The lead time is 1 week. Therefore, the planned order release will be 900 in week 4 which will be the planned order receipt in week 5.
Switch:
Week | ||||||||||||
Switch | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | ||||||||||||
On hand (20) | 20 | 8 | ||||||||||
Net requirement | 880 | |||||||||||
Planned order receipt | 888 | |||||||||||
Planned order release | 888 |
Week 5:
The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 20. Hence, the net requirement is 880. The lead time is 1 week. Therefore, the planned order release will be 888 (Lot Size = 12) in week 4 which will be the planned order receipt in week 5. The excess inventory will be available at week 6.
Knob:
Week | ||||||||||||
Knob | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Gross requirements | 900 | |||||||||||
Scheduled receipt | 200 | |||||||||||
On hand (0) | 200 | 200 | 200 | |||||||||
Net requirement | 700 | |||||||||||
Planned order receipt | 700 | |||||||||||
Planned order release | 700 |
Week 2:
There is a scheduled receipt of 200 which can be used as inventory.
Week 5:
The gross requirement is 900 (1 assembly) derived from the planned order release of Electrical unit. The on hand inventory is 0. But, there is a scheduled receipt of 200. Hence, the net requirement is 7000. The lead time is 1 week. Therefore, the planned order release will be 700 in week 4 which will be the planned order receipt in week 5.
Want to see more full solutions like this?
Chapter 14 Solutions
Principles Of Operations Management
- Assume that you are the manager of Assembly, Inc. You have just received an order for 40 units ofan industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of thoseorders, given that subassembly G must be ordered in multiples of 80 units and all other componentsare ordered lot-for-lot. Assume that the components are used only for this particular robot.Item Lead Time (weeks) On Hand ComponentsRobot 2 10 B, G, C(3)B 1 5 E, FC 1 20 G(2), HE 2 4 —F 3 8 —G 2 15 —H 1 10 —arrow_forward) The following data have been prepared for master production scheduling purposes in IKEA Australia: End product A: Beginning inventory of 60, Period forecast of 10, Lot size of 30, and 30 hours in lot size. End product B: Beginning inventory of 20, Period forecast of 5, Lot size of 20, and 20 hours in lot size. End product C: Beginning inventory of 30, Period forecast of 15, Lot size of 50, and 50 hours in lot size. Capacity: 38 hours/ week (i) Prepare the master production schedule for these items during the next four periods using the Ethan Allen master production scheduling method. (ii) Suppose that the master production schedule is frozen for the next three periods. What specific impact would the policy have on the IKEA's performance?arrow_forwardFarmers Groceries To You (FGTY) is a fast-growing company started by JMU alumni, which delivers fresh groceries collected in Virginia farms to families in the Shenandoah region. As part of an expansion plan, FGTY is considering approaching the northern Virginia market through printed product lists (PLs) containing deals, coupons and customers testimonies. The initial plan is to send 200,000 PLs to households in Fairfax and Arlington, expecting new customers to place orders. The company estimates to incur a fixed cost of $30,000 associated with design, printing setup and transportation contracting. Beyond this, the average transportation cost per PL is ¢20, while the printing cost per PL is ¢10. Also, FGTY incurs in an average cost of ¢25 for processing each order placed by a customer using the PL’s promotion codes. The expected size of an order is $50, and FGTY’s variable cost per order (mainly product costs labor) is close to 80% of the order’s average. You’ve been hired to help FGTY…arrow_forward
- Problem 6 Part A:Available to promise in period 4 = 50Problem 6 Part B:PAB in period 7 = 35 In part A, the only thing that you need to do is to calculate the ATP in periods 1,4,5, and 7. In part B, remember that you are rolling through time. The part B solution spreadsheet starts with time period 2 and period 1 is now history. For the part B, you must capture all of the events that occurred during week 1. For example, I gave you that the beginning PAB is 45. If you had 20 in stock (from part A), you produced 50 as planned in period 1, and the actual demand for period 1 was 25, then the beginning PAB (your stock quantity) is 20+50-25=45. The forecast and MPS quantities will not change from part A to part B. After you accept each of the orders (simply add the new order quantities to the existing customer order quantities in the correct time bucket), you will then recalculate the PAB, and then recalculate the ATP.arrow_forwardA linear programming computer package is needed. Greenville Cabinets received a contract to produce cabinets for a major furniture distributor. The contract calls for the production of 3,300 small cabinets and 4,100 large over the next two months, with the following delivery schedule Model Month 1 Month 2 Small 2,100 1,200 Large 1,500 2,600 Greenville estimates that the production time for each small cabinet is 0.7 hours and the production time for each large cabinet is 1 hour. The raw material costs are $10 for each small cabinet and $12 for each large cabinet. Labor costs are $22 per hour using regular production time and $33 using overtime. Greenville has up to 2,400 hours of regular production time available each month and up to 1,000 additional hours of overtime available each month. If production for either cabinet exceeds demand in month 1, the cabinets can be stored at a cost of $5 per cabinet. For each product, determine the number of units that should be…arrow_forwardWhat are the two main approaches to scheduling calving in Australian dairy production systems, and where are they dominant in the Australian dairy industry? What is the link between these calving systems, the milk marketing systems where each calving system is dominant, and the feed base needed to support each system?arrow_forward
- Courtney Kamauf schedules production of a popularRustic Coffee Table at Kamauf Enterprises, Inc. The table requires a top, four legs, 1 8 gallon of stain, 1 16 gallon of glue, 2 short braces betweenthe legs and 2 long braces between the legs, and a brass cap that goeson the bottom of each leg. She has 100 gallons of glue in inventory,but none of the other components. All items except the brass caps, stain, and glue are ordered on a lot-for-lot basis. The caps are pur-chased in quantities of 1,000, stain and glue by the gallon. Lead time is 1 day for each item. Schedule the order releases necessary to pro-duce 640 coffee tables on days 5 and 6, and 128 on days 7 and 8.arrow_forwardElectro Fans has j ust received an order for one thousand 20-inch fans d ue week 7. Each fan consists of a housing assembly, two grill s, a fan assembly, and an electrical unit.The housing assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub and five blades. The electrical unit consists of a motor, a switch, and a knob.The following ta ble gives lead times, on-hand inventory, and scheduled receipts.a) Construct a product structure.b) Construct a time-phased product structure.c) Prepare a net material requirements plan.arrow_forwardThe El Dorado Star is the only newspaper in El Dorado, New Mexico. Certainly, the Star competes with The Wall Street Journal, USA Today, and the New York Times for national news reporting, but the Star offers readers stories of local interest, such as local news, weather, high-school sporting events, and so on. The El Dorado Star faces the revenue and cost schedules shown in the spreadsheet that follows: A template for the spreadsheet is provided in the Course Materials. You may download my template or create your own. Since we are using dollars and cents, be sure to go out two decimal places on your calculations. Add columns to show, respectively, marginal cost (MC), marginal revenue (MR), and total profit. 1. Dell Computer Corp., the world's largest personal-computer maker, is keenly aware of everything its rival PC manufacturers decide to do. Explain why Dell usually reacts more quickly and more substantially to pricing, product design, and advertising decisions made by…arrow_forward
- The ATV Corporation makes three models of all-terrain vehicles: Model A, Model B, and Model C. Model A uses a 0.4-liter engine, Model B uses a 0.5-liter engine, and Model C uses a 0.6-liter engine. The aggregate production plan is the twelve-month plan that combines all three models together in total monthly production. The planning horizon is twelve months. The APP determines the size of the workforce, which is the constrained resource. Assume that the beginning inventory for January and that the desired monthly ending inventory is 120 units (30 units each of Model A and Model B, and 60 units of Model C), and the firm desires to have an ending inventory of 160 units at the end of the year. On average, one unit of ATV requires eight labor hours to produce, and a worker contributes 160 hours (8 hours × 5 days × 4 weeks) per month. The data has been collected in the Microsoft Excel Online file attached. Answer the question below: 1. What are the totals of the forecast demand (including…arrow_forwardTots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information: component plastic time space cost to manufacture cost to purchase front 2 11 2 7 11 seat/frame 3 7 2 6 10 rear 0.5 2.5 0.2 2 5 available 60000 180000 35000 The company obviously does not have the resources available to manufacture everything needed for the completion of 15,000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. (state the objective function, decision…arrow_forwardTots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information: component plastic time space cost to manufacture cost to purchase front 2 11 2 7 11 seat/frame 3 7 2 6 10 rear 0.5 2.5 0.2 2 5 available 60000 180000 35000 Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. Use Excel's Solver to obtain the optimal solution. How many of each component should be manufactured vs. purchased? What is the overall cost? What are the binding constraints? Upload a screenshot of the spreadsheet that you used…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.