Concept explainers
Refer again to Problems 14.3 and 14.5. In addition to 100 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Modify the net material requirements plan to reflect this change.
•• 14.5 Using the information in Problem 14.3, construct a net material requirements plan using the following on-hand inventory.
•• 14.3 The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
- a. Construct a product structure. Identify all levels, parents, and components.
- b. Prepare a time-phased product structure.
Want to see the full answer?
Check out a sample textbook solutionChapter 14 Solutions
Operations Management, Student Value Edition & Student Cd For Operations Management
- Briefly explain the components of an MRP system?arrow_forwardItem A has a gross requirement of 2,400 in week 6. Currently, there are 200 Item A's on hand with a scheduled receipt of 2,100 items in week 3. The lead time for item A is 2 weeks with an order quantity of 900. Complete the MRP record for Item A. Complete the MRP record for Item A (enter your responses as whole numbers). Week 0 1 2 3 4 5 6 Item A LT=2 Quantity: FOQ=900 Gross Requirementsarrow_forwardNote:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. 14.) A part structure, lead time (weeks), and on-hand quantities for product A are shown in Figure 14. From the information shown, generate: a) An indented bell of material for product A. b) Net requirements for each part to produce 10 As in week 8 using lot-for-lot. Figure 14:arrow_forward
- Discuss what is the primary report in Material Requirements Planning ( MRP )system output ?arrow_forwardUse the following partially completed MRP record to answer the question. Item: XYZ Lot Size: L4L; ;EAD Time: 1 week Date 1 2 3 4 5 6 7 8 20 30 50 40 20 Scheduled Receipts Projected on Hand (80) Planned Receipts Planned Order Release What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1, 2, 3, 4, 5, and 6)?arrow_forwardIdentify five specific requirements of an effective MRP system.arrow_forward
- Provide Linda with information on the ERP's expenses and advantages.arrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount Direct Components on Hand End 1 0 L(2), C(1), K(3) L 1 10 B(2), J(3) C 2 14 G(2), B(2) K 2 19 H(4), B(2) B 1 34 J 2 25 G 2 7 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are needed? b. An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time?arrow_forwardWhat are the most important inputs to the MRP system and how do they differ?arrow_forward
- What is the significance of a Requirements Management Plan (RMP) in complex projects, and how does it ensure requirements are well-defined and properly managed?arrow_forwardSOLVED FIXED TIME PERIOD MODEL PROBLEMS Activities/Assessments:Activity 13• The weekly demand for a product is 770 units. The standard deviation of daily demand is 10 units. The firm reviews its inventory every 28 days. Each order for the product arrives 9 days after placement. At the time of review, there are 10 units backorder. If 95 percent of all demand is to be satisfied from items in stock:a) How many units should be the safety stock?b) What’s the product’s inventory status?c) How many units should be ordered for this period?arrow_forwardGiven the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.