a)
To develop: A gross requirements plan for item C.
Introduction:
Gross requirements plan:
The gross requirements plan is the plan where the independent and dependent demands for a product or a component before the on-hand inventory and the
b)
To develop: A net requirements plan for item C.
Introduction:
Net requirements plan:
The net requirements plan is the plan which is established on the gross requirements plan formed by deducting the stock on and the scheduled receipts. If the total requirement is below the safety stock levels, a planned order is made based on the given lot sizing technique.
Trending nowThis is a popular solution!
Chapter 14 Solutions
Operations Management, Student Value Edition & Student Cd For Operations Management
- Given the product structure, master productionschedule, and inventory status in Figure 14.13, and assuming therequirements for each BOM item is I:a) develop a gross requirements plan for Item C;b) develop a net requirements plan for Item C.arrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks),and quantities on hand. Item Lead Time Amount on Hand Direct ComponentsEnd 1 — L(2), C(1), K(3)L 2 10 B(2), J(3)C 3 15 G(2), B(2)K 3 20 H(4), B(2)B 2 30J 3 30G 3 5H 2 —a. If 40 units of the end item are to be assembled, how many additional units of B are needed?(Hint: You don’t need to develop an MRP plan.)b. An order for the end item is scheduled to be shipped at the start of week 8. What is the latestweek that the order can be started and still be ready to ship on time? (Hint: You don’t need todevelop an MRP plan.)arrow_forwardWhat are some hidden costs of ERP?arrow_forward
- The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.     Item Lead Time Amount Direct Components   on Hand  End 1 0 L(2), C(1), K(3) L 1 10 B(2), J(3) C 2 14 G(2), B(2) K 2 19 H(4), B(2) B 1 34  J 2 25  G 2 7  H 3 0  a. If 43 units of the end item are to be assembled, how many additional units of B are needed? b. An order for the end item is scheduled to be shipped at the start of week 9. What is the latest week that the order can be started and still be ready to ship on time?arrow_forwardA part structure, lead time (weeks), and on-handquantities for product A are shown in Figure 14. 14. From theinformation shown, generate:a) An indented bill of material fo r product A b) Net requirements for each part to produce I0 As in week 8using lot-for-lot. IParrow_forwardList dimensions for decisions making for ERP?arrow_forward
- step by step how does one complete an MRP matrix for item xarrow_forwarda. Write the product structure diagram as an indented bill-of-materials list.arrow_forwardExplain the significance of a Requirements Management Plan (RMP) in complex projects. How does it ensure requirements are well-defined and properly managed?arrow_forward
- What is the significance of a Requirements Management Plan (RMP) in complex projects, and how does it ensure requirements are well-defined and properly managed?arrow_forwardProblem 13-3 (Static) The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand.  Item  Lead Time  Amounton Hand  Direct Components End  1  −  L(2), C(1), K(3) L  2  10  B(2), J(3) C  3  15  G(2), B(2) K  3  20  H(4), B(2) B  2  30   J  3  30   G  3  5   H  2  −       Click here for the Excel Data File  a. If 40 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.)arrow_forwardThe following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item  Lead Time Amounton Hand Direct Components End  1  0  L(2), C(1), K(3) L  2  11  B(2), J(3) C  3  17  G(2), B(2) K  4  23  H(4), B(2) B  3  34   J  3  25   G  3  7   H  3  0    a. If 43 units of the end item are to be assembled, how many additional units of B are needed? (Hint: You don’t need to develop an MRP plan.) b.An order for the end item is scheduled to be shipped at the start of week 11. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don’t need to develop an MRP plan.)arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.