Resset Co. provides the following results of April's operations: F indicates favorable and U indicates unfavorable. In applying management by exception:the company investigates all variances of $400 or more. Which variances will the company investigate?
Direct materials price variance............. % 300 F
Direct labor efficiency variance_____....... $2,2O0 F
Direct materials -quantity variance.....____ 3,000 U
Controllable overhead variance............ 400 U
Direct labor rite variance................. 100 U
Fixed overhead volume variance ........... 500 F
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QS 23-11 Direct labor variances P3
The following information describes a company's direct labor usage in a recent period. Compute the direct labor rate and efficiency variances for the period and classify each as favorable or unfavorable.
Actual direct labor hours used............
Actual direct labor rate per hour..........
Standard direct labor rate per hour...............
Standard direct labor hours for units produced....
65,000
$14
$15
67,000
Lemon Company manufactures a single product. The company manufactured 5,000
units in March, using 6,150 pounds of material and 2,420 labor hours. During the same
month, they purchased 6,200 pounds of material for $151,590. The actual labor cost
for March was $39,930. There were no beginning or ending work-in-process
inventories. The company has the following unit standard costs for direct materials
and labor.
Budgeted
quantity
Per unit
Direct materials 1.20 pounds
Budgeted price
$25 per pound
$15 per hour
Direct labor
0.50 hours
QS 23-8 Materials variances P3
Tercer reports the following for one of its products. Compute the direct materials price and quantity variances and classify each as favorable or unfavorable.
Actual finished units produced....
Direct materials standard (4 lbs. @ $2 per Ib.) ... $8 per finished unit
300,000 lbs.
60,000 units
Actual direct materials used
Actual cost of direct materials used...
$540,000
Chapter 23 Solutions
FUND ACCOUNTING PRINCIPLES CONNECT
Ch. 23 - Prob. 1QSCh. 23 - Prob. 2QSCh. 23 - Prob. 3QSCh. 23 - Prob. 4QSCh. 23 - Prob. 5QSCh. 23 - Prob. 6QSCh. 23 - Prob. 7QSCh. 23 - Prob. 8QSCh. 23 - Prob. 9QSCh. 23 - Prob. 10QS
Ch. 23 - Prob. 11QSCh. 23 - Prob. 12QSCh. 23 - Prob. 13QSCh. 23 - Prob. 14QSCh. 23 - Volume variance P3 Refer to information in QS...Ch. 23 - Prob. 16QSCh. 23 - Prob. 17QSCh. 23 - Prob. 18QSCh. 23 - Prob. 19QSCh. 23 - Prob. 20QSCh. 23 - Prob. 21QSCh. 23 - Prob. 22QSCh. 23 - Prob. 23QSCh. 23 - Prob. 24QSCh. 23 - Prob. 25QSCh. 23 - Exercise 23-1 Management by exception C1 Resset...Ch. 23 - Prob. 2ECh. 23 - Exercise 23-2 Preparing flexible budgets P1 Tempo...Ch. 23 - Prob. 4ECh. 23 - Prob. 5ECh. 23 - Prob. 6ECh. 23 - Prob. 7ECh. 23 - Prob. 8ECh. 23 - Prob. 9ECh. 23 - Prob. 10ECh. 23 - Prob. 11ECh. 23 - Prob. 12ECh. 23 - Exercise 23-13 Computing and interpreting...Ch. 23 - Prob. 14ECh. 23 - Exercise 23-15
Direct materials and direct labor...Ch. 23 - Prob. 16ECh. 23 - Prob. 17ECh. 23 - Exercise 23-18A Detailed overhead variances P5...Ch. 23 - Prob. 19ECh. 23 - Prob. 20ECh. 23 - Prob. 21ECh. 23 - Prob. 22ECh. 23 - Prob. 23ECh. 23 - Prob. 24ECh. 23 - Prob. 25ECh. 23 - Prob. 26ECh. 23 - Prob. 27ECh. 23 - Prob. 28ECh. 23 - Prob. 1PSACh. 23 - Prob. 2PSACh. 23 - Prob. 3PSACh. 23 - Prob. 4PSACh. 23 - Prob. 5PSACh. 23 - Prob. 6PSACh. 23 - Prob. 1PSBCh. 23 - Prob. 2PSBCh. 23 - Prob. 3PSBCh. 23 - Prob. 4PSBCh. 23 - Prob. 5PSBCh. 23 - Prob. 6PSBCh. 23 - Prob. 23SPCh. 23 - Flexible budgets and standard costs emphasize the...Ch. 23 - Prob. 2AACh. 23 - Prob. 3AACh. 23 - Prob. 1DQCh. 23 - Prob. 2DQCh. 23 - Prob. 3DQCh. 23 - Prob. 4DQCh. 23 - Prob. 5DQCh. 23 - Prob. 6DQCh. 23 - Prob. 7DQCh. 23 - Prob. 8DQCh. 23 - Prob. 9DQCh. 23 - Prob. 10DQCh. 23 - Prob. 11DQCh. 23 - Prob. 12DQCh. 23 - Prob. 13DQCh. 23 - How can the manager of advertising sales at Google...Ch. 23 - Prob. 15DQCh. 23 - Prob. 16DQCh. 23 - Prob. 1BTNCh. 23 - Prob. 2BTNCh. 23 - Prob. 3BTNCh. 23 - Prob. 4BTN
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Question 1 --/1 View Policies Current Attempt in Progress t In producing product ZZ, 14,800 direct labor hours were used at a rate of $8.20 per hour. The standard was 15,000 hours at $8.00 per hour. Based on this data, the direct labor O price variance is $3,000 unfavorable. O quantity variance is $1,600 unfavorable. O price variance is $2,960 favorable. O quantity variance is $1,600 favorable. hparrow_forwardQuestion Content Area Myers Corporation has the following data related to direct materials costs for November: actual cost for 4, 690 pounds of material at $5.30 and standard cost for 4, 410 pounds of material at $6.30 per pound. The direct materials price variance is a. $1,764 favorable b. $4,690 favorable c. $1,764 unfavorable d. $4,690 unfavorablearrow_forwardD Question 14 Use the following data to find the direct labor efficiency variance. Direct labor standard (4.0 hrs.@ $7/hr.) Actual hours worked per unit Actual units produced Actual rate per hour O $3,413 unfavorable O $15,600 unfavorable O $15,600 favorable O $13,650 favorable O $3,412 favorable Question 15 $28per finished unit 3.5 hrs 3,900 units $7.25 A unit of a business that not only incurs costs but also generates revenues is called F6 F7arrow_forward
- 58. The following are the available data of Anton Corp. for year 2025: Budgeted Fixed Overhead Budgeted Variable Overhead Budgeted Labor hours Actual labor hours Actual Fixed Overhead Actual Variable Overhead 1,566,000 3,078,000 540,000 521,100 1,566,000 2,870,460arrow_forwardIncome statement with variances Prepare an income statement through gross profit for Bellingham Company for the month ending March 31 using the variance data from Brief Exercises 1, 2, 3, and 4. Assume Bellingham sold 15,000 units at 172 per unit.arrow_forwardVariance interpretation You have been asked to investigate some cost problems in the Assembly Department of Ruthenium Electronics Co., a consumer electronics company. To begin your investigation, you have obtained the following budget performance report for department for the last quarter: The following reports were also obtained: You also interviewed the Assembly Department supervisor. Excerpts from the interview follow: Q: What explains the poor performance in your department? A: Listen, you've got to understand what it's been like in this department recently. Lately, it seems no matter how hard we try, we can't seem to make the standards. I'm not sure what is going on, but we've been having a lot of problems lately. Q: What kind of problems? A: Well, for instance, all this quarter we've been requisitioning purchased parts from the material storeroom, and the pans just didn't fit together very well I'm not sure what is going on. but during most of this quarter we've had to scrap and sort purchased pansjust to get our assemblies put together. Naturally, all this takes time and material. And that's not all. Q: Go on. A: All this quarter, the work that we've been receiving from the Fabrication Department has been shoddy. I mean, maybe around 20% of the stuff that comes in from Fabrication just can't be assembled. The fabrication is all wrong. As a result, we've had to scrap and rework a lot of the stuff. Naturally, this has just shot our quantity variances. Interpret the variance reports in light of the comments by the Assembly Department supervisor.arrow_forward
- Refer to the data in Exercise 9.15. Required: 1. Compute overhead variances using a two-variance analysis. 2. Compute overhead variances using a three-variance analysis. 3. Illustrate how the two- and three-variance analyses are related to the four-variance analysis. Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours. (Practical capacity is 500,000 hours.) Annual budgeted overhead costs total 787,200, of which 556,800 is fixed overhead. A total of 119,400 units using 478,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were 230,600, and actual fixed overhead costs were 556,250. Required: 1. Compute the fixed overhead spending and volume variances. How would you interpret the spending variance? Discuss the possible interpretations of the volume variance. Which is most appropriate for this example? 2. Compute the variable overhead spending and efficiency variances. How is the variable overhead spending variance like the price variances of direct labor and direct materials? How is it different? How is the variable overhead efficiency variance related to the direct labor efficiency variance?arrow_forwardVariances Refer to Cornerstone Exercise 9.6. Required: 1. Calculate the variable overhead spending variance using the formula approach. (If you compute the actual variable overhead rate, carry your computations out to five significant digits and round the variance to the nearest dollar.) 2. Calculate the variable overhead efficiency variance using the formula approach. 3. Calculate the variable overhead spending variance and variable overhead efficiency variance using the three-pronged graphical approach. 4. What if 26,100 direct labor hours were actually worked in February? What impact would that have had on the variable overhead spending variance? On the variable overhead efficiency variance? Standish Company manufactures consumer products and provided the following information for the month of February: Required: 1. Calculate the fixed overhead spending variance using the formula approach. 2. Calculate the volume variance using the formula approach. 3. Calculate the fixed overhead spending variance and volume variance using the three-pronged graphical approach. 4. What if 129,600 units had actually been produced in February? What impact would that have had on the fixed overhead spending variance? On the volume variance?arrow_forwardIncome statement with variances Prepare an income statement through gross profit for Dvorak Company for the month ended July 31 using the variance data in Practice Exercises 25-1B through 23-4B. Assume that Dvorak sold 1,000 units at 90 per unit.arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningAccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Financial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
- Accounting (Text Only)AccountingISBN:9781285743615Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage LearningFinancial & Managerial AccountingAccountingISBN:9781285866307Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Financial & Managerial Accounting
Accounting
ISBN:9781337119207
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Accounting (Text Only)
Accounting
ISBN:9781285743615
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Financial & Managerial Accounting
Accounting
ISBN:9781285866307
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY