Textbook Question
Chapter 23, Problem 1E
Exercise 23-1 Management by exception C1
Resset Co. provides the following results of April's operations: F indicates favorable and U indicates unfavorable. In applying management by exception:the company investigates all variances of $400 or more. Which variances will the company investigate?
Direct materials price variance............. % 300 F
Direct labor efficiency variance_____....... $2,2O0 F
Direct materials -quantity variance.....____ 3,000 U
Controllable overhead variance............ 400 U
Direct labor rite variance................. 100 U
Fixed overhead volume variance ........... 500 F
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 23 Solutions
Fundamental Accounting Principles
Ch. 23 - Prob. 1DQCh. 23 - Prob. 2DQCh. 23 - Prob. 3DQCh. 23 - Prob. 4DQCh. 23 - Prob. 5DQCh. 23 - Prob. 6DQCh. 23 - Prob. 7DQCh. 23 - Prob. 8DQCh. 23 - Prob. 9DQCh. 23 - Prob. 10DQ
Ch. 23 - Prob. 11DQCh. 23 - Prob. 12DQCh. 23 - Prob. 13DQCh. 23 - How can the manager of advertising sales at Google...Ch. 23 - Prob. 15DQCh. 23 - Prob. 16DQCh. 23 - Is it possible to evaluate a cost center’s...Ch. 23 - Prob. 18DQCh. 23 - Prob. 1QSCh. 23 - Prob. 2QSCh. 23 - Prob. 3QSCh. 23 - Prob. 4QSCh. 23 - Prob. 5QSCh. 23 - Prob. 6QSCh. 23 - Prob. 7QSCh. 23 - Prob. 8QSCh. 23 - Prob. 9QSCh. 23 - Prob. 10QSCh. 23 - Prob. 11QSCh. 23 - Prob. 12QSCh. 23 - Prob. 13QSCh. 23 - Prob. 14QSCh. 23 - Volume variance P3 Refer to information in QS...Ch. 23 - Prob. 16QSCh. 23 - Prob. 17QSCh. 23 - Prob. 18QSCh. 23 - Prob. 19QSCh. 23 - Prob. 20QSCh. 23 - Prob. 21QSCh. 23 - Prob. 22QSCh. 23 - Prob. 23QSCh. 23 - Prob. 24QSCh. 23 - Exercise 23-1 Management by exception C1 Resset...Ch. 23 - Prob. 2ECh. 23 - Exercise 23-2 Preparing flexible budgets P1 Tempo...Ch. 23 - Prob. 4ECh. 23 - Prob. 5ECh. 23 - Prob. 6ECh. 23 - Prob. 7ECh. 23 - Prob. 8ECh. 23 - Prob. 9ECh. 23 - Prob. 10ECh. 23 - Prob. 11ECh. 23 - Prob. 12ECh. 23 - Exercise 23-13 Computing and interpreting...Ch. 23 - Prob. 14ECh. 23 - Exercise 23-15
Direct materials and direct labor...Ch. 23 - Prob. 16ECh. 23 - Prob. 17ECh. 23 - Exercise 23-18A Detailed overhead variances P5...Ch. 23 - Prob. 19ECh. 23 - Prob. 20ECh. 23 - Prob. 21ECh. 23 - Prob. 22ECh. 23 - Prob. 23ECh. 23 - Prob. 1APSACh. 23 - Prob. 2APSACh. 23 - Prob. 3APSACh. 23 - Prob. 4APSACh. 23 - Prob. 5APSACh. 23 - Prob. 6APSACh. 23 - Prob. 2BPSBCh. 23 - Prob. 3BPSBCh. 23 - Prob. 4BPSBCh. 23 - Prob. 5BPSBCh. 23 - Prob. 6BPSBCh. 23 - Prob. 23SPCh. 23 - Flexible budgets and standard costs emphasize the...Ch. 23 - Prob. 2AACh. 23 - Prob. 3AACh. 23 - Prob. 1BTNCh. 23 - Prob. 2BTNCh. 23 - Prob. 3BTNCh. 23 - Prob. 4BTNCh. 23 - Prob. 5BTNCh. 23 - Training employees to use standard amounts of...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Income statement with variances Prepare an income statement through gross profit for Dvorak Company for the month ended July 31 using the variance data in Practice Exercises 25-1B through 23-4B. Assume that Dvorak sold 1,000 units at 90 per unit.arrow_forwardVariance interpretation You have been asked to investigate some cost problems in the Assembly Department of Ruthenium Electronics Co., a consumer electronics company. To begin your investigation, you have obtained the following budget performance report for department for the last quarter: The following reports were also obtained: You also interviewed the Assembly Department supervisor. Excerpts from the interview follow: Q: What explains the poor performance in your department? A: Listen, you've got to understand what it's been like in this department recently. Lately, it seems no matter how hard we try, we can't seem to make the standards. I'm not sure what is going on, but we've been having a lot of problems lately. Q: What kind of problems? A: Well, for instance, all this quarter we've been requisitioning purchased parts from the material storeroom, and the pans just didn't fit together very well I'm not sure what is going on. but during most of this quarter we've had to scrap and sort purchased pansjust to get our assemblies put together. Naturally, all this takes time and material. And that's not all. Q: Go on. A: All this quarter, the work that we've been receiving from the Fabrication Department has been shoddy. I mean, maybe around 20% of the stuff that comes in from Fabrication just can't be assembled. The fabrication is all wrong. As a result, we've had to scrap and rework a lot of the stuff. Naturally, this has just shot our quantity variances. Interpret the variance reports in light of the comments by the Assembly Department supervisor.arrow_forwardIncome statement with variances Prepare an income statement through gross profit for Bellingham Company for the month ended March 31 using the variance data in Practice Exercises 23-1A through 23-4A. Assume that Bellingham sold 15,000 units at 172 per unit.arrow_forward
- Variance interpretation You have been asked to investigate some cost problems in the Assembly Department of Ruthenium Electronics Co., a consumer electronics company. To begin your investigation, you have obtained the following budget performance report for the department for the last quarter. Ruthenium Electronics Co.Assembly Department Quarterly Budget Performance Report Standard Quantity at Standard Rates Actual Quantity at Standard Rates Quantity Variances Direct labor 157,500 227,500 70,000 U Direct materials 297,500 385,000 87,500 U Total 455,000 612,500 157,500 U You also obtained the following reports: Ruthenium Electronics Co.Purchasing Department Quarterly Budget Performance Report Actual Quantity at Standard Rates Actual Quantity at Actual Rates Price Variance Direct materials 437,500 385,000 (52,500) F Ruthenium Electronics Co.Fabrication Department Quarterly Budget Performance Report Standard Quantity at Standard Rates Actual Quantity at Standard Rates Quantity Variances Direct labor 245,000 203,000 (42,000) F Direct materials 140,000 140,000 0 Total 385,000 343,000 (42,000) F You also interviewed the Assembly Department supervisor. Excerpts from the interview follow: Q: What explains the poor performance in your department? A: Listen, youve got to understand what its been like in this department recently. Lately, it seems no matter how hard we try, we cant seem to make the standards. Im not sure what is going on, but weve been having a lot of problems lately. Q: What kind of problems? A: Well, for instance, all this Quarter weve been requisitioning purchased parts from the material storeroom, and the parts just didnt fit together very well. Im not sure what is going on, but during most of this quarter, weve had to scrap and sort purchased partsjust to get our assemblies put together. Naturally, all this takes time and material. And thats not all. Q: Go on. A: All this Quarter the work we've been receiving from the Fabrication Department has been shoddy. I mean, maybe around 20% of the stuff that comes in from Fabrication just cant be assembled. The fabrication is all wrong. As a result we've had to scrap and rework a lot of the stuff. Naturally, this has just shot our quantity variances. Interpret the variance reports in light of the comments by the Assembly Department supervisor.arrow_forwardVariance interpretation You have been asked to investigate some cost problems in the Assembly Department of Ruthenium Electronics Co., a consumer electronics company. To begin your investigation, you have obtained the following budget performance report for the department for the last quarter. Ruthenium Electronics Co.Assembly Department Quarterly Budget Performance Report Standard Quantity at Standard Rates Actual Quantity at Standard Rates Quantity Variances Direct labor 157,500 227,500 70,000 U Direct materials 297,500 385,000 87,500 U Total 455,000 612,500 157,500 U You also obtained the following reports: Ruthenium Electronics Co.Purchasing Department Quarterly Budget Performance Report Actual Quantity at Standard Rates Actual Quantity at Actual Rates Price Variance Direct materials 437,500 385,000 (52,500) F Ruthenium Electronics Co.Fabrication Department Quarterly Budget Performance Report Standard Quantity at Standard Rates Actual Quantity at Standard Rates Quantity Variances Direct labor 245,000 203,000 (42,000) F Direct materials 140,000 140,000 0 Total 385,000 343,000 (42,000) F You also interviewed the Assembly Department supervisor. Excerpts from the interview follow: Q: What explains the poor performance in your department? A: Listen, youve got to understand what its been like in this department recently. Lately, it seems no matter how hard we try, we cant seem to make the standards. Im not sure what is going on, but weve been having a lot of problems lately. Q: What kind of problems? A: Well, for instance, all this Quarter weve been requisitioning purchased parts from the material storeroom, and the parts just didnt fit together very well. Im not sure what is going on, but during most of this quarter, weve had to scrap and sort purchased partsjust to get our assemblies put together. Naturally, all this takes time and material. And thats not all. Q: Go on. A: All this Quarter the work we've been receiving from the Fabrication Department has been shoddy. I mean, maybe around 20% of the stuff that comes in from Fabrication just cant be assembled. The fabrication is all wrong. As a result we've had to scrap and rework a lot of the stuff. Naturally, this has just shot our quantity variances. Interpret the variance reports in light of the comments by the Assembly Department supervisor.arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Financial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage LearningAccounting (Text Only)AccountingISBN:9781285743615Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
- Financial & Managerial AccountingAccountingISBN:9781285866307Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Financial & Managerial Accounting
Accounting
ISBN:9781337119207
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Accounting (Text Only)
Accounting
ISBN:9781285743615
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
Financial & Managerial Accounting
Accounting
ISBN:9781285866307
Author:Carl Warren, James M. Reeve, Jonathan Duchac
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY