Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned with the amount of time it took to complete several recent jobs. Some of his workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are given in the following table:
a) Determine the expected completion time and variance for each activity.
b) Determine the total project completion time and the critical path for the project.
c) Determine ES, EF, LS, LF, and slack for each activity.
d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
- A project network is shown below, with three time estimates (Optimistic Time-Most Likely Time-Pessimistic Time (in days)) for each activity in the network. a. Compute the expected time for each activity in the project network. b. Identify and list all possible paths in the project network. Compute the expected duration for each path in the project network. c. Identify the critical path(s) in the project network. What is the expected project completion time? d. Compute the variance of each activity on the critical path(s). e. Determine the project variance and project standard deviation. Use the PERT analysis results in 2(c) and 2(e) to answer questions (f), (g), (h), and (i) below:f. What is the probability that the project can be completed within 22 days of its start? g. What is the probability that the project can be completed within 16 days of its start? h. Determine the project deadline that gives this project a 78% chance of on-time completion. i. Determine the project deadline…arrow_forwardA local political campaign must coordinate a number of necessary activities to be prepared for an upcoming election. The following table describes the relationships between these activities that need to be completed, as well as their completion times. Activity Immediate Predecessors Time (weeks) A - 3 B - 6 C A 2 D A 3 E B, C 7 F B 6 G D, E 1 H F 1 Use excel to answer the following; a) Develop a project network for this problem. b) Determine the EST, EFT, LST, LFT, and slack for each activity. c) What is the critical path and project completion time?arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors,and times appear in the accompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forward
- An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity. Job Description Predecessor Expected time in days A Prepare preliminary sketches NA 2 B Outline specifications NA 1 C Prepare drawings A 3 D Write specifications A B 2 E Run prints C D 1 F Have specifications printed B D 3 G Assemble bid package E F 1arrow_forwardRoger Ginde is developing a program in supplychain management certification for managers. Ginde haslisted a number of activities that must be completed beforea training program of this nature could be conducted. Theactivities, immediate predecessors, and times appear in theaccompanying table: a) Develop an AON network for this problem.b) What is the critical path?c) What is the total project completion time?d) What is the slack time for each individual activity?arrow_forwardDraw the Network Diagram, determine the critical path and draw Gantt chart for project scheduling for the following two problems Problem1. Activity Predeccsor Duration(hours) Lag Time(hours) A - 2 0 B A 4 5 C B 3 3 D B 5 0 E D, C 2 0 Problem 2. Activity Predeccsor Duration(months) A - 2 B A 1 C A 3 D B, C 1 E D 2 F D…arrow_forward
- A marketing firm is planning to conduct a survey of a segment of the potential product audience for one of its customers. The planning process for preparing to conduct the survey consists of six activities, with precedence relationships and activity time estimates as follows: a. Determine all paths through the network from node a to node f and the duration of each. Also indicate the critical path. b. Determine the earliest and latest activity start and finish times. c. Determine the slack for each activity.arrow_forwardScott and Associates, Inc., is an accounting firm that has three new clients. Project leaders will be assigned to the three clients. Based on the different backgrounds and experiences of the leaders, the various leader–client assignments differ in terms of projected completion times. The possible assignments and the estimated completion times in days are as follows: CLIENTS Project Leader 1 2 3 Jackson 10 16 32 Ellis 14 22 40 Smith 22 24 34 a. How many alternatives are available? b. Obtain the optimal assignment using the Hungarian method. c. Suppose there was an additional project leader, Burton, who has the following times, 14, 28, 36. Should Burton be used? What is the new total time?d. Which project leader remains unassigned?arrow_forwardThe project described in the following table is scheduled to be completed in 11 weeks. Constructa network diagram using AOA or AON (see Example 5 for either type). Then answer the following questions:a. If you were the manager of this project, would you be concerned? Explain.b. If there is a penalty of $5,000 a week for each week the project is late, what is the probabilityof incurring a penalty of at least $5,000?Path ActivityEstimated Time(weeks)StandardDeviation (wks.)A C 4 0.70D 6 0.90B E 3 0.62F 9 1.90arrow_forward
- Hoosier Burger Juan Rodriquez has assigned you the task of requirements determination for the Hoosier Burger project. You are looking forward to this opportunity because it will allow you to meet and interact with Hoosier Burger employees. Besides interviewing Bob and Thelma Mellankamp, you decide to collect information from Hoosier Burger’s waiters, cooks, and customers. Mr. Rodriquez suggests that you formally interview Bob and Thelma Mellankamp and perhaps observe them performing their daily management tasks. You decide that the best way to collect requirements from the waiters and cooks is to interview and observe them. You realize that discussing the order-taking process with Hoosier Burger employees and then observing them in action will provide you with a better idea of where potential system improvements can be made. You also decide to prepare a questionnaire to distribute to Hoosier Burger customers. Because Hoosier Burger has a large customer base, it would be impossible to…arrow_forwardConsider a project for which the following activities and time estimates in weeks apply activity To tm tp 1-2 3 5 8 1-3 2 3 5 1-5 2 3 4 2-3 1 2 5 2-6 7 8 9 3-4 1 3 6 3-5 2 4 6 4-5 1 2 4 5-6 1 2 3 Draw the project network Compute the expected time and variance for each activity iii. Compute slack for each event and find the critical path Find the length of the critical path and the project duration Approximate the probability that activity 3 – 4 will have positive slack. What is the managerial implication of that probability?arrow_forwardUse the following information in a table about the activities of an information technology project of ABC Bank and solve the given questions. Activity Activity Predecessors Time Estimate/Duration (days) ES EF LS LF Slack time A B C D E F -- A A B B, C D, E 4 5 6 5 3 7 Draw a network diagram. List all the paths and their durations Find the critical path. Calculate early start, early finish, late start and late finish Calculate the slack time of each activityarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.