Managing Hard Rock’s Rockfest
At the Hard Rock Cafe, like many organizations, project management is a key planning tool. With Hard Rock’s constant growth in hotels and cafes, remodeling of existing cafes,
activities. For the first 3 months, Tomasso updates his Microsoft Project charts monthly. Then at the 6-month mark, he updates his progress weekly. At the 9-month mark, he checks and corrects his schedule twice a week.
Early in the project management process, Tomasso identifies 10 major tasks (called level-2 activities in a work breakdown structure, or WBS):† talent booking, ticketing, marketing/PR, online promotion, television, show production, travel, sponsorships, operations, and merchandising. Using a WBS, each of these is further divided into a series of subtasks. Table 3.8 identifies 26 of the major activities and subactivities, their immediate predecessors, and time estimates. Tomasso enters all these into the Microsoft Project software.‡ Tomasso alters the Microsoft Project document and the time line as the
“Without Microsoft Project." says Hard Rock Vice-President Chris Tomasso, “there is no way to keep so many people on the same page.” Tomasso is in charge of the Rockfest event, which is attended by well over 100,000 enthusiastic fans. The challenge is pulling it off within a tight 9-month planning horizon. As the event approaches, Tomasso devotes greater energy to its project progresses. “It’s okay to change it as long as you keep on track." he states.
The day of the rock concert itself is not the end of the project planning. “It’s nothing but surprises. A band not being able to get to the venue because of traffic jams is a surprise, but an ‘anticipated’ surprise. We had a helicopter on stand-by ready to fly the hand in," says Tomasso.
On completion of Rockfest in July. Tomasso and his team have a 3-month reprieve before starting the project planning process again.
†The level-1 activity is the Rockfest concert itself
‡There are actually 127 activities used by Tomasso; the list is abbreviated for this ease study.
TABLE 3.8 Some of the Major Activites and Subactivities in the Rockfest plan
2. Which activities have a slack time of 8 weeks or more?
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
- Show the project schedule by drawing Gant Chart in Microsoft excle for the given data:- (10) Activity Name Preceding activity Activity Time (Hours) B - 18 A B 8 C A,B 2 D A,C 6 E D 5 F C 9 G D,C 4 H F,G 11arrow_forwardProject involve doing something that has never done before with specific requirements like time, cost, and performance to be considered. Discuss.arrow_forwardThe managers at AllBirds have operations in multiple countries, which operate on different financial management systems. This has been increasingly challenging for the company, so the Justin is looking to consolidate and integrate the financial management across all locations into a single software system that can operate across the national boundaries. This is a new, complicated and lengthy project, so Justin has identified a set of activity categories that will need to be carefully managed, as noted in the table. What is the probability that project can be completed two months early?arrow_forward
- You lead a family day project for welcoming the arrival of the new students to the campus. The accompanying Table 1 shows the activities, times and sequences required for the project planning and monitoring. Table 1 Activities Immediate Predecessors Time (In Days) A -- 9 B A 5 C A 9 D B,C 6 E B, C 7 F D 10 G E 12 H F,G 8 Based on the Table 1, using Critical Path Method (CPM) diagram, determine the ES, EF, LS & LF, identify the critical activities, critical path and the expected project completion time.arrow_forwardQ3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagramarrow_forward1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION (in weeks)4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS5. WHEN WILL THE PROJECT BE COMPLETED? (Write in week)arrow_forward
- For the following Activity Tables, identify the critical path. Follow these steps: Step – 1: Construct a network diagram. Step – 2: Perform Forward and Backward pass (Early Start, Early Finish, Late Start, Late Finish) Step – 3: Determine Project Completion time. (from Critical Path) Step – 4: Calculate the float. (TOTAL FLOAT) Notes: 1. All duration are in terms of weeks.arrow_forwardOutline the steps involved in identifying the critical path of a project. Briefly describe each step 2. Listed below are tools used for project scheduling. Briefly describe each Time sheets Task lists Shared calendars Automated scheduling tools 3. Answer the following questions about work breakdown structures (WBS). Briefly explain what a WBS is. How does the WBS help determine project deliverables? How does the WBS help determine the sequence of activities on a project?arrow_forwardDevelop a CPM diagram for the activities/relationships listed below (assumedurations are in months). For each activity calculate the Early Start, Late Start, EarlyFinish, Late Finish, Total Float, and Free Float. Clearly identify the critical path forthe project (hint: a highlighter would be a good tool to use) How do you solve this? I don't understand how it's done.arrow_forward
- 1. When can the individual activities start and finish (at the earliest) if no delays occur? 2. Which are the critical bottleneck activities where any delays must be avoided to prevent delaying project completion? 3. For the other activities, how much delay can be tolerated without delaying project completion?arrow_forwardThe conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?arrow_forwardA senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. What is the minimum time required to finish the project? State the critical path. Activity Time (week) Immediate Predecessor A. Find client 4 --- B. Write prospectus 2 A C. Obtain approval from client and professor 3 B D. Complete programming 12 C E. Do industry background research 10 --- F. Write final paper 6 D, E G. Write oral report 5 D, Earrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.