Chapter 3, Problem 23P
a)
Summary Introduction
To determine:The probability of completing the project in 17 months.
Introduction:
The activity times of various tasks in a PERT project network are assumed to follow a probability distribution. For calculating the expected times and standard deviation, the parameters required are the following:
- Optimistic time: This is the time denoted by “a”, which is the best possible or in other words, the quickest time in which an activity can be completed, assuming that everything goes as per plan.
- Pessimistic time: This is the worst case scenario, where all the conditions are adverse or unfavorable. The maximum time which may be taken in such a situation is the pessimistic time denoted by “b”.
- Most likely time: The most realistic estimate of the time, denoted by “m” in normal conditions, is another parameter which is important in the computation of expected times and variances.
b)
Summary Introduction
To determine:The probability of completing the project in 20 months.
c)
Summary Introduction
To determine:The probability of completing the project in 23 months.
d)
Summary Introduction
To determine:The probability of completing the project in 25 months.
e)
Summary Introduction
To compute: The due date that yields a 95% chance of completion.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
11. Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is
24
months, and the project variance is
4.
Part 2
a) The probability that the project will be completed in
20 months = ______
(round your response to four decimal places)
Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeks
Chapter 3 Solutions
MyOMLab Principles of operations management : Sustainability and supply chain management (Book & eText Access Card)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - The Rover 6 is a new custom-designed sports car....Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 1CSCh. 3 - Prob. 2CSCh. 3 - Prob. 3CSCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Gabrielle Kramer, owner of Pet Paradise, is opening a newstore in Columbus, Ohio. Her major concern is the hiringof a manager and several associates who are animal lovers.She also has to coordinate the renovation of a building thatwas previously owned by a chic clothing store. Kramer hasgathered the data shown in Table 7.14. a. How long is the project expected to take?b. Suppose that Kramer has a personal goal of completingthe project in 14 weeks. What is the probability that it willhappen this quickly?arrow_forwardA project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)arrow_forwardThe following table describes project XYZ Duration Predecessor Variance A 5 2 B 3 A 1 C 13 A 6 D 18 B 2 E 10 B 4 F 4 D, E 1 G 11 C, E 5 H 9 F, G 2 I 2 H 1 Based on the information provided, perform the following tasks: Identify the crucial path and project duration Calculate probability that the project in going to be completed after the day 45arrow_forward
- Suppose the due date of the project is 24 months and expected time of completion is 28 months, while the probability of completing it is 90%. What will be the standard deviation?arrow_forwardThe project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistakearrow_forwardManagement Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)arrow_forward
- you decide to estimate duration and standard deviation of a project using PERT method. the project has 3 steps the following are the optimistic, most likely and pessimistic durations in weeks:step 1: 2,5,10Step 2: 1,3,13Step3: 7,8,11,what is the estimated duration and standard deviation of the project duration?Estimated Duration =16 standard Deviation =4.9Estimated Duration =18 standard Deviation =4.9Estimated Duration =18 standard Deviation =2.49Estimated Duration =16 standard Deviation =24arrow_forwardKimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.arrow_forwardI also know answer is d, but please explain each and every option why other option are incorrect too. Which of the following statements regarding PERT analysis is true? Each activity has two estimates of its duration. Project variance is the sum of all activity variances. Project standard deviation is the sum of all critical activity standard deviations. Only critical activities contribute to the project variance. none of these is true.arrow_forward
- Dan, the project manager, has indicated in a planning meeting that the team should identify and avoid any circumstances of ‘scope creep.’ What does Dan means? Select one: a. He does not want the team members to discuss the project scope with other project stakeholders b. He wants to be the only person responsible for scope management throughout the project duration c. He wants the team members to make any changes to the project scope that they deem necessary d. He does not want the continuous or uncontrolled growth and changes in the project's scope at any point after the project beginsarrow_forwardJordanne King, the project manager for Webjets International, Inc., compiled a table showing time estimates for each of the activities of a project to upgrade the company’s Web page, including optimistic, most likely, and pessimistic.a. Calculate the expected time, te, for each activity.b. Calculate the variance, s2, for each activity.Activity Optimistic (days) Most Likely (days) Pessimistic (days)A 3 8 19B 12 15 18C 2 6 16D 4 9 20E 1 4 7arrow_forwardConsider the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$ 361,504 −$ 16,050 1 28,700 5,368 2 51,000 8,456 3 53,000 14,000 4 423,000 9,699 Whichever project you choose, if any, you require a 6 percent return on your investment. a. What is the payback period for Project A? b. What is the payback period for Project B? c. What is the discounted payback period for Project A? d. What is the discounted payback period for Project B? e. What is the NPV for Project A? f. What is the NPV for Project B ? g. What is the IRR for Project A? h. What is the IRR for Project B? i. What is the profitability index for Project A? j. What is the profitability index for Project B?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY