Textbook Question
Chapter 3, Problem 9PA
Consider a four-step serial process with the number of workers at each step and processing times given in the following table.
Process Step | Number of Workers | Time per Customer (in Minutes) |
1 | 1 | 5 |
2 | 5 | 15 |
3 | 3 | 10 |
4 | 1 | 3 |
Assuming that the process starts out empty and is worker-paced, how long will it take (in minutes) to serve 20 customers? [LO3-5]
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Four employees at a fast-food restaurant each perform one of the four activities in
serving a customer: greet customer, take order, process order, and deliver order. The
processing time for each activity is given as follows:
Greet customer
Take order
Process order
Deliver order
A) 50%
Assume demand is unlimited. What is the average labor utilization?
B) 68%
C) 40%
Activity
D) 162%
Processing time per customer
2 seconds
30 seconds
60 seconds
5 seconds
PA 3-9 (Algo) Consider a four-step serial process with...
Consider a four-step serial process with the number of workers at each step and processing times given in the following table.
Time per Customer (in
Minutes)
5
14
6
3
Process Step
1
Number of Workers
1
Assuming that the process starts out empty and is worker-paced, how long will it take (in minutes) to serve 30 customers?
Note: Round to nearest minute.
Time taken
minutes
Cubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes taking order from the customer. After this, Tim prepares bread and Kim prepares filling for the order. These activities are performed in parallel, and take 6 and 12 minutes respectively. Jim then assembles the bread and filling, which takes 4 minutes of his time. Finally, Tim spends 1 minutes in delivering the order and taking payment. What is maximum number of sandwiches Cubway can make per hour? (In other words, what is the capacity of the process in sandwiches per hour?)
Chapter 3 Solutions
OPERATIONS MANAGEMENT LL W/CONNECT CODE
Ch. 3 - Prob. 1CQCh. 3 - Prob. 2CQCh. 3 - Prob. 3CQCh. 3 - Prob. 4CQCh. 3 - You observe a long line at the airport security....Ch. 3 - Prob. 6CQCh. 3 - What is the maximum utilization a resource can...Ch. 3 - Is the capacity of the bottleneck larger than,...Ch. 3 - Prob. 9CQCh. 3 - You observe a vehicle registration department at...
Ch. 3 - Prob. 1PACh. 3 - A community health systems nurse team consists of...Ch. 3 - Consider a process consisting of three resources....Ch. 3 - Prob. 4PACh. 3 - Prob. 5PACh. 3 - Prob. 6PACh. 3 - Prob. 7PACh. 3 - Consider a four-step serial process with...Ch. 3 - Consider a four-step serial process with the...Ch. 3 - Prob. 10PACh. 3 - Prob. 11PACh. 3 - Prob. 12PACh. 3 - The Tesla Model S, one of the most sought-after...Ch. 3 - The Tesla Model S, one of the most sought-after...Ch. 3 - The Tesla Model S, one of the most sought-after...Ch. 3 - The Tesla Model S, one of the most sought-after...
Additional Business Textbook Solutions
Find more solutions based on key concepts
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Operations Management
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
The Big Black Bird Company (BBBC) has a large order for special plastic-lined military uniforms to be used in a...
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (11th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- n a manufacturing process, a molded part spends 7 hours in inventory before being placed in a deburring machine, where the part is processed for 2 minutes. After deburring, the part spends 4 hours in inventory waiting for its turn on the polishing machine. The part then spends 7 minutes in polishing before waiting 6 hours in line to be painted. The part goes through a painting process that takes 7 minutes, then spends 11 hours in inventory before being shipped to the customer. What is the percentage of value-added time for the part?arrow_forwardA company assembles a product that consists of three pieces called AA, BB, and CC. The AA and BB parts are manufactured by the company itself, while the CC parts are purchased from another manufacturer. The process times, in hours, required for each piece in each of the processes are given in the following table: Process 1 Process 2 Process 3 Process 4 Process 5 AA 1 0.5 0.5 BB 1.5 0.5 0.5 0.5 The company has 20 machines that can carry out process 1, 5 process 2, 10 process 3, 5 process 4 and 5 process 5. Each machine works a maximum of five days each week at a rate of fifty weeks a year , in working days of 8 hours a day. Formulate and solve to determine the maximum number of assembled sets that you can produce.arrow_forwardA local bakery is renowned for its elaborately cecorated sheet cakes. Consider the following process information: One baker is ivailable to prepare the cake batter (measuring and mixing ingredients and then adding it to baking pans). On average, this takes 10 minutes to prepare two cakes, ie. to make enough batter for 2 cakes and to add the batter to 2 cake pans. Move time to add and remove them from the oven is neglig bile, it takes 32 minutes to bake cakes - the bakery has two ovens, each able to hold 2 cakes. The one pastry chef on staff puts on an amazing show that draws a crowd all day-each cake is decorated in 6 minutes. The bakery operates 8 hours per day. Answer each of the following questions: a. What is the cycle time (in minutes per cake) of each stage - preparing, baking, and decorating? b. What is the dally process capacity? Explain. c. If orders arrive at a rate of 3 cakes every 20 minutes, can the bakery meet the caily demand Explain, Note: Be clear about how you…arrow_forward
- Three employees at a fast-food restaurant each perform one of the three activities in serving a customer: take the order, process the order, and deliver the order. The processing time for each activity is given as follows: Activity Processing Time Take the order 30 seconds Process the order 2 minutes Deliver the order 1 minute Assume that the demand is 20 customers/hour. What is the average labor utilization? a 38.9% b 85.7% c 66.7% d 100%arrow_forwardDreamInflate is a balloon manufacturing company. Balloon manufacturing consists of seven work stations, each performing a single step as indicated in the table below. There are five workers manned for the seven work stations as shown. Assume the workers are paid $15 per Worker Task Sequence Processing Time (secs/balloon) Task Dye production Electrocharging Dipping (Cold and Hot) Mortar Dipping Balloon inflation and delaltexing Vulcanization Inspection/Testing 1 30 w1 20 3 35 W2 25 W3 30 W4 6. 45 W5 7 40 hour. Each balloon pack is sold for $6 and has a variable cost of $1. The company has fixed costs of $200 per hour. There is more demand than the overall production system can provide. Based on the information provided, answer the following questions: • What is the cost of direct labor for balloons? • How much profit does DreamInflate make every hour? (note that the cost of direct labor is also a variable cost). What would the profit of DreamInflate be if the variable costs were 10…arrow_forwardMr. K’s is a very popular hair salon. It offers high quality hairstyling andphysical relaxation services at a reasonable price, so it always has unlimiteddemand. The service process includes five activities that are conducted inthe sequence described below ( the time required for each activity is shownin parenthesis):Activity 1: Welcome a guest and offer homemade herb tea (10 minutes)Activity 2: Wash and condition har (10 minutes)Activity 3: Neck, shoulder, and back stress release massage (10 minutes)Activity 4: Design and hair style and do the hair (25 minutes)Activity 5: Ring up the guest bill (5 minutes)Each activity has one employee dedicated to it. For the following questions,assume unlimited demand. Also assume that the employee at activity 1 onlyadmits new guests at the rate of the bottleneck.(a) Which resource is the bottleneck?(b) What is the capacity of the process?(c) What is the flow rate?(d) What is the utilization of the employee at activity 3(e) What is the cycle time?arrow_forward
- A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the i nished product. Station 1 can process 2,700 units per month, station 2 can process 2,500/month, station 3 can process 2,300/month, and station 4 can process 2,100/month. What station sets the maximum possible output from this system? What is that maximum output number?arrow_forwardA manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the finished product. Station 1 can process 2,700 units per month, station 2 can process 2,500/month, station 3 can process 2,300/month, and station 4 can process 2,100/month. What station sets the maximum possible output from this system? What is that maximum output number?arrow_forwardPanini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. Demand (sandwiches per hour) are Grilled Vegetables = 25, Grilled Chicken = 15, and Pastrami = 10. There are up to five steps in the process of making sandwiches, listed below with processing times. Step Grilled Vegetables Grilled Chicken Pastrami Cut bread 0.75 minutes 0.75 minutes 0.75 minutes Grill 1.4 minutes 1.4 minutes Slice meat 3 minutes Toast 2 minutes 2 minutes 2 minutes Wrap 0.5 minutes 0.5 minutes 0.5 minutes Only 50 percent of customers want their sandwich toasted, no mattor which sandwich is ordered. Suppose Panini employs 1 worker at each step. Instructions: Round all answers to 1 decimal place. (a) What is the implied utilization of each of the five steps in this process? 62.5 % 93.3 % 50.이% 83.3 % 41.7 % Cut Grill Slice Toast Wrap (b) What is the actual and maximum flow rates of the three sandwich types? per hour Veg Chicken per hourarrow_forward
- Consider the following batch-flow process consisting of three process stepsperformed by three machines. Process steps step 1 step 2 step 3 processing time 0.25min./unit 0.20 min./unit 0.15 min./unit setup time 30 min 20 min 45 min Work is processed in batches at each step. Before a batch is processed at a step, the machine atthat step must be set up. (During a setup, the machine is unable to process any product.) Assumethat there is a dedicated setup operator for each machine (i.e., there is always someone availableto perform a setup at each machine.)a. What is the capacity of step 1 if the batch size is 35 parts?b. For what batch sizes is step 1 (2, 3) the bottleneck?arrow_forwardConsider a process consisting of five resources that are operated 8 hours per day. Theprocess works on three different products, A, B, and C: Demand for the three different products is as follows: product A, 40 units per day;product B, 50 units per day; and product C, 60 units per day.a. What is the bottleneck?b. What is the flow rate for each flow unit, assuming that demand must be served in the mixdescribed above (i.e., for every four units of A, there are five units of B and six units of C)?arrow_forwardPanini, a popular sandwich shop, offers 3 types of sandwiches: grilled vegetables, grilled chicken, and pastrami. Demand (sandwiches per hour) are Grilled Vegetables = 25, Grilled Chicken = 15, and Pastrami = 10. There are up to five steps in the process of making sandwiches, listed below with processing times. Step Grilled Vegetables Grilled Chicken Pastrami 0.75 minutes 0.75 minutes 0.75 minutes 0.75 minutes 1.4 minutes 1.4 minutes - - - - 3 minutes 3 minutes 2 minutes 2 minutes 2 minutes 2 minutes 0.5 minutes 0.5 minutes 0.5 minutes 0.5 minutes Only 50 percent of customers want their sandwich toasted, no matter which sandwich is ordered. Suppose Panini employs 1 worker at each step. Instructions: Round all answers to 1 decimal place. What is the implied utilization of each of the five steps in this process? Cut ____% Grill ____% Slice ____% Toast…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY