Chapter 4, Problem 4T

Explanation of Solution

Project Charter

Project Title:     Global Treps:

Project Start Date:    January 14, 2019    Projected Finish Date: June 14, 2019

Budget Information: $130,000

Project Manager: Jon Snow, (123)456-7890, jon@email.com

Project Objectives: Create Global Treps website and mobile application.

Main Project Success Criteria:

The project will take no more than six months to complete and not exceed a budget of $130,000.

Approach:

  • Complete all of the analysis and paperwork for the project in less than a week.
  • Have a detailed software development plan and scheduled dates for each phase of the plan.
  • Have the team ready for when the plan is approved
  • Ensure that the correct people are in the correct area based on their expertise and ensure that they know what the timeframe is that they need to have their part completed.
Assumption Log
Project: Global TrepsDate: 14/2/2019
IDCategoryAssumptionResponsibilityDue DateStatusActions
001DesignThe donation module is not accepting currencies other than dollars...

Blurred answer
Students have asked these similar questions
Create a Gantt Chart, assign resources and predecessors, save the Gantt chart as Project baseline, Identify the CPM and Critical Chain in your project.
Prepare and print a one-page cost model for the project, similar to the one provided in Figure 7-2. Use the following WBS, and be sure to document assumptions you make in preparing the cost model. Assume a labor rate of $100/hour for the project manager and $60/hour for other project team members. Assume that none of the work is outsourced, labor costs for users are not included, and there are no additional hardware costs. The total estimate should be $200,000. 1. Project management 2. Requirements definition
Gantt chart is widely used to illustrate the planning and scheduling of a project. Show a common use of Gantt Chart in a project of your choice from inception to commissioning.
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Information Technology Project Management
Computer Science
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781285867168
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,