Information Technology Project Management
Information Technology Project Management
9th Edition
ISBN: 9781337101356
Author: Kathy Schwalbe
Publisher: Cengage Learning
Expert Solution & Answer
Book Icon
Chapter 4, Problem 5QQ
Program Description Answer

“20 percent” is derived as the estimated return on investment (ROI) if, the total discounted benefits is $120,000 and a total discounted cost is $100,000.

Hence, the correct answer is option “C”.

Blurred answer
Students have asked these similar questions
Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 What is the cost variance, schedule variance, cost performance index (CPI), and scheduleperformance index (SPI) for the project? How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? Use the schedule performance index (SPI) to estimate how long it will take to finish this project. Sketch the earned value chart based for this project, using Figure 7-5 as a guide.
Given the following information for a one year project, address the following queries:  Planned Value PV = $2300  Earned Value EV  = $2000  Actual cost AC     = $2500  Budget at completion BAC = $12000 Formulas are given below. Hint: Chapter 7, Page 312 to 316 of your ref book (IT Project Management by kathy) What is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project. How is the project doing? Is it ahead of schedule or behind the schedule? Is it under budget or over budget? Use the CPI to calculate the estimate at completion EAC for the project. Is the project performance better or worse than planned? Use the SPI to identify how long it will take to finish. Draw the earned value chart for this project. Sample is given below.
Consider the following information about a project: Project Year 0 Year 1 Year 2 Year 3 Year 4 Costs $160,000 $43,000 $50,000 $50,000 $64,000 Benefits $0 $400,000 $400, 000 $500,000 $500,000 A ) Calculate the NPV assuming 10% discount rate          B ) Determine in which year will be the payback                                    C ) Calculate (ROI)?
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Principles of Information Security (MindTap Cours...
Computer Science
ISBN:9781337102063
Author:Michael E. Whitman, Herbert J. Mattord
Publisher:Cengage Learning